Project ManagementE&C Projects Phases

 Prof. Mauro Mancini

e-mail: Mauro.Mancini@polimi.it

ph.: +39-02-23994057

POLITECNICO DI MILANODepartment of Management, Economics and Industrial Engineering

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 2/36

Plant’s Projects Phases

engineering

PLANNING/CONTROL

OPERATING

2

start-up/testing

construction/assembly

procurement

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 3/36

Plant’s Projects Phases

PHASE RATIONALE

Base EngineeringSystems (functional units of the

plant)

 

3

e a e ng neer ng pec a s sc p nes

Procurement Product classes

Construction/Assembly Work’s processes/physical areas

Start-up/testing Systems

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 4/36

Plant’s Projects Phases

Base

Engineering

Detailed

EngineeringFUNCIONAL

SPECIFICATIONS

CONSTRUCTIVE 

DESIGN 

SUPPLIERDATAPURCHASE

SPECIFICATIONS

4

MATERIALS

Start-up/

Testing

Construction

/Assembly

Procurement

CONSTRUCTIVE 

MODIFICATIONS

FUNCTIONALPERFORMANCE

TESTING

SYSTEMS

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 5/36

Engineering Phase

Elaborating engineering of a plant means todefine coherently, with an increasing level

,plant sub-systems (primary and auxiliary)

and the relative integration ways

5

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 6/36

Engineering Phase

Base Engineering

SYSTEMIC APPROACH

Detailed Engineering

ENGINEERING DISCIPLINE APPROACH

6

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 7/36

Engineering Phase

Base Engineering

From requirements (functional, performance, technological,constructive) indicated from the customer, until the

complete definition of the plant (articulated in primary

7

PRIMARY SYSTEM

SECONDARY

SYSTEM:

Instrumentatio

n and control

SECONDARY

SYSTEM:

Electric Power

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 8/36

Engineering Phase

Base Engineering

  project requirements’ analysis•   technological process choice

•   plant collocation

•   lant confi uration and its articulation in sub-s stems

•   automation level definition•   sub-systems characteristics definition

•   layout definition

•   health, security and environmental impact matters analysis

•   operating management politics definition

•   design criteria and constraints for detailed engineering definition

8

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 9/36

Engineering Phase

Block Diagram

Process FlowDiagram

Material Balance

Overall Layout

Detailed Layout

Buried Network

Equipment List

Data Sheet

9

ner e c a ance

Process &

Instrument Diagram

PID mechanized

Aerial Network

PROCESS

LAYOUT 

COMPONENTS

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 10/36

Engineering Phase

Detailed Engineering

Multidisciplinary activity through which technicalspecification of plant components and relative ways of 

installations are defined, on the basis of prefixed

10

(material take-off ) and to define ways of  construction/assembly (sketches)

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 11/36

Engineering Phase

Detailed Engineering

Front End Engineering

Engineering for Requisitioning and Procurement

11

Engineering for Construction/Assembly

Engineering during Construction

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 12/36

Engineering Phase

Detailed Engineering

Front End Engineering  task is to define design choicefundamental for each specialist discipline, coherently

with base engineering, to start supply campaign

12

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 13/36

Engineering Phase

Detailed Engineering

Engineering for Requisitioning and Procurementdevelops through the following:

•  formulation of technical specifications for Request for

13

•   formulation of technical opinions on offers coming

from suppliers;

•   control and approval of technical documentation

coming from selected supplier

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 14/36

Engineering Phase

 Technical documents

•   to specify technical characteristics of a

plant/component•   to specify ways of construction, assembly, testing,

exercise, maintenance

14

absolving, authorizations, etc.

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 15/36

Engineering Phase

 Technical documents Life-Cycle

1. planning2. elaboration

3. filing

15

4. transmission (if the document is used during theproject in progress)

5. research and rendering (if the document is used in

other projects)

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 16/36

Engineering Phase

16

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 17/36

Procurement Phase

Site Logistics

Product Support Logistics

a er a s og s cs

17

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 18/36

Procurement Phase

Materials logistics can be divided in:

Materials Management   to guarantee the

presence of materials on site

18

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 19/36

Procurement Phase

Procurement

Supplied materials:

• construction materials;

• p an componen s;

• consumption materials;

• operating means and advices.

19

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 20/36

Procurement Phase

Procurement

Vendor List

20

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 21/36

Procurement Phase

Procurement Phases1. Emission of “Purchase Specification” (from Engineering and

Procurement);2. Emission of “Inquiry for Bid” (from Procurement and supplier

inserted in vendor list);

Engineering);4. Economic tabulation of received proposals (from

Procurement);

5. Emission of “Inquiry for Purchase” (from Engineering);

6. Order emission (from Procurement);7. Final approval of supplier technical documentation (from

Engineering).

21

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 22/36

Procurement Phase

Materials Management

Expediting

Inspecting and testing

TransportsReception/storing/handling of materials in

site

22

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 23/36

Procurement Phase

Expediting

This phase guarantees the control of 

milestones corresponding to the right

progress of the project

Aims to obtain from the supplier information

about:

• furniture progress• technical documentation development

• completion of foreseen testing

23

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 24/36

Procurement Phase

Expediting Activities•   reunions among order manager, supplier and

corporate functions interested•  detailed exam of the order, identifying uncertainty

areas that could determine delivery delay

•  control milestones definition and interventionsfrequency between them

•   actions of reminder (visits, phone calls, meetings)

  expediting report, sent to corporate functions

24

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 25/36

Procurement Phase

Expediting ActivitiesMaterials Statur Report

•  material description

•   number of purchase specification

•   supplier

•  number of order

•   planned, foreseen and actual date of completion

•   planned, foreseen and actual date of testing

•  way of testing

25

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 26/36

Procurement Phase

Expediting ActivitiesMaterials Statur Report

•   planned, foreseen and actual date of free factoryrendering

•  wa of shi ment and carrier

•   planned, foreseen and actual date of shipment•   planned, foreseen and actual date of delivery to the

site

•  corresponding activity of construction/assembly

•   planned and foreseen date of activities execution

•   date for which materials availability on site is

required26

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 27/36

Procurement Phase

Transports

Transport Plan

• ways of transport

• paths

 contract typology (for example “door todoor”)

• carrier

• charges• packaging

• delivery dates

27

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 28/36

Procurement Phase

Transports

Delivery documents are very important from a

contractual point of view because theyactivate payment share from the customer

28

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 29/36

Procurement Phase

Inspecting and Testing Activities

• participation to technical qualification of 

suppliers

• verification of suppliers’ quality warranty

• technical supervision through inspections

aimed to verify conformance of materials,

processes, construction methodologies, and

order specifications.

29

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 30/36

Procurement Phase

Inspecting and Testing Activities

The level of supervision depends on

supplied components characteristics and

on quality level of the plant that have to

be realized

30

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 31/36

Procurement Phase

Inspecting and Testing Activities

1) PRODUCT CATEGORIES

1 – realized on demand on supplier’s engineering

2 – realized on demand on E&C society’s engineering

 –

2) QUALITY CATEGORIES OF PLANTS/SYSTEMS

1 – particularly high2 – high

3 – normal

31

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 32/36

Procurement Phase

Inspecting and Testing Activities

Supervision Levels:

– inspection during furniture and presence

during testing (intermediate and final) at

– only presence during testing (intermediate and

final) at suppliers’

– acceptance of materials on the basis of documents (without presence during testing)

32

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 33/36

Construction/Assembly Phase

Collocated at the end of detailed

engineering (that provides technical

documents) and procurement (thatguarantees availability of materials to

ns a , an prece es s ar -up an

testing phases, where technical

performance of the plant are verified

33

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 34/36

Construction/Assembly Phase

Aspects to consider : changes in scope of work

materials amount revision

site logistics and transport and communication

infrastructure

activities programming and temporal profile of resources’ utilization

availability of technical documents and materials on

site contractual constraints

plan of security on site

problems from operating in strangers countries

34

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 35/36

Construction/Assembly Phase

Specialist work processes constructive

sequence

Constructive area/draft/cubeCrossing assembly processes and constructive

phase is obtained

Subcontracts

35

8/14/2019 PM6 - CO10 - EC Project Phase.pdf

http://slidepdf.com/reader/full/pm6-co10-ec-project-phasepdf 36/36

Construction/Assembly Phase

Constructive area approach

 

Materials may be installed:

• per area and per system (e.g. piping)

• per area (e.g. conduits)

• per system (e.g. cables)

36