Coal-fired Power Plant 2 x 22 MW

Galang Batang – Bintan - Indonesia

Date : 02MAY2012 Prepared by : Werner S.

Approved by : WS File Name : PIC 01/0512

P T C T I I n d o n e s i a P i c t u r e s d u r i n g C o n s t r u c t i o n

Page 1 of 2

Steel Structures of Turbine House (left) & Boiler

House (right) Front View STG 1788 GEC-ALSTOM – on Foundation,

Turbine type: C24L/E60/12.5 Straight Condensing

Side View STG 1788 GEC - ALSTOM Best View STG 1788 GEC-ALSTOM, waiting for next

process alignment

Follow up, check every progress and make sure that

everything goes according to the project plan. Every mistake caused increasing project cost and

extending project schedule and everybody will not happy working under pressure.

Coal-fired Power Plant 2 x 22 MW

Galang Batang – Bintan - Indonesia

Date : 02MAY2012 Prepared by : Werner S.

Approved by : WS File Name : PIC 01/0512

P T C T I I n d o n e s i a P i c t u r e s d u r i n g C o n s t r u c t i o n

Page 2 of 2

Boiler House Steel Structuring, Roofing, Side wall structure and reinforcement. Guest House, Meeting Room and Guard house are basically ready to use (picture at bottom right),

still waiting for finishing touch and Office furniture.