Scenario 2:- Capitalization of Asset under ConstructionABB is one of the biggest transformer manufacturers in the world. Over the past few years, theirfocus has been to increase their dominance in India. For the same, they have decided to increase
their manpower capacities and also their infrastructure to accommodate the resources. The
management has decided to construct a building consisting of 3 wings. The duration of building
each wing is 2months and they want to capitalize each wing on completion.
You are required to create the building as an asset and capitalize each wing as it is completed using
Asset under Construction facility in SAP. Depreciation calculated for the year should also take
into consideration the capitalization date for the wings.Creation of Company
Creation of Fiscal Year Variant AB & Assigning to Company Code ABU
8/8/2019 Ravi Scenario Presentation
2/23
Posting Period Variant Created ABB
Open & Close Posting Periods
Posting Period Variant Assigned to Company Code ABU
Field Status Variant ABB
Tolerance Group for Employees
8/8/2019 Ravi Scenario Presentation
3/23
Tolerance for G/L Accounts
Tolerance for Vendors
8/8/2019 Ravi Scenario Presentation
4/23
Chart of Accounts ABB
Define Retained Earnings Account
Creation of G/L Master
8/8/2019 Ravi Scenario Presentation
5/23
Creation of Vendor Account Group ABB
Creation of Vendor Master 8000000005
8/8/2019 Ravi Scenario Presentation
6/23
Asset Configuration
Copy Reference Chart of Depreciation 1IN to ABC
8/8/2019 Ravi Scenario Presentation
7/23
Copy/Delete Depreciation Areas
Assign Input Tax Indicator for Non-Taxable AcquisitionsTax Code for Input V0
Tax Code for Output A0
Assign Chart of Depreciation to Company Code ABU
Account Determination600000 Buildings
40000 AUC
8/8/2019 Ravi Scenario Presentation
8/23
Screen Layout Rules for Assets
1100 Buildings
4000 AUC
Number Ranges for Asset Master
8/8/2019 Ravi Scenario Presentation
9/23
Asset Classes
600000 Buildings
AUCABB AUC
8/8/2019 Ravi Scenario Presentation
10/23
Integration with G/L
Balance Sheet Accounts
Depreciation Accounts
Specify Financial Statement Version for Asset Reports ABB
Define Base Method for Depreciation 0012
8/8/2019 Ravi Scenario Presentation
11/23
Define Multi Level Method
Define Period Control Method
Maintain Depreciation Key and Activate
8/8/2019 Ravi Scenario Presentation
12/23
Document Types for Asset
Maintain Controlling Area
Assigning Company Code to Controlling Area
8/8/2019 Ravi Scenario Presentation
13/23
Define Settlement Profile
Assign Settlement Profile to Company
Creation and Assigning of Settlement Number Range to Controlling Area
8/8/2019 Ravi Scenario Presentation
14/23
Master, Transactions & Reports
1. Creation of AUC Master
2. Creation of Main Asset Building for Hotel
8/8/2019 Ravi Scenario Presentation
15/23
3. Creation of Sub-Asset Hotel Wing A
4. Posting Values to AUC F-90
Press Enter - Next Screen
8/8/2019 Ravi Scenario Presentation
16/23
4. Settlement of AUC - AIAB
8/8/2019 Ravi Scenario Presentation
17/23
Click on Save
Settlement (AIBU)
8/8/2019 Ravi Scenario Presentation
18/23
Depreciation Run AFAB
Log for Posting Run
8/8/2019 Ravi Scenario Presentation
19/23
Reports
1. Asset Explorer AW01N for Building Wing A
8/8/2019 Ravi Scenario Presentation
20/23
Wing B
8/8/2019 Ravi Scenario Presentation
21/23
2. Report for the Main Asset S_ALR_87011978
3. Report for Asset transactions S_ALR_87012048
8/8/2019 Ravi Scenario Presentation
22/23
4. Current Year Depreciation figures S_ALR_87012035
5. G/L Line Item Wise Report FBL3N
For Depreciation Expense
For Main Asset G/L Account
8/8/2019 Ravi Scenario Presentation
23/23
6. G/L Summary Report FS10N