Presentation Parkside Pedestrian Bridge Project Update Meeting 2

Post on 20-Apr-2015

363 views 0 download

Transcript of Presentation Parkside Pedestrian Bridge Project Update Meeting 2

Parkside Pedestrian BridgeDesign Update Public Meeting 2May 24, 2012

1

2

DDOT IPMA Team 4/AWIProject Team

• Dawit Muluneh, Program Manager, DDOT Team 4

• Todd Springer, Project Manager, CH2M HILL, AWI

• Bryon Johnston, Public Information Manager, Stratacomm, AWI

May 24, 2012

3

How We Got Here 2005 – Parkside Neighborhood Design Developed with

Concept for New Pedestrian Bridge

2007 – Bridge Conceptual Design Competition Winner Selected by Anacostia Waterfront Corporation AWC)

2007 – Bridge incorporated into Parkside Master Plan in Stage 1 PUD and Approval

2007 – AWC Dissolved and Project Transitioned to Deputy Mayors Office for Planning and Economic Development (DMPED)

2008 – DDOT Re-evaluated Design Concepts

2011 – Began Preliminary Design, Incorporating 2008 Design Concepts

2011 – Current Design Alignment Presentation at the Parkside Civic Association Meeting

2012 – Design Progress Up to Tonight’s Public Meeting

May 24, 2012

4

Project Objectives

New Pedestrian Bridge

Direct Connectivity Between

West: Mayfair and Parkside Communities

East: Deanwood Community, Minnesota Avenue Metro Station/Bus Transfer Station, Downtown Ward 7

Disabled Accessible/ADA compliant ramps

Safety Enhancement Increased Visibility New Lighting Security Cameras

May 24, 2012

5

Project Area

WMATATracks

WMATA Bus Transfer

Station

Overhead PEPCOTransmission Lines

Parkside Development

May 24, 2012

6

Aerial View of Bridge

May 24, 2012

7

Looking South at Bridge

To MinnesotaAvenue

To KenilworthTerrace

CSX Tracks

WMATATracks

DC 295

May 24, 2012

8

Bridge AccessFrom Minnesota Avenue

To MinnesotaAvenue Metro Station

WMATA Bus Transfer Station

May 24, 2012

9

Bridge Access from Kenilworth Terrace

To Kenilworth Terrace

May 24, 2012

10

View from Kenilworth TerraceToward Bridge

May 24, 2012

11

Walking Through the Bridge

May 24, 2012

12

Sustainable Design Features

Goal: Reduce Long-term Maintenance, Repairs and Costs

Standing Seam Metal Roof

Weathering Steel Truss/Arches

Low-maintenance Deck

May 24, 2012

Sample Bridge

13

Project Coordination & Challenges District Department of Transportation (DDOT)

Bridge crosses above DC 295 and Kenilworth Avenue Service Drive

City Interests Contributing 25 percent, up to $3 million, toward the cost of the bridge

Providing 45-foot-wide easement for bridge access at Kenilworth Terrace

CSX Bridge crosses above CSXT tracks and construction work will occur

within area of tracks with equipment crossing them

PEPCO PEPCO power transmission lines above the bridge need to be raised

Washington Area Transit Authority (WMATA) Bridge crosses above WMATA tracks and station service building

Bridge access at Minnesota Avenue will be within the Minnesota Avenue Bus Transfer Station area

May 24, 2012

14

Project Area

WMATATracks

WMATA Bus Transfer

Station

Overhead PEPCOTransmission Lines

Parkside Development Easement

May 24, 2012

15

Project Next Steps

Complete Preliminary Late Summer 2012Design

Next Public Meeting Fall 2012

Begin Construction/ Fall 2012Utility Relocation

Anticipated Bridge 2014 *Construction Completion

* Dependent upon funding and coordination with CSXT, PEPCO, WMATA

May 24, 2012

Presenter
Presentation Notes
The Parkside Pedestrian Bridge will provide safe, well-lit, disabilities-accessible pedestrian and bicycle travel between neighborhoods and a local Metro station now separated by DC 295 and two sets of railroad tracks just north of the Benning Road interchange. Specifically, the bridge will more directly and safely connect the Mayfair neighborhood and proposed Parkside development to its west with the Minnesota Avenue Metro and Bus Transfer Stations, Downtown Ward 7 and the Deanwood Community to its east. Currently under design, the bridge will be 400-feet-long with three spans, arches at each end, a metal roof, and a 10-foot-wide concrete deck. Sides of the bridge will be enclosed with fencing to prevent the throwing of objects onto the roadway or tracks below. The bridge is currently under design and we anticipated starting construction late this year. The project is anticipated to cost $13 million, with 25 percent or up to $3 million coming from the developer of the new Parkside development where the bridge’s western touchdown point will be.

16

Staying Involved

• For more information: www.anacostiawaterfront.org/ParksidePedestrianBridge

• Receive project updates, ask questions or comment: Sign up tonight for the project email list Email: ddot.awi@dc.gov Call: 202-741-8528

May 24, 2012

17

Questions?

May 24, 2012