Public Workshop #5

Post on 21-Jan-2015

199 views 0 download

Tags:

description

 

Transcript of Public Workshop #5

Public Workshop #5 Public Workshop #5 July 20, 2011

Meeting AgendaMeeting Agenda

6:00 – 6:30 Visit Stations

6:30 – 7:00 Presentation

7:00 – 7:30 Group Session(Fill out Workbooks)

7:30 – 8:00 Comment on Cross Sections andIntersection Treatment

2

Presentation OutlinePresentation Outline

Project Recap

Review of Concept Development Process

3 Most Promising Alternatives

Technical Evaluation of Alternatives

Streetscape Sections

Intersection Treatment Options

Next Steps

3

Project Background VideoProject Background Video4

Project Website / Virtual Workshop (http://172nd.com)Project Website / Virtual Workshop (http://172nd.com)

5

Project PurposeProject Purpose

Address corridor congestion and safety problems Serve future north-south trafficServe expected population growth in the area– Damascus – Happy Valley – Pleasant Valley Plan area – Gresham

Serve the growing demand for regional travel

7

Alternatives Development ProcessAlternatives Development Process

Summary of Public WorkshopsSummary of Public Workshops8

Alternative AT2Alternative AT29

Alternative AT6Alternative AT610

Alternative AS10AAlternative AS10A11

8.1 – Transportation Analysis of Alternatives8.1 – Transportation Analysis of AlternativesBased on Metro’s current 2035 land use assumptions. Operations with new Metro assumptions are expected to be betterRange forecasts to be performed in conjunction with the Preferred Build Alternative

8.1 – Transportation Analysis of Alternatives 8.1 – Transportation Analysis of Alternatives

* 5 lanes near Sunnyside Road

Concept Roadway Required Cross Section

AT2, AT6 172nd -190th Corridor 5 Lanes

AS10a 172nd Ave 3 Lanes*

AS10a Foster-190th Corridor 5 Lanes

All 172nd Ave (North of 172nd-190th Connector)

3-5 Lanes

All Hemrick Rd 3 Lanes

All Cheldelin Rd 3 Lanes

Alternative AT2Alternative AT214

Alternative AT6Alternative AT615

Alternative AS10AAlternative AS10A16

Alternative AS10A – Relies on Planned Foster Road ExtensionAlternative AS10A – Relies on Planned Foster Road Extension

17

Foster Extension

Foster Road Extension – Damascus Draft TSPFoster Road Extension – Damascus Draft TSP18

Sunnyside Rd

Vogel Rd

Foste

r Rd

18

7th A

ve

Hwy 212

172nd Avenue Frontage Road Concept(All Alternatives)172nd Avenue Frontage Road Concept(All Alternatives)

19

172nd Ave

Fu

ture

Road

Hag

en

Rd

Trog

e R

d

Frontage Road

North

Recently Completed Technical AnalysisRecently Completed Technical Analysis

Environmental– Biological Resources– Wetlands– Historical/Cultural– Hazardous Materials– Soils– Air Quality– Noise

Transportation– Transportation Analysis of Alternatives– Conceptual Level Design and Cost Estimates

Preliminary Cost EstimatesPreliminary Cost Estimates

Total costs (Public Project Scenario)– AT2 - $156 Million– AT6 - $154 Million– AS10a - $138 Million

Public costs likely less due to development related right-of-way dedications and roadway construction.

Technical Evaluation ResultsTechnical Evaluation Results

EVALUATION CRITERIA AT2 AT6 AS10A

Vehicular Mobility +1.5 +1.5 +1.5

Multi-Modal Mobility +1 +1 +1

Local Access +0.5 +0.5 +0.5

Multi-Modal Safety +1 +1 +1.67

Impacts to Natural Environment +0.33 -0.67 +1.33

Impacts to Built Environment -0.67 -1.33 -0.33

Land Use Compatibility +1.5 -0.5 +1

Flexibility of Implementation +0.5 0 +0.5

Cost 0 0 +1

Aesthetic Character +0.33 +2 -0.33

Environmental Enhancement 0 0 0

Maintenance +0.5 +0.5 +0.5

Functionality +2 +2 +1.5

TOTAL SCORE 8.49 6.00 9.84

22

Initial Consultant Team RecommendationsInitial Consultant Team Recommendations

Alternative AS10a– Meets the Purpose and Need– Scores above the other alternatives based on the goals,

objectives, and evaluation criteria– Lowest cost of the 3 most promising alternatives– Highest approval rating from public participants to date

Things to Consider– Need to construct 5-lanes on Foster within the horizon year

- Dependent on Widening of 190th Drive and Extension of 187th

Initial Streetscape AssumptionsInitial Streetscape Assumptions

Cycle Track ConceptCycle Track Concept

Source: NACTO Urban Bikeway Design Guide(National Association of City Transportation Officials, 2011)

25

Example Streetscape PhotosExample Streetscape Photos26

Sunnyside Road, Happy Valley

Intersection Treatment OptionsIntersection Treatment Options

Traffic Signal Roundabout

27

Initial Project Team RecommendationInitial Project Team Recommendation

Use roundabouts where feasible.

– Safety Benefits

– Environmental Benefits

– Pedestrian Friendly

– Access Management

– Aesthetics

28

Upcoming MeetingsUpcoming Meetings

Virtual Open House (Open until 7/22)

Project Advisory Committee Meeting (7/27)

Clackamas Transportation Advisory Committee Meeting (8/23)

Project Management Team Meeting (8/4) Final selection of Preferred Build Alternative

29

30

Upcoming Public HearingsUpcoming Public Hearings

Winter 2011/12 – Damascus Planning Commission– Happy Valley Planning Commission– Damascus City Council– Happy Valley City Council– Board of County Commissioners

Let’s Get Your InputLet’s Get Your Input

Review Posters for Alignment Concepts

– Future Land Use/Environmental Constraints

– Evaluation Scores

Use “Notes” Section of Your Handout to Provide Feedback

Today’s Goals are to:

1) Select the Preferred Build Alternative

2) Provide Suggested Refinements to the Preferred Build Alternative

How to fill out your workbookHow to fill out your workbook32

How to fill out your workbookHow to fill out your workbook33

Yes

No

No

1

3

2

Your comments here.

Completing the WorkbookCompleting the Workbook34

Your comments here.

Thanks!Thanks!