Oct 2015 ProSys Sampling - MMcL · 06/10/2015 20 Unit 1 Unit 1 ––––Sectional planSectional...

Post on 10-Oct-2020

0 views 0 download

Transcript of Oct 2015 ProSys Sampling - MMcL · 06/10/2015 20 Unit 1 Unit 1 ––––Sectional planSectional...

06/10/2015

1

ProSys Containment

ISOLATOR CONTAINMENT TECHNOLOGY FOR THE MANUFACTURE OF

ANTIBODY DRUG CONJUGATES (ADCS)

OCTOBER 2015

Pharmaceutical Market in Transition

Targeted Drug Therapies (Personalised Treatment)

◦ Mabs, (Monoclonal Antibodies)

◦ ADCs, (Antibody Drug Conjugates)

◦ CART (Chimeric Antigen Receptor T) Cell Immunotherapy

06/10/2015

2

ADC IN ACTION !

� ADC Monoclonal antibody (mAb) + cell-killing cytotoxic drug

� mAb Delivery system which selectively targets the tumour cells

It has high binding specificity for tumour-specific antigens

� Once in the tumour, the ADC releases its cytotoxic payload by chemical or enzymatic processes, eventually leading to the death of the targeted cell

Components of ADC

COURTESY: (GENENTECH INC., 2015)

06/10/2015

3

Clinical Landscape of ADCs

COURTESY: ROSTAMI, S., I. QAZI, AND R. SIKORSKI, THE CLINICAL LANDSCAPE OF

ANTIBODYDRUG CONJUGATES. ADC REVIEW. AUGUST 1, 2014.

Isolator Definition

A separative device that provides assured protection by using physical

and dynamic barriers to create separation between operation

(product) and operator/exterior environment.

Containment Aseptic

Operator protection Product protection

06/10/2015

4

Containment Performance Target (CPT) & Occupational Exposure Limit (OEL)

CPT measured in ‘ µg/m³ or ng/m³@’ at 8 hours Time weighted average (TWA)

CPT= Containment capacity in terms of airborne concentration (µg/m3) of the isolator based on the OEL of the compound/API to be handled

OEL = Airborne concentration of a compound/API to which nearly all workers can be repeatedly be exposed 8 hours a day, 40 hours a week, without adverse effects.

ADC projects Customer Location : Cambridge, USATarget CPT : ≤10ng/cubmAchieved CPT: ≤5ng/cubm

06/10/2015

5

ADC projects Customer Location : California, USATarget CPT : 10 nanogram/cubm

MSB Isolator

Achieved CPT: 8ng/cubm

VSE Isolator

Achieved CPT: 10ng/cubm

CASE STUDYCASE STUDYCASE STUDYCASE STUDYCustomer Location : Dublin, IrelandTarget CPT : 50ng

06/10/2015

6

Project ObjectiveProject ObjectiveProject ObjectiveProject Objective

To develop a Production Suite for the contained manufacture of HPAI of an ADC

Project Drivers

EHS Achieve appropriate OEB 5 containment levels – less than

50ng/m3

EHS/GMP Prevent escape of airborne material from the suite or ingress

of material to the suite

GMP GMP improvements over existing cleanrooms (class and bio-

burden)

Production Maintain production during project execution

Concept Concept Concept Concept studystudystudystudy

2 processes:

� Lyophilisation of liquid API

� Lyophilisation of API Salt

Review existing process, equipment and SOP’s with production staff –decide what is sacrosanct and what can be changed.

06/10/2015

7

Process No.1 Process No.1 Process No.1 Process No.1 ----Lyophilisation of liquid API Lyophilisation of liquid API Lyophilisation of liquid API Lyophilisation of liquid API

Lyophilisation of liquid API Lyophilisation of liquid API Lyophilisation of liquid API Lyophilisation of liquid API

06/10/2015

8

Process No.2 Process No.2 Process No.2 Process No.2 ----Produce API Salt Produce API Salt Produce API Salt Produce API Salt

Produce API salt Produce API salt Produce API salt Produce API salt

06/10/2015

9

Key success factors for achieving Key success factors for achieving Key success factors for achieving Key success factors for achieving ng ng ng ng containment containment containment containment levelslevelslevelslevels

� Isolation technology

� Transfer technology

� Minimise number of transfers

� Minimise internal dust levels

� Perform transfers after cleaning where possible

� Effective cleaning

Key Equipment requirements to satisfy Key Equipment requirements to satisfy Key Equipment requirements to satisfy Key Equipment requirements to satisfy driversdriversdriversdrivers

� Separate units in independent rooms

� Achieve CPT of 50ng/m3

� Test in accordance with ISPE good practice guide

� Analyse results in accordance to EN 689

� Fit within available footprint (long and thin)

� Adhere to product registration –final package format

06/10/2015

10

Biggest isolator design challengesBiggest isolator design challengesBiggest isolator design challengesBiggest isolator design challenges

� Parallel development of isolator and process equipment

� Integration of 3rd party equipment (4 suppliers)

� Ergonomics

� Layout to provide logical process flow with minimum footprint

Isolator (unit 1) Isolator (unit 1) Isolator (unit 1) Isolator (unit 1) ––––Design considerations Design considerations Design considerations Design considerations ----ergonomicsergonomicsergonomicsergonomics

06/10/2015

11

Isolator (unit 1) Isolator (unit 1) Isolator (unit 1) Isolator (unit 1) ––––Design considerations Design considerations Design considerations Design considerations ----ErgonomicsErgonomicsErgonomicsErgonomics

Conclusion:

Integrate into isolator

base, accessed from

half-suit

Isolator (unit 1) Isolator (unit 1) Isolator (unit 1) Isolator (unit 1) ––––design design design design considerations considerations considerations considerations ----ergonomicsergonomicsergonomicsergonomics

06/10/2015

12

Isolator (unit 1) Isolator (unit 1) Isolator (unit 1) Isolator (unit 1) ––––design considerations design considerations design considerations design considerations ---- ergonomicsergonomicsergonomicsergonomics

Isolator (unit 1) Isolator (unit 1) Isolator (unit 1) Isolator (unit 1) –––– design considerations design considerations design considerations design considerations ----ergonomics ergonomics ergonomics ergonomics

06/10/2015

13

Unit 1 Unit 1 Unit 1 Unit 1 ––––Concept Design LayoutConcept Design LayoutConcept Design LayoutConcept Design Layout

Unit 1 Unit 1 Unit 1 Unit 1 ––––Concept Design LayoutConcept Design LayoutConcept Design LayoutConcept Design Layout

06/10/2015

14

Isolator (unit 2) Isolator (unit 2) Isolator (unit 2) Isolator (unit 2) ––––design considerations design considerations design considerations design considerations ----ergonomicsergonomicsergonomicsergonomics

� Non-hazardous dispensing outside isolator: Solids and liquids in VBE.

� Need Peristaltic Pump connections

Isolator (unit 2) Isolator (unit 2) Isolator (unit 2) Isolator (unit 2) ––––design considerations design considerations design considerations design considerations ----ergonomicsergonomicsergonomicsergonomics

50 l vessels

� ergo issues similar to unit 1 mixing vessel

� 2 vessels require agitator and weigh cells

06/10/2015

15

Isolator (unit 2) Isolator (unit 2) Isolator (unit 2) Isolator (unit 2) ––––design considerations design considerations design considerations design considerations ----ergonomicsergonomicsergonomicsergonomics

� Need to be able to inspect internals

� Need to be able to remove basket

� Need a filtrate receiver

Isolator (unit 2) Isolator (unit 2) Isolator (unit 2) Isolator (unit 2) ––––design considerations design considerations design considerations design considerations ----ergonomicsergonomicsergonomicsergonomics

Conclusions:

� Access OK for door opening and tray loading

� Access not OK for cleaning and inspection

� Half-suit preferred

06/10/2015

16

Isolator (unit 2) Isolator (unit 2) Isolator (unit 2) Isolator (unit 2) –––– design considerations design considerations design considerations design considerations ---- ergonomics ergonomics ergonomics ergonomics

Isolator (unit 2) Isolator (unit 2) Isolator (unit 2) Isolator (unit 2) ––––design considerations design considerations design considerations design considerations ----ergonomicsergonomicsergonomicsergonomics

Same design as Unit 1

06/10/2015

17

Unit 2 Unit 2 Unit 2 Unit 2 ––––Concept Design LayoutConcept Design LayoutConcept Design LayoutConcept Design Layout

Unit 2 Unit 2 Unit 2 Unit 2 –––– Concept Design LayoutConcept Design LayoutConcept Design LayoutConcept Design Layout

Vessels Centrifuge

Sieve

06/10/2015

18

Post Procurement Post Procurement Post Procurement Post Procurement ––––detailed design phasedetailed design phasedetailed design phasedetailed design phase

� Initial GA / P&ID review

� Ergonomic review of physical model

� Design documents review –

◦ Design specification

◦ FDS

◦ Software design and testing

�Testing

P&ID P&ID P&ID P&ID ––––Unit 1Unit 1Unit 1Unit 1

06/10/2015

19

Ergonomic reviewErgonomic reviewErgonomic reviewErgonomic reviewSuccess factors:

� Involve people with good process knowledge

� Involve people of different heights

� Step through process, cleaning and maintenance

� Simulate activity durations

� Identify control element locations

� Use actual equipment or weights

� Use gloves and half-suits

� Take photos

� Take minutes and agree during review

97 design points minuted for unit 1

06/10/2015

20

Unit 1 Unit 1 Unit 1 Unit 1 ––––Sectional planSectional planSectional planSectional plan

Unit 1 Unit 1 Unit 1 Unit 1 ––––Sectional elevationSectional elevationSectional elevationSectional elevation

06/10/2015

21

Unit 2 Unit 2 Unit 2 Unit 2 ––––Sectional planSectional planSectional planSectional plan

06/10/2015

22

Unit 2 Unit 2 Unit 2 Unit 2 ––––Sectional elevationSectional elevationSectional elevationSectional elevation

06/10/2015

23

Factory TestingFactory TestingFactory TestingFactory Testing

� Get protocols signed off early

� Pre-FAT recommended

◦ 149 items on unit 1 punch list

� Ensure vendor has completed testing

� Allow time in your schedule

◦ Pre-FAT, FAT, remedial work, Re-FAT -8 wks

◦ Bespoke solutions

Factory Testing Factory Testing Factory Testing Factory Testing ----challengeschallengeschallengeschallenges� Started too early –schedule driven

� Design errors of minor components

◦ bespoke designs

�Leak rate tests

�Cleanroom recovery tests

�Vessel Weigh cells

�Vessel agitators interface

�Peristaltic pump interface

06/10/2015

24

Layout Layout Layout Layout

06/10/2015

25

Installation Installation Installation Installation ––––Unit 1Unit 1Unit 1Unit 1

06/10/2015

26

06/10/2015

27

Installation Installation Installation Installation ––––Unit Unit Unit Unit 2222

06/10/2015

28

06/10/2015

29

Surrogate Testing

� Conducting air sampling and surface sampling to determine how much dust escapes from the containment.

� The sampling results provide a means of estimating how effectively the equipment will contain the API under similar conditions of use.

�Evaluate containment performance without potential exposures to potent Active Pharmaceutical Ingredients (APIs)

06/10/2015

30

Surrogate Materials

Containment testing Containment testing Containment testing Containment testing ----SATSATSATSAT

CPT: 50ng/m3

Geometric mean target: <25ng/m3

Equipment accepted.

Further actions: Test during operation

Consider using worker activity multiplier if necessary

Note: Operational results with product may be higher or lower

06/10/2015

31

ScheduleScheduleScheduleSchedule

High pointsHigh pointsHigh pointsHigh points

� Met the goals

� Successful integration of third party equipment

� Use of 3D to interrogate design

� Ergonomics

� Project on budget and schedule

06/10/2015

32

Low PointsLow PointsLow PointsLow Points

� Integration of Weighing and pump control system

� FAT time

� SAT time

Thank You

Contact Details

Michael McLoughlin

Managing Director

Email: mmcl@prosys.ie

Tel: +353 (0)21 4853900

Web: www.prosys.ie

06/10/2015

33

ProSys Containment HQ, Ireland

Our Clients

06/10/2015

34

Our Vision Our Vision Our Vision Our Vision (purpose)(purpose)(purpose)(purpose)

Our Vision is to be the Preferred Supplier of Custom Containment Equipment to the Global Pharmaceutical Production

Industry

Strategy StatementStrategy StatementStrategy StatementStrategy Statement

To be the Preferred Supplier of Custom Containment Equipment to the Global Pharmaceutical Production Industry

by

Delivering High Quality Engineered Solutions

by

Providing a responsive, can-do service driven by a sense of urgency to exceed customer expectations

by

Leading innovation in Containment Technology

by

Developing lean agile processes across the organization

by

Keeping our Promises

06/10/2015

35

ProSys Core ValuesProSys Core ValuesProSys Core ValuesProSys Core Values

Customer Orientation

Innovation

Flexibility

Communication - Face to Face Interaction

Co-operation & Knowledge Sharing

Accountability

Cost Conscious