Project Factsheet – Tan Kwai Tsuen North Fresh Water Service Reservoir, Yuen Long

Page 1 of 2 Tan Kwai Tsuen North Fresh Water Service Reservoir, Yuen Long

Project: Tan Kwai Tsuen North Fresh Water Service Reservoir, Yuen Long

Original Contract Sum: HK$200 million

Contract Start Date: June 1998

Contract Completion Date: November 2002

Client: Water Supplies Department

Project Factsheet – Tan Kwai Tsuen North Fresh Water Service Reservoir, Yuen Long

Page 2 of 2 Tan Kwai Tsuen North Fresh Water Service Reservoir, Yuen Long

Description:

Site formation for the service reservoir, resulting in an excavation of roughly 231,700m3 and platform extension using approx.

81,500m3 of excavated hard material. Construction of a covered reinforced concrete service reservoir comprising two compartments

of nominal total capacity 80,000m3. Construction of 6m dia. tunnel using drill and blasting method.