Post on 22-Oct-2014
Overseas Technical Coatings & Services
SAUDI ARAMCO CONTRACT
METHOD STATEMENT
FOR
APPLICATION OF VARIOUS APCS SYSTEM FOR INTERNAL,
EXTERNAL & UNDERSIDE OF FLOOR PLATE COATING OF
CARBON STEEL TANKS
MS -KHI- 001
Prepared for
Approval21 Feb, 2012
Rev 00 DatePrepared By Hertel OTC Reviewed
ByApproved By
OTC/QCP.Doc, MS-IC-002 (Rev 01) Page 1 of 11
Overseas Technical Coatings & Services
Index
1. Scope
2. Purpose
3. Definitions
4. References
5. General
6. Access
7. Equipments
8. Procedure
9. Personnel Qualification
10. Safety
11. Attachment
OTC/QCP.Doc, MS-IC-002 (Rev 01) Page 2 of 11
Overseas Technical Coatings & Services
1. SCOPE
This method statement covers the minimum requirements for shop & field applications of various APCS systems for internal and external coating of CS storage tanks.
2. PURPOSE
This method statement and quality control procedure covers the painting work to be carried out for tankage for Wasit-SAUDI ARAMCO Project
3. DEFINITIONS
3.1.1. COMPANY : SAUDI ARAMCO
3.1.2. EPC CONTRACTOR : S.K. ENGINEERING
3.1.3. CLIENT : AL KHODARI HEAVY INDUSTRIES
3.1.4. PROJECT :
3.1.5. JOB NO. :
3.1.6. COATING CONTRACTOR : Overseas Technical Coatings & Services (OTC)
4. REFERENCES
4.1 SAUDI ARAMCO Engineering Standard H-001, Coating Selection & Application Requirements for Industrial Plants & Equipment
4.2 SAUDI ARAMCO Engineering Standard H-102. Safety Requirements for Coating Applications
4.3 SAUDI ARAMCO Engineering Procedure 316 Performance Qualification of Coating Personnel
4.4 SUADI ARAMCO material system specification 09-SAMSS-067
4.5 Steel Structure Painting Council (SSPC-SP1)
4.6 Swedish Standards Institution SIS 05 59 00
4.7 Manufacturer’s Product Data Sheets & MSDS
4.8 National Association of Corrosion Engineers (NACE)
4.9 British standard for protective coating of iron and steel structures against corrosion (BS 5493)
OTC/QCP.Doc, MS-IC-002 (Rev 01) Page 3 of 11
Overseas Technical Coatings & Services
5.0 GENERAL
5.1 The plant will be under construction while painting work is being carried out safety will be a main consideration while working at construction site.
5.2 The work permit will be required all the time while the sky climber shall be used for surface preparation and painting activity is going on OTC supervisor will ensure that the work permit is in place before starting the work in the designated area.
5.3 OTC will deploy trained and skilled manpower for the project. Such manpower will have experience of working in operational petrochemical / refinery plant. All the manpower being mobilized for the project will go the safety orientation programme of S. K. engineering /KHI prior to start working in the plant.
5.4 OTC will ensure sufficient supervision for the project. Separate QA/QC & safety officer shall be deployed and shall report directly to KHI Project Manager.
5.6 Sky climber’s motor and control panel shall be covered by sheeting or tarpaulin to prevent the ingress of dust or paint wherever practical.
5.7 The immediate work area will be barricade with tube and “ No Entry” & danger painting work is progress “Sign will be posted”.
6.0 ACCESS 6.1 Access to coating work for external shall be by suspended plateform such as sky climber
and man lift.
6.2 Sky climber access shall comply safety requirement of Saudi Kayan.
6.3 Sky climber shall meet or exceed all OSHA and ANSI standard.
6.4 Fixed and mobile scaffold shall be used for internal painting work.
6.5 Scaffold shall meet Saudi Aramco requirement.
7.0 EQUIPMENT.
7.1 Air operated Alpha 500 Sky Climber hoists with 2/3/4 meter suspended plateform will be used.7.2 Sufficient 375/800 CFM compressor will be used to supply free air to motor of the Sky
climber.
7.3 All compressed air hoses and steel wire ropes shall be circular in section, free of cuts, kinks and twists. Any change in direction shall be by long radius curves to maintain constant and unrestricted flow where possible.
OTC/QCP.Doc, MS-IC-002 (Rev 01) Page 4 of 11
Overseas Technical Coatings & Services
7.4 The following equipment part shall be inspected in field prior to operations of sky climber.
7.5 Safety Equipment (Such as Rolling Roof Rigging, Safety Life line & Full body harness)Rope ConditionSky Lock (Coupling nuts & Bolts)Hoist Unit (Coupling nuts, Bolts & Rope Housing Drain)Work Platform (All joints,Roller Wheel & Control Panel)Air Connection ( All Hoses, Air Valve & Connection)
7.6 The sky climber is equipped with sky lock overspeed device which sense the speed of ropepassing through its mechanism and if preset speed is exceeded the Sky Lock brake will lock onto the wire rope and rope can not be release until the load on the Sky Lock brake is released.
7.7 Abrasive blasting machines will be fitted with an abrasive regulating valve and moisture and oil separators to ensure all air passing through the equipment is clean and dry.
7.8 Breathing air fed to operator’s blast helmets will be filtered through approved filters.
7.9 Spray painting machine will be of the airless type and will be fitted with moisture and oil separators and pressure control valves.
7.10 Vacuum cleaners for internal dust removal will be of industrial quality and will be of 220/110 voltage.
7.11 Spotlight and background lights for internal blasting will be of 110 voltages.Lighting for spray painting will be of the explosion proof type.
7.12 Venturi air movers and extractors fans will be utilized for dust removal during internal blasting operations.
7.13 All major equipment will be run to ground.
7.14 Power tool & paint mixer shall by air driven (Pneumatic)
8 PROCEDURE
Pre-Blast Check
8.1.1 QC Inspector shall carry out checks before blasting to determine if cleaning is required either with the use of chemicals or solvents. If required solvent cleaning shall be carried out in accordance with SSPC - SPI.
8.1.2 No abrasive blasting shall be carried out unless the steel surface is at least minimum 3°C above the Dew Point.
8.1.3 Prior to start for blasting, all sharp edges and cut-offs shall be rounded to a smooth radiusand all weld spatters shall be removed.
OTC/QCP.Doc, MS-IC-002 (Rev 01) Page 5 of 11
Overseas Technical Coatings & Services
8.1.4 The compressed air supply shall be checked free of oil, moisture and contamination. As a minimum the inspector shall check and approve the air quality at the start of each 4-hour period. The method of checking shall be in accordance with SAES-H-100 Para 5.4
8.1.5 All compressed air hoses and paint lines shall be circular in section, free of cuts, kinks and twists. Any change in direction shall be by long radius curves to maintain constant and unrestricted flow where possible.
8.1.6 All hoses and nozzle connections shall be inspected prior to commencement of work to ensure they are secured. Any defective connection will be immediately replaced.
Surface Preparation: (Shop & Field)
8.1.7 Surface preparation shall be carried out to achieve Sa-3 and Sa-2.5 as per SAES H-101. All abrasive blasting shall be carried out by regular blasting equipment and Track blasting equipment for the Floor Plates.
8.1.8 The type of abrasive to be used shall be determined by the surface Profile and cleanliness requirements as per SAES H-100 item 5.1. All inspection and tests shall be carried out on accessible areas only.
8.1.9 Approved Abrasives (GARNET, Steel Shot & Steel Grit) shall be kept dry and free of contamination as per SAES-H-100 Para 5.2.1
8.1.10 Sufficient capacity compressors shall be used to supply free air to all elements of the abrasive and coating operation as per SAES-H-100 Para 5.4
8.1.11 The Blast profile shall be measured for internal surface of pipes on accessible areas only using Profile thickness gauge with “PRESS-O-FILM” Testex tape (X coarse replica tape). The same replica tape shall be attached with inspection report as a permanent record.
8.2 Abrasive Blasting :
8.2.1 Abrasive shall be kept clean and dry and free of contamination and shall be an approved mineral abrasive such as Garnet, Coal Slag or Steel shot and grit.
8.2.2 Surface preparation shall be carried out by manual blasting to required surface cleanliness level. Tank floor plate shall be blasted using Blast Track Machine.
8.2.3 On internal surfaces the abrasive will be removed, the area swept with clean soft brooms and finally vacuum cleaned.
8.2.4 Salt contamination test shall be carried out in accessible areas for internal tanks surface.
8.2.5 Blasted surfaces will be primed in accordance with the relevant specifications and before the surfaces conditions degrades below the specified cleanliness level.
OTC/QCP.Doc, MS-IC-002 (Rev 01) Page 6 of 11
Overseas Technical Coatings & Services 8.2.6 Whenever work is ongoing, one man will be allocated as “lookout” and will be stationed outside
the working area.
8.2.7 On completion of blasting surfaces will be checked for chloride contamination and if required decontamination shall be carried out.
8.3 Cleaning:
8.3.1 Used abrasives shall be removed from blasted surfaces using a dry brush, blowing down with clean dry compressed air or vacuum cleaner.
8.4 Coating:
8.4.1 Paint Storage:
a. Paints and thinners shall be stored in air-conditioned container. Warnings signs “Danger, flammable, no smoking, no naked lights” will be posted. The storage temperature shall be below 270C.
b. Containers that show signs of leakage or materials that have gelled shall be discarded.
c. The date of manufacture shall be clearly marked on each paint container and paints that have exceeded their shelf life shall be discarded.
d. Manufactures data sheets and MSDS on all materials will be readily available at the job site.
8.5 Paint Preparation:
a. All paints shall be thoroughly mixed using a power mixer.
b. All paints shall be mixed or thinned in strict accordance with the manufactures instructions.
c. The prepared surface shall be inspected for cleanliness and profile prior to coating.
d. Prepared surface shall be coated within a maximum of six hours and before any deterioration begins. Surfaces that have begun to deteriorate, or have exceeded the six hours shall be re-blasted.
e. Paint shall only be applied if the following conditions are met (or as specified by the paint manufacturers.)* Surface temperature to be at least 30C above dew points.* Surface to be free of oil, grease and other contaminants.* Protection from adverse weather conditions
8.6 Paint Application (Shop & Field):
a. All full coat will be applied by spray or brush / roller. The spray application shall be preferred method.
OTC/QCP.Doc, MS-IC-002 (Rev 01) Page 7 of 11
Overseas Technical Coatings & Services b. Each coat to be applied to the specified DFT and in accordance with the relevant manufactures
guidelines.
c. Recoating and drying times will be observed as per the manufactures recommendations.
d. Dry film thickness of each coat shall be measured in accordance with SSPC-PA2 using a suitable magnetic thickness gauge.
e. Coating System shall be followed as par attached Coating System Detail Chart (Attached)
8.7 Paint Repairs:
a. Areas less than 1.0 M2 shall be cleaned to ST.2 using hand wire brush or power brush to ground back to the metal surface, using at least an 80 grit disc sander. The edges being feathered back at least 50mm beyond the clean metal surface.
b. Area greater than 5.0 M2 shall be blast cleaned or ST 3 using power tool. The conditions to be obtained are as the original requirements, with the edges being feathered back at least 50 mm beyond the clean metal surface.
c. For areas less than 5.0 M2 brush coating is acceptable, but for areas above 5.0 M2, the paint shall be applied as per the original specification.
d. Recoating intervals shall be as per manufacturer’s data sheet recommendations.
e. All the work shall be documented for future reference.
8.8 Quality Control / Inspection & Acceptance Criteria
a. Quality Control, Inspection & Acceptance Criteria shall be in accordance with approved ITP as par SATIP-H-100-01.
b. Holiday / Pinhole test shall be carried out as per ASTM D 5162 for internal surface only
c. Final DFT shall be checked with magnetic gauge as per SSPC-PA-2. The total dry film thickness should not exceed 120 percent of the maximum dry film thickness nor shall it be less than 80 percent of the minimum specified dry film thickness.
9. PERSONNEL QUALIFICATION
OTC personnel involved in preparation, application, direct supervision or inspection of coatings shall be qualified and certified by Hertel-OTC and ARAMCO as per SAEP-316. This includes abrasive blasters, coating applicators, crew supervisors and QC inspectors.
10.SAFETY.
10.1 Safety Requirements for Painting shall be observed at all times and shall be strictly followed in accordance with SAES-H-102
10.2 The Project safety plan will be fully enforced during the duration of the work.
OTC/QCP.Doc, MS-IC-002 (Rev 01) Page 8 of 11
Overseas Technical Coatings & Services
10.3 During lining operations, all lighting will be of the explosion proof type as per SAES-H-102 Item 4.1
10.4 A standby man will be at the work at all times during the work. His role will be observing activities in the painting work and to stop the work immediately while any safety concern arises.
10.5 All operators will wear full personal protective equipment including coveralls, safety boots, gloves, helmets and positive air feed breathing masks in accordance with SAES-H-102 item 4.3
10.6 All recommendations of the Material/Equipments manufacturers concerning the safe handling and application of their products shall be followed as per SAES-H-102 item 4.4.
10.7 Forced air ventilation during abrasive blasting, solvent cleaning, paint application and curing
shall be followed as per SAES-H-102 item 4.2 & SAES-H-001 item 8.3.4
OTC/QCP.Doc, MS-IC-002 (Rev 01) Page 9 of 11
Overseas Technical Coatings & Services
11 ATTACHMENT(S)
11.1 Coating Systems Detail Chart
COATING SYSTEMS DETAILS CHART
AL KHODARI TANKS
SR. NO
.ITEM NO.
SERVICE NAME
INT. DIA
(mm)
HEIGHT
(mm)
NO. OF TANKS
COATING SYSTEM PINHOLE/HOLIDAY TEST
FOR INT. SURFACE
Floor U/S Internal External
1 Q68-D-011A/B
Lean MEG Storage
Tank11735 1093
72 SAES H-001
APCS-3SAES H-001
APCS-21SAES H-001
APCS-4As par ASTM-
D5162
2 Q68 D 12Fresh MEG
Storage Tank
15240 7315 1 SAES H-001 APCS-3
SAES H-001 APCS-2A
SAES H-001 APCS-4
As par ASTM-D5162
3 Q70-D-031
ARG Fresh MDEA
Storage Tank
7315 7315 1 SAES H-001 APCS-3
SAES H-001 APCS-27
SAES H-001 APCS-4
As par ASTM-D5162
4 Q70-D-032
ARG Solvent Storage
Tank18288 1341
1 1 SAES H-001 APCS-3
SAES H-001 APCS-27
SAES H-001 APCS-4
As par ASTM-D5162
5 Q68-D-106/206
Sour Water Feed Tank 25603 2011
7 2 SAES H-001 APCS-3
SAES H-001 APCS-2A
SAES H-001 APCS-4
As par ASTM-D5162
6 Q68-D-061A/B
Rich Sulfer Solvent Storage
Tank
30480 14021 2 SAES H-001
APCS-3
SAES H-001 Epoxy Lining
SAES H-001 APCS-4
As par ASTM-D5162
7Q68-D-062A/B
Stabilized Rich Solvent
Storage Tank
249931402
1 2
Painting is NOT
Possible Due to PWHT
SAES H-001 Epoxy Lining
SAES H-001 APCS-4
As par ASTM-D5162
8Q72-D-001A/B
Sulfer Storage
Tank25908 9754 2
SAES H-001 APCS-113 No
SAES H-001 APCS-2H
As par ASTM-D5162
9 Q73-D-108
Demin Water
Storage Tank
21945 12801
1 SAES H-001 APCS-3
SAES H-001 APCS-2B
SAES H-001 APCS-4
As par ASTM-D5162
10 Q73-D-200A/B
Drinking Water Tank 7010 4876 2 SAES H-001
APCS-3SAES H-001
APCS-2BSAES H-001
APCS-4As par ASTM-
D5162
OTC/QCP.Doc, MS-IC-002 (Rev 01) Page 10 of 11
Overseas Technical Coatings & Services
11 Q73-D-300A/B
Cooling Water Surge
Tank9144 7315 2 SAES H-001
APCS-3SAES H-001
APCS-2ESAES H-001
APCS-4As par ASTM-
D5162
12 Q73-D-401A/B
Condensate Storage
Tank51816 1280
22 SAES H-001
APCS-113SAES H-001
APCS-27SAES H-001
APCS-2HAs par ASTM-
D5162
13 Q73-D-901A/B
Utility & Fire Water
Storage Tank
29260 13716 2 SAES H-001
APCS-3SAES H-001
APCS-2ESAES H-001
APCS-4As par ASTM-
D5162
14 Q73-D-101A/B
Industrial Water
Storage Tank
36576 18288
2 SAES H-001 APCS-3
SAES H-001 APCS-2E
SAES H-001 APCS-4
As par ASTM-D5162
15Q69-D-
182
7% Wt Caustic
Supply Tank8686 8686 1
Painting is NOT
Possible Due to PWHT
SAES H-001 Belzona
1591
SAES H-001 APCS-1E
As par ASTM-D5162
OTC/QCP.Doc, MS-IC-002 (Rev 01) Page 11 of 11