LEONEL LIMA PONCEPratt Institute PSPD
MS in Urban Environmental Systems Management
Demonstration of Professional CompetencyAdvisors:
Jaime Stein . Alec Appelbaum . Evren Uzer . David Seiter
Final Presentation - 26 April 2013
+ =
FROM OPEN SEWER TO OPEN (RE)SOURCE
PARTICIPATORY SUSTAINABLE INFRASTRUCTURE PLANNING:PICA-PAU FAVELA IN RIO DE JANEIRO
02
INFRASTRUCTURAL ISSUES
PARTICIPATORY SUSTAINABLE INFRASTRUCTURES
FAVELA PICA PAU: CLIENT + SITE + COMMUNITY
PARTICIPATORY PROCESS (FIELD WORK)
RESULTS + REASSESSMENTS
CONTINUATION + REPLICABILITY
PRESENTATION AGENDA:
of populationin cities a
50% over
in informalhousing b
800MILLION
of populationw/improved
sewage c
61%
03 a: Grimm, N. et al. “Global Change and the Ecology of Cities.” Science; vol.319, Feb. 2008: 756-759.b: United Nations Millenium Development goals: 2011 update. (2010 statistics)c: United Nations Millenium Development goals: 2011 update. (2008 statistics)
URBAN MIGRATION + INFORMAL SETTLEMENTS
GLOBAL URBAN MIGRATION
INFORMAL COMMUNITIES
STRAINED INFRASTRUCTURE
INFRASTRUCTURAL ISSUES
ofpopulationhas treatedsewage a,b
76%
2015: 86%2020: 89%
2030: 96%
04
cd
a: Cavallieri, F.; S. Oliveira. “A melhoria das condições de vida de habitantes de assentamentos precários no Rio de Janeiro.” IPP (RIo de Janeiro City Planning Dept.). Rio de Janeiro, Brazil; December 2006.b: “Plano Nacional de Saneamento Básico (National Basic Sanitation Plan).” SNSA (National Secretariat of Environmental Sanitation of Brazil). Brasília, Brazil: April 2011.c: Open sewer in a favela in Rio de Janeiro. http://oglobo.globo.com/participe/mat/2010/11/10/rio-salgado-na-zona-norte-do-rio-sofre-com-acumulo-de-lixo-falta-de-cuidado-922995860.asp; by Sizenaldo Marinho do Nascimentod: Effluent reaching the Guanabara Bay. http://www.ambientalsustentavel.org/2011/bid-vai-emprestar-us-452-milhoes-para-melhorar-esgoto-na-baia-de-guanabara/
SANITATION INFRASTRUCTURAL DEFICIT: RIO DE JANEIRO
SEWAGE TREATMENT GOALS (RJ STATE) b
*over R$ 135B cost (SE Region of Brazil)
INFRASTRUCTURAL ISSUES
NO participation
BY
2020 investment
in development of favelas c
05
a b
a: A Morar Carioca community facility project in Rio de Janeiro. http://www.uppsocial.org/acao-prefeitura/programa-morar-carioca-secretaria-municipal-de-habitacao/ b: Removals at a favela in the Jacarepaguá neighborhood. http://comitepopulario.wordpress.com/2013/02/22/graves-violacoes-de-direitos-humanos-no-largo-do-tanque-em-jacarepagua/#c: Municipal Housing Secretariat of Rio de Janeiro. “Conheça o Programa.” Morar Carioca summary. http://www.rio.rj.gov.br/web/smh/exibeconteudo?article-id=1451251d: Morar Carioca logo. http://www.cidadeolimpica.com/en/morar-carioca-en/
c
SOCIOPOLITICAL INFRASTRUCTURAL DEFICIT: FAVELAS
current favela redevelopment program
R$ 8BILLION
INFRASTRUCTURAL ISSUES
06
HOW CAN WE PROPERLY LEVERAGE THE
SOCIAL AND ENVIRONMENTAL ASSETSOF OUR CURRENT URBAN CONDITION,
SO AS TO IMPROVE THE QUALITY OF LIFE
OF ITS RESIDENTS?
07
NATURALSYSTEMS
COMMUNITYPARTICIPATION
SUSTAINABLEINFRASTRUCTURES
+ =
PARTICIPATORY SUSTAINABLE INFRASTRUCTURES
08
KNOWLEDGE
COLLABORATION
LEADERSHIP
TRUST
SOLUTIONS
ENGAGEMENT
ACCOUNTABILITY
TRANSPARENCY
COMMUNITY PARTICIPATION
09
SYSTEMS
PERFORMANCE
HABITATS
PROCESSES
OPEN SPACES
PUBLIC HEALTH
BIODIVERSITY
PRODUCTS
NATURAL SYSTEMS
11
PARTNERSHIPS
INFRASTRUCTURAL NEED
POTENTIAL IMPACT
OPPORTUNITY
COMMUNITY BUY-IN + ORGANIZATION
DEFINING A CLIENT: SELECTION CRITERIA
12 a, photo by Christina Parkb. Catalytic Communities logo. courtesy of Catalytic Communitiesc, Irenaldo Honório da Silva. courtesy of Catalytic Communities
CATALYTICCOMMUNITIES
LEONELLIMA
PONCE
PICA-PAURESIDENTS’
ASSOCIATION
FAVELA ADVOCACY
NGORESEARCHERCOMMUNITYLEADERSHIP
PARTNERSHIPS
13map: Google/ NOAA. “Rio de Janeiro.” Google Maps (Orthographic photography).
Rio de Janeiro
Guanabara Bay
Niterói
PICA-PAU
SITE:RIO DE JANEIRO
map: Instituto Pereira Passos (IPP). “Mapas Digitais do Rio de Janeiro.” (digital interactive maps). http://portalgeo.rio.rj.gov.br/ipp_viewer/?config=config/ipp/cadlog.xml14
sewage treatment plant
sewage treatment plant
Guanabara Bay
Governor’s Island(airport)
Cordovil
PICA-PAU
~3 km
INFRASTRUCTURAL NEEDRIO DE JANEIRO >>> CORDOVIL
15images: Infrastructural issues, favela Pica-Pau. photos by Leonel Lima Ponce
AREAS OF
RISK
FAILINGCOMBINED
SEWER
INFORMALWATERPUMPS
+SEWERS
OPENSEWAGEDITCHES
+FLOODING
WASTEDUMPING
+CANALCSO’S
INFRASTRUCTURAL NEEDRIO DE JANEIRO >>> CORDOVIL >>> PICA-PAU
2,300-12,000 PEOPLE AFFECTED16
Pica Pau (official boundaries): Est. Area a: 3,8000 m2
Est. Population (2010) b: 2,300
Estimated Cordovil favela complex(subject to Morar Carioca project) Est. Area a: 235,000 m2 Est. Population (2010) b: 12,000
a: Instituto Pereira Passos (IPP). “Mapas Digitais do Rio de Janeiro.” (digital interactive maps). http://portalgeo.rio.rj.gov.br/ipp_viewer/?config=config/ipp/cadlog.xmlb: IBGE (Brazilian Institute of Geography and Statistics). “Censo Demográfico 2010: Aglomerados Subnormais.” Rio de Janeiro, Brazil: 2010.
a
POTENTIAL IMPACT: MORAR CARIOCA RIO DE JANEIRO >>> CORDOVIL >>> PICA-PAU
MAR./APR. 2013
17
RFP+
BIDS
DESIGN TEAMS
CHOSEN
SITESURVEY
+DIAGNOSIS
PROJECTDESIGN
CONSTRUCTION
* ARCHITECTS FOR CORDOVIL PROJECT CHOSE TO
HOST A COMMUNITY MEETING.
OPPORTUNITY: MORAR CARIOCA
MAR./APR. 2013
18
RFP+
BIDS
DESIGN TEAMS
CHOSEN
SITESURVEY
+DIAGNOSIS
PROJECTDESIGN
CONSTRUCTION
PARTICIPATORYPLANNING
WORKSHOPS
NATURALSYSTEMSINCORPORATION
OPPORTUNITY: MORAR CARIOCA
19
a b
a, b, c: Favela Pica-Pau in Cordovil; Irenaldo Honório da Silva. courtesy of Catalytic Communities
aa
c
ENVIRONMENTALEDUCATION
POLITICALADVOCACY
PARTICIPATORY SUSTAINABLE
INFRASTRUCTURES
COMMUNITY BUY-IN + ORGANIZATION
20
OPENENDED
ACTIVITIES
FAMILIARTOOLS +
SETTINGS
DIAGNOSTICEXPLORATIONS
RESULTORIENTEDACTIVITIES
NOVELTOOLS +SETTINGS
SOLUTIONS
PARTICIPATON STRATEGIES
MAR./APR. 2013
21
MORAR CARIOCA TIMELINE
MAR
18MAR
23MAR
30APR
06
SITE VISIT + WORKSHOPS
ORGANIZINGMEETINGS
TRANSECTWALKS
COMMUNITYVISIONING
WORKSHOPS
PARTICIPATORY + SUSTAINABLE TIMELINEPRE-RESEARCH RESEARCH
PARTICIPATON STRATEGIES: TIMELINE
22 a, Irenaldo Honório da Silva. courtesy of Catalytic Communitiesb. Catalytic Communities logo. courtesy of Catalytic Communities
b
a
PICA-PAU RESIDENTS’ ASSOCIATION (MAR. 23)
COMMUNITY PRIORITIES
AVAILABILITY
CAPACITY
PREFERRED SCOPE
INITIAL VISIT: SYSTEMS DIAGNOSIS
CATALYTIC COMMUNITIES (MAR./APR.)
PROJECT TEAM AVAILABILITY
CAPACITY
COLLABORATIVE ORGANIZING MEETINGS
24images: Transect Walks in Pica-Pau favela. 30 March 2013. photo by Leonel Lima Ponce.
PROCESS: THE WALK
GROUP WALK
DIAGNOSEINFRASTRUCTURAL ISSUES
MAPCOMMUNITY
INPUT
MARCH 30: TRANSECT WALKS
RESIDENTDIAGNOSIS
RESIDENTINTERVIEWSADAPTATIONS
EXPLAINED
GROUPOBSERVATIONS
25images: Transect map of Aricambú Street, in Pica-Pau favela. 30 March 2013. photo by Leonel Lima Ponce.
PRODUCT: TRANSECT MAPSMARCH 30: TRANSECT WALKS
PRIORITYAREAS
PRIORITYCATEGORIES
PRIORITYISSUES
26images: Transect Diagram of Pica-Pau favela. 30 March 2013. photo by Leonel Lima Ponce.
PRODUCT: TRANSECT DIAGRAMMARCH 30: TRANSECT WALKS
27images: Favela Pica-Pau community visioning workshop, 06 April 2013. courtesy of Catalytic Communities.
FREEPLAY
FOUNDOBJECTS
COMMUNITYBUILDING
Q:How can Pica-Pau resolve its problems, especiallywater, sewage, and waste?
APRIL 06: COMMUNITY VISIONING WORKSHOPPROCESS: “CITY AS PLAY”
CONNECTINGPROBLEMS
+ SOLUTIONS
28image: Favela Pica-Pau community visioning workshop, 06 April 2013. courtesy of Catalytic Communities.
APRIL 06: COMMUNITY VISIONING WORKSHOPPRODUCT: “CITY AS PLAY” - PHYSICAL MODELS
29images: Favela Pica-Pau community visioning workshop, 06 April 2013. courtesy of Catalytic Communities.
COMMUNITYPRIORITY
RE-EVALUATION
BROADERPARTICIPATION
TRANSPARENCY
PROCESS: REVIEW OF TRANSECT WALKSAPRIL 06: COMMUNITY VISIONING WORKSHOP
30images: Sustainable Infrastructure Matrix, by Leonel Lima Ponce. photo by Leonel Lima Ponce.
PROCESS: SUSTAINABLE INFRASTRUCTURE CATALOG
NATURAL SYSTEMS
PRIORITIESADDRESSED
OBSTACLESTO
IMPLEMENTATION
POTENTIALS+ VISIONS
APRIL 06: COMMUNITY VISIONING WORKSHOP
31images: Favela Pica-Pau community visioning workshop, 06 April 2013. courtesy of Catalytic Communities.
PROCESS: COMMUNITY VISIONING SESSION
RESIDENTSGROUPEDBY AREA
DISCUSSIONBASED ON
PRECEDING INFO(VISIONS)
COLLABORATIVEPROCESS
APRIL 06: COMMUNITY VISIONING WORKSHOP
INCORPORATEDSUSTAINABLE
SOLUTIONSPRIORITIZEDSOLUTIONS
ADDITIONALDIAGNOSES
32image: Community vision exercise, Pica-Pau community workshop, 06 April 2013. photo by Leonel Lima Ponce
PRODUCT: COMMUNITY VISIONING SESSIONAPRIL 06: COMMUNITY VISIONING WORKSHOP
33
TRANSECT WALKS: TAKEAWAYS
DIAGNOSIS: RESIDENTS VS. OFFICIAL
GROUP: DREW BYSTANDERS’ ATTENTION
GROUP: ENRICHED DISCUSSION
SEVERE INFRASTRUCTURE FAILURE
COMPLEX MIX: FORMAL + INFORMAL
LACK OF SPACE FOR LARGE PROPOSALS
INITIAL RESULTS
34
TRANSECT WALKS: PRIORITY ISSUES
FLOODING (ARICAMBU / ALLEYS)
WATER SUPPLY: PUMPS + RAINWATER COLLECTION
COMBINED SEWER SIPLLS OVER AT CATCHBASINS
OPEN SEWERS + BROKEN PIPES = CONTAMINATION
COMBINED SEWER OUTFALLS AT IRAJA RIVER
WASTE DUMPED AT IRAJA RIVER
DISEASES: INCIDENCES OF DENGUE, TB, OTHERS
PUBLIC WORKS EXACERBATE AREAS OF RISK
INITIAL RESULTS
35
COMMUNITY VISIONING WORKSHOP: TAKEAWAYS
RESIDENT COLLABORATION
RESIDENT LEADERSHIP +ACCOUNTABILITY
RESIDENTS: HOLISTIC SOLUTIONS
SMALL SCALE, PERSONAL SOLUTIONS
LARGE SCALE, UTOPIAN SOLUTIONS
BUY-IN: PROCESS + POSSIBILITIES
FEW NATURAL SYSTEMS IN SOLUTIONS
INITIAL RESULTS
36
BUILD OVER THE RIVER: SPACE GENERATION
CISTERN UNDER SOCCER COURT:WATER SUPPLY + FLOOD REDUCTION
RECYCLING PROGRAMS, STREET LEADERS:SUSTAINABLE MANAGEMENT
COMMUNITY VISIONING WORKSHOP: MAJOR VISIONS
DAYCARE > PRESCHOOLS >> TECHNICAL SCHOOLSCHILD + YOUTH DEVELOPMENT
GREEN SPACES AT DITCHES + EMPTY LOTSNATURAL SYSTEMS
INITIAL RESULTS
37
EXPAND TIMELINE
ENGAGE EVEN BROADER DEMOGRAPHIC
ADVOCACY + SOCIAL INFRASTRUCTURE
SEPARATE DESIGN WORKSHOP
MONITORING + MAINTENANCE WKSHOP
FEASIBILITY: TECHNICAL EXPERTS
JOB CREATION POSSIBILIIES
REASSESSMENTS
38
“WE WANT THIS TO CONTINUE BEYOND APRIL 6, 2013.
WE WANT TO GO BEYOND PAPER, BEYOND PROJECTS.
WE WANT SOLUTIONS.”
- Kelly Cristina Tavares de Jesusresident, Pica-Pau favela
39
POSSIBLE PARTNERSHIPS
RFP+
BIDS
DESIGN TEAMS
CHOSEN
SITESURVEY
+DIAGNOSIS
PROJECTDESIGN
CONST.
CATCOMM
PUBLIC DEFENDERS
STUDIO X
IBASE
TIBA INSTITUTE
UFRJ / PUC
ARQHOS
BOTANIC GARDENS
CONTINUATION
40
FLEXIBILITY
MORAR CARIOCA PROCESS
PARTICIPATORY + SUSTAINABLEPROCESS
INCORPORATION
COMMUNITY-BUILTINDIVIDUAL PROJECTS
PARALLELPLAN
CONTINUATION
41
TIMELINE
MORAR CARIOCA TIMELINE
MAY
2013
FUTURE WORKSHOPS
SUSTAINABLEPICA-PAU
PLAN
MAINTENANCE+ MONITORING
PARTICIPATORY + SUSTAINABLE TIMELINE
MID
2013LATE
2013EARLY
2014
NATURALSYSTEMSDESIGN
REMOVALS+ HOUSING
RIGHTS
CONTINUATION
44
Pica-Pau Community (clients)
Irenaldo Honório da Silva
Resident Guides: Geraldo, Natalia, Paulo, Sebastião,
Karolayne, Marissa, Zilá; interviewees
Residents / Workshop Participants
Catalytic Communities (project team)
Theresa Williamson
Catherine Osborn, Gloria Jimenez, Sarah De Rose
Ministério Semear Church, Brás de Pina (workshop hosts)
ARQHOS (survey/technical support)
family + friends
ACKNOWLEDGEMENTS