New York StateReliability Council
……..Promoting Electric System Reliabilityin New York State
Presentation to the MEUA Annual Meeting - 2000
September 19-21, 2000
Richard J. Bolbrock, P.E.Chairman - New York State Reliability Council
2
NYSRC Mission
To Promote and Preserve
the Reliability of Electric Service
on the Bulk Power System
in New York State
3
General Responsibilities
• Establish and maintain Reliability Rules for use by the NYISO and all entities engaging in electric power transactions on the Bulk Power System
• Along with NPCC and the ISO, monitor compliance with the Reliability Rules
• Establish State-Wide Installed Capacity Requirements consistent with NPCC Standards
4
NYSRCExecutive Committee
ReliabilityRules
Subcommittee
ReliabilityComplianceMonitoring
Subcommittee
ICAPWorking Group
NYSRC Organizational Structure
5
7 - Affiliated Members from the Transmission Providers
1 - Member from the Electric Suppliers
1 - Member from the Municipalities
1 - Member from the Large Customers
3 - Non-Affiliated Members
3 - Observers
ISO
PSC
NPCC
NYSRC Membership
6
NYSRC Responsibility Topics
• NYSRC Rule Development
• NYSRC Compliance Monitoring
• NYCA ICAP Requirements
7
NYSRC Rule Development
1. Elements of NYSRC Rules
2. Process for Updating NYSRC Rules
3. Rule Development Program for 2000
8
Elements of the NYSRC Rules
• NERC Standards
• NPCC Standards
• Local Reliability Rules
• Other more restrictive or stringent criteria than NPCC Standards, recognizing special NYS system characteristics or reliability needs
Procedure for Reviewing, Developing,Modifying, and Disseminating NYSRC Reliability Rules
NYSRC
Rule ChangeRequest
EC Assigns to RRS
RRS Recommendation to Accept or Reject Rule Change
NotificationEC
Action
Notify MPs
Implement Rule Dispute Resolution
PostNotifyFERC & PSC
FinalNew or Modified
Rule
To RRSfor Revision
RRSFinal Draft Rule
PostRRS 1st Draft Rule
ISOReviews
Rule
(Agrees with Rule)
(Disagrees with Rule)
(Return)
(Reject Rule Change) (Accept Rule Change)
RRS Reviews Comments
(Approve)
(45 DayComment Period)
PostRequest
ISO MPs
ECAction
1
2
3
4
5
6
78
10
Rule Development Program for 2000
• Preparing new NYSRC Rules
• Merging NERC/NPCC Standards into NYSRC Rules
11
NYSRC Compliance Monitoring
1. NYSRC Compliance Review Process
2. 2000 NY Reliability Compliance Program
[2000 NYRCP]
12
Compliance Review Process
• Develop reporting procedures
• Collect data, documentation, and assessments to demonstrate compliance
• Evaluate compliance
• Report conclusions regarding full compliance or levels of non-compliance
13
Types of NYSRC Rule Assessments
AssessmentType
Type of
NYSRC Rule
Entity RuleIs
Applicable To **
ComplianceMonitoring
EntityOversight
Review
A NERC/NPCC ISO NPCC NYSRC
B NERC/NPCC MPs ISO NYSRC/NPCC
C NYS Specific * ISO NYSRC -
D NYS Specific * MPs ISO NYSRC
____* NYSRC Local Rules or Rules that are either more stringent than NPCC or NERC criteria, or notcovered by NPCC or NERC criteria.
** Also, this entity has reporting responsibility
14
Compliance Review - Type ANYSRC Rule: NPCC CriteriaResponsible Reporting Entity: ISOCompliance Monitoring Entity: NPCCOversight Review Entity: NYSRC
Examples:
• Transmission System Performance (3.2.1-3.2.6)
• NERC/NPCC Pilot Program Standards
ISOPrepares
Compliance Report
NYSRCProvides
Oversight Reviewand Comments
to ISO
NPCC MonitorsISO
Compliance
1
23
15
Compliance Review - Type BNYSRC Rule: NPCC CriteriaResponsible Reporting Entity: MPsCompliance Monitoring Entity: ISOOversight Review Entity: NYSRC/NPCC
Examples:
• NERC/NPCC Pilot Program Standards
MPsPrepares
Compliance Report
NYSRCProvides
Oversight Reviewand Comments
to ISO
NPCC ProvidesOversight
Review
ISO MonitorsMP
Compliance
1
2
3 4
16
Compliance Review - Type C
NYSRC Rule: Not Covered by NPCC/NERC CriteriaResponsible Reporting Entity: ISOCompliance Monitoring Entity: NYSRC
Examples:
• Locational ICAP Responsibility (3.1.2)
• Restoration Procedures (4.1.6)
• DMNC Testing Procedure (3.1.3.1)
ISOPrepares
Compliance Report
NYSRC MonitorsISO
Compliance
1
2
17
Compliance Review - Type DNYSRC Rule: Not Covered by NPCC/NERC CriteriaResponsible Reporting Entity: MPsCompliance Monitoring Entity: ISOOversight Review Entity: NYSRC
Rule Examples:
• Local Rules
• LSE Capacity Responsibility (3.1.4)
• DMNC Testing - Test Results (3.1.3.1)
MPs PrepareCompliance Report
ISO MonitorsMP
Compliance
NYSRC ProvidesOversight
Review
1
2
3
18
Summary2000 NY Reliability Compliance Program (NYRCP)
Assessments
Assessment / RuleReporting
EntityMonitoring
Entity
1. Statewide ICAP NYSRC NPCC2. Locational ICAP Responsibility ISO NYSRC3. DMNC Testing ISO
GNYSRC
ISO*4. LSE Capacity Responsibility LSE ISO*5. Transmission System Performance ISO NPCC*6. Proposed Transmission & Interconnection
ProjectsG, T ISO*
7. System Restoration Plan ISO NYSRC8. ISO Operating Data ISO NYSRC9. Local Rules (5) ConEd, LIPA ISO*10. NERC/NPCC Pilot Program ** ISO, MPs NPCC, ISO*
* NYSRC has an oversight role.** This program includes approximately 40 planning and operating assessmentsG Generation OwnerTLSE
Transmission Owner Load Serving Entity
19
2000 NYRCP Summary
NYSRC Rules
Compliance/ReportingEntity NYS Specific NERC/NPCC Total
NYISO 5 23 28
Market Participants 8 16 24
____ ____ ____
Total 13 39 52
20
2000 NYRCP Objectives
• To Monitor Compliance with NYSRC Rules
• To Test Effectiveness of the Compliance Review Process and Procedures
• To Assess Communication between NYSRC, NYISO, Market Participants, and NPCC Concerning Reliability Assurance
21
NYCA IRM RequirementsNYSRC Study Process
Study Assumptions
Multi-Area ReliabilityModel
NYCA ResultsIRM - 18%
NYISO Study
LSEIRM
Requirements
LocationalCapacity
Requirements
ISONE OntarioPJM H-Q
11 NYCA Zones
22
New York ModelNYISO/NYSRC Relationship
NY StateReliabilityCouncil
(NYSRC)
IndependentSystem
Operator(NYISO)
DisputeResolution
Reliability Rules / Criteria
Compliance Data
23
NYSRC Relationship to NYISO
• NYSRC and the NYISO will function as two separate and distinct entities but work cooperatively
• NYSRC defines the reliability rules for operating the system• NYISO responsible for short term reliability of NYS power
system• NYSRC and NYISO will both participate at NPCC and
NERC/NAERO• NYSRC assesses and monitors NYISO's compliance with
reliability rules
24
NYSRC Relationship to NYISOCont’d
• NYISO provides NYSRC with data, reports, and assistance• NYISO provides reports to NYSRC describing performance of
NYS Power System• NYSRC reviews and approves triennial reviews and other
reliability reports prepared by the NYISO for submittal to NPCC/NERC
25
Functional RelationshipsBetween NYSRC & NYISO
FUNCTION NYSRC ROLE ISO ROLE
NYSRC Reliability Rules Develops RulesOperates system incompliance with Rules
Convey NYSRC Rulesand Procedures
Convey to ISOConvey applicable Rulesand Procedures to MarketParticipants
Compliance with RulesMonitors ISOcompliance withRules
Prepare compliancedocumentation inaccordance with NYSRCprocedures and timelines
26
Functional RelationshipsBetween NYSRC & NYISO
FUNCTION NYSRC ROLE ISO ROLE
ISO Non-Compliancewith Rules
Notify ISO of non-compliance actions tocorrect deficiencies
Correct deficiencies
Dispute ResolutionParticipate in processas required
Participate in process asrequired
Compliance with NPCCStandards
Review ISOcompliancedocuments submittedto NPCC
Submit compliancedocuments to NPCC andNYSRC for oversightreview
27
Functional RelationshipsBetween NYSRC & NYISO
FUNCTION NYSRC ROLE ISO ROLE
Market Participantcompliance with Rules
Review MPcompliance reportsprepared by ISO andfollow-up actions
Report to NYSRC, MPcompliance with Rules
LSE ReserveRequirements
Determine state-widereserve requirementsbased on ReliabilityRules
Determine LSE reserverequirements based onstate-wide requirementsand Reliability Rules
ISOStudies/Assistance forNYSRC
Request ISOsutdies/assistance
Preparestudies/assistance forNYSRC
ISO Liaison to NYSRCStaff representativeassigned