SCHOOL BUILDINGS STATUS &
ACCOMPLISHMENTS
Presented by:
ROLANDO M. PACURIBOTActing City Engineer
5/22/2018 Report School Board
2/36
ON
-
GOING PROJECTS
16 CL 3-STOREY (COVERED ROOFDECK)
Balulang National High School Building
16 CL 3-STOREY (COVERED ROOFDECK) Macasandig National High School Building
16 CL 3-STOREY (COVERED ROOFDECK) Tablon National High School Building
10 CL 3-STOREY (COVERED ROOFDECK) Camaman-an Elementary School Building
16 CL 3-STOREY (COVERED ROOFDECK) Pagatpat Elementary School Building
21 CL 3-STOREY with Roofdeck P.N. Roa Elementary School Building
8 CL 3-STOREY (COVERED ROOFDECK) Pagatpat National High School Building
8 CL 1-STOREY Dansolihon National High School Building
3 CL 1-STOREY Man-ai National High School Building
6 CL 1-STOREY Tumpagon National High School Building
6 CL 1-STOREY Tuburan National High School Building
5/22/2018 Report School Board
3/36
16 Classroom 3
-
Storey (Covered
Roofdeck
)Balulang
National High School (Phase I)
Contract Amount: 14,494,741.70Date Started: April 25,2014Actual Accomplishment: 68.00%
G i k a n s a K a t a w h a n , I b a l i k s a K a t a w h a n
5/22/2018 Report School Board
4/36
5/22/2018 Report School Board
5/36
5/22/2018 Report School Board
6/36
16 Classroom 3
-
Storey (Covered
Roofdeck
)Macasandig
National High School (Phase I)
Contract Amount: 14,494,061.77Date Started: June 17, 2014Actual Accomplishment: 10.60%
G i k a n s a K a t a w h a n , I b a l i k s a K a t a w h a n
5/22/2018 Report School Board
7/36
5/22/2018 Report School Board
8/36
5/22/2018 Report School Board
9/36
16 Classroom 3-Storey (Covered Roofdeck)Tablon National High School (Phase I)
Contract Amount: 14,451,175.88Date Started: June 2, 2014Actual Accomplishment: 5.00%
G i k a n s a K a t a w h a n , I b a l i k s a K a t a w h a n
5/22/2018 Report School Board
10/36
5/22/2018 Report School Board
11/36
10 Classroom 3-Storey (Covered Roofdeck)Camaman-an Elementary School Building
(Phase I)Contract Amount: 9,194,173.87Date Started: June 16, 2014Actual Accomplishment: 30.00%
G i k a n s a K a t a w h a n , I b a l i k s a K a t a w h a n
5/22/2018 Report School Board
12/36
5/22/2018 Report School Board
13/36
5/22/2018 Report School Board
14/36
5/22/2018 Report School Board
15/36
21 Classroom 3-Storey with Covered RoofdeckP.N. Roa Sr. Elementary School Building
Contract Amount: 25,338,965.05Date Started: June 5, 2014Actual Accomplishment: 25.00%
G i k a n s a K a t a w h a n , I b a l i k s a K a t a w h a n
5/22/2018 Report School Board
16/36
5/22/2018 Report School Board
17/36
5/22/2018 Report School Board
18/36
5/22/2018 Report School Board
19/36
8 Classroom 1-StoreyDansolihon National High School Building
Contract Amount: 7,197,202.94Date Started: June 19, 2014Actual Accomplishment: 10.00%
G i k a n s a K a t a w h a n , I b a l i k s a K a t a w h a n
5/22/2018 Report School Board
20/36
5/22/2018 Report School Board
21/36
5/22/2018 Report School Board
22/36
8 Classroom 3-Storey (Covered Roofdeck)Pagatpat National High School Building
Contract Amount: 11,195,144.70Date Started: June 19, 2014Actual Accomplishment: 10.00%
G i k a n s a K a t a w h a n , I b a l i k s a K a t a w h a n
5/22/2018 Report School Board
23/36
5/22/2018 Report School Board
24/36
5/22/2018 Report School Board
25/36
16 Classroom 3-Storey (Covered Roofdeck)Pagatpat Elementary School Building
Contract Amount: 19,870,810.32Date Started: June 19, 2014Actual Accomplishment: 2.00%
G i k a n s a K a t a w h a n , I b a l i k s a K a t a w h a n
5/22/2018 Report School Board
26/36
5/22/2018 Report School Board
27/36
3 Classroom 1-StoreyMan-ai National High School Building
Contract Amount: 2,847,627.75Date Started: June 19, 2014Actual Accomplishment: 19.52%
G i k a n s a K a t a w h a n , I b a l i k s a K a t a w h a n
5/22/2018 Report School Board
28/36
5/22/2018 Report School Board
29/36
5/22/2018 Report School Board
30/36
6 Classroom 1-StoreyTuburan National High School Building
Contract Amount: 5,488,839.99Date Started: June 17,2014Actual Accomplishment: 2.00%
G i k a n s a K a t a w h a n , I b a l i k s a K a t a w h a n
5/22/2018 Report School Board
31/36
5/22/2018 Report School Board
32/36
6 Classroom 1-StoreyTumpagon National High School Building
Contract Amount: 5,488,839.99Date Started: June 17, 2014Actual Accomplishment: 60.80%
G i k a n s a K a t a w h a n , I b a l i k s a K a t a w h a n
5/22/2018 Report School Board
33/36
5/22/2018 Report School Board
34/36
Projects for CAF Issuance:
Proposed 6 CL 2-Storey Macasandig National High SchoolABC: 7,000,000.00
Projects for Bidding:
Proposed 39 CL 3-Storey (Covered Roofdeck) Gusa National HighSchool
ABC: 51,244,863.29
Proposed 14 CL 2-Storey Fr. Masterson Elementary School
ABC: 15,099,106.90
Proposed 40 CL 2-Storey (2-Buildings) Bugo National High SchoolABC: 41,682,890.99
5/22/2018 Report School Board
35/36
Summary of Accomplishments:
On Going 126 Classrooms
For Bidding 6 Classrooms
For CAF Issuance 93 Classrooms
TOTAL 225 Classrooms
Total Contracted Amount = Php. 130,061,583.96CAF Issued = Php. 153, 261,583.96