Presentation Outline

1. Brief History of Norriego Point Project

2. Norriego Point Beach Restoration, Stabilization and Recreation Improvement Project Funding

3. NRDA Process and Requirements

4. Restoration/Stabilization/Recreation Project Description

5. Questions

3/5/2018 DWH 2

Project History

• 1995 – Hurricane Opal

• 1999 -Stabilization First Recommended in IMP

• 2008 - Stabilization Design Commenced

• 2009 – City of Destin Commissioned a Feasibility Study

• 2008 – 2016 - Numerous Design Revisions

• 2011 – City of Destin submitted an application for project to be considered for funding under the DWH NRDA ERP

• 2013 - Project permitted June • Rock/Sheet pile and All-Rock Alternatives

3/5/2018 DWH 3

• 2012 - Project Submitted by the City of Destin for Consideration Under the NRDA DWH ERP

• 2014 - Project Selected for DWH NRDA ERP Phase III and Funding Received

• 2015 – FDEP solicited/awarded/contracted for Value Engineering services & Preparation of Construction Documents

• 2017 – FDEP issues ITB, awards construction contract and starts construction of Shoreline Stabilization and Beach Restoration Component

3/5/2018 DWH 4

Project History (Cont.)

Project History (Cont.)

• Summer - Fall 2018 – Vegetation of Constructed Dune

• Fall 2018 – Spring 2019 – Construction of Recreation Facilities

• Summer 2019 – Project Completed

3/5/2018 DWH 5

Project Funding

• NRDA ERP - $10,228,130 • Beach Restoration/Stabilization

• Recreational Facilities

• FDEP Beaches Restoration Grant - $3,768,750

• Beach Restoration/Stabilization

3/5/2018 DWH 6

NRDA Process

• Applications submitted by the City, County, State & Federal Agencies, NGOs, and/or individuals

• Review and Selection Process – TIG (DEP, FWC, NOAA, USDA, DOI, USACOE, EPA)

• Public Input

• Environmental and Cultural Resource Review(s)

• Final Project Selection & Receipt of NRDA Funding

3/5/2018 DWH 7

All FL DWH NRDA ERP Projects Authorized to Date

3/5/2018 DWH 8

> 90 Projects, ~$250 million https://floridadep.gov/wra/deepwater-horizon

Project Types

Recreational

• State Park improvements (4)

• Boat Ramp Construct (3)

• Boat Ramp Enhance (11)

• Boardwalks (2)

• Dune walkovers (3)

• Pier Construct (3)

• Pier Enhance (3)

• Other Local park facilities and improvements (4)

• Fish hatchery (1)

• Artificial reefs (1)

Recreational – cont.

• New or Improved Coastal Access (8)

• Scallop enhancement (1)

• Wildlife viewing and fishing areas (2)

• Shoreline stabilization and beach nourishment (2)

Ecological

• Living shorelines (2)

• Dune restoration (2)

• Seagrass restoration (2)

• Oyster cultch placement (1)

• Birds (1)

• Turtles (1)

3/5/2018 DWH 9

Project Components

• Stabilization Component – Fall 2017 – Summer 2018 • Project Shall Restore Approx. 1200 LF of Shoreline • 3,000 LF Shoreline Open to the Public Upon Completion • 5.4 AC of Beach Restoration and Dune construction from

Dredging within Federal Navigation Channel in East Pass (North of Hwy 98 Bridge) and entrance to Destin Harbor

• Total Area of the Park – 13 AC • Shoreline Stabilization consisted of construction of new

groins and rehabilitation of existing groins through a combination of Marine Mattresses (foundation), rock (protection) and composite sheet pile (sand retention)

3/5/2018 DWH 10

Project Components (Cont.)

• Dune Vegetation Component –Summer 2018- Fall 2018 • 5+ AC

• Recreation Component – Fall 2018 –Spring 2019 • Restroom Facility

• Entrance & Parking Improvements

• Outdoor Shower / Water Fountains

• Bicycle Parking

• Boardwalks and Multi-use Trail

• ADA Accessibility

3/5/2018 DWH 11

Stabilization Components

3/5/2018 DWH 12

Stabilization Components

3/5/2018 DWH 13

Stabilization Components Dune Construction

3/5/2018 DWH 14

Recreation Improvement Components

3/5/2018 DWH 15

3/5/2018 DWH 16

Recreation Improvement Components

Norriego Point Summer 2019

3/5/2018 DWH 17

For Further Information

• Pearce L. Barrett III, P.E., FCCM NRDA Project Coordinator Pearce.Barrett@dep.state.fl.us 850-245-2106

• Rachel Horne Gulf Coast Public Affairs Manager Rachel.Horne@dep.state.fl.us 850-245-2107

3/5/2018 DWH 18

Questions?