NEPLAN-Maintenance (RCM, CBM, TBM)
This document describes the software of the NEPLAN-Maintenance module. It is not
intended to give an overview over the maintenance strategies. A good overview over
different maintenance strategies and the NEPLAN-Maintenance philosophy can be
found here:
www.neplan.ch/downloads/public/NEPLAN-Maintenance-Strategies_e.pdf
The main features of the NEPLAN-Maintenance module are:
- Available sub-modules are:
o HV Components
o HV AIS Substations
o HV GIS Substations
o HV/MV Overhead line
o MV Substations
o MV Local Substations
o MV Cables- Data can be stored in any database (e.g. Oracle, MS-Access, SQL Server
etc.)
- Allows easy integration to existing ERP systems (e.g. SAP)
- Assessment criterion can be added or changed by the user
- Allows quickly to assess the conditions of the components
- Different charts give a useful overview over the overall conditions of the
components- A budgeting evaluation tools is available, which calculates the costs for the
following maintenance strategies:
o TBM Estimation (estimated time based maintenance)
o TBM (time based maintenance)
o CBM (condition based maintenance)
o RCM (reliability based maintenance)
- Integrates smoothly with our famous NEPLAN-Reliability module
- Can be excellently used a for reinvestment strategies
8/2/2019 NEPLAN Maintenance Descr
2/9
Overview NEPLAN-Maintenance Module
NEPLAN-Maintenance Software
The NEPLAN-Maintenanceassessment sheet editor allows theuser to freely configure any
assessment sheets withhis own criterions.
8/2/2019 NEPLAN Maintenance Descr
3/9
Component Assessment in NEPLAN-Maintenance
The picture below shows on the left side the assessment sheet of the currentcomponent. The diagram shows all conditions (y-axes) and all importances (x-axes)of all components (in this case circuit breakers). The actual circuit breaker to assessis colored differently. The user can define any filter to reduce the amount of displayedcomponents.
The condition of each component can easily be assessed with the freely configurable
assessment sheets.
8/2/2019 NEPLAN Maintenance Descr
4/9
Budgeting Evaluation Tool in NEPLAN-Maintenance
In NEPLAN-Maintenance a budgeting tool is included, which allows evaluating thecosts of the different maintenance strategies:
o TBM Estimation (estimated time based maintenance)
o TBM (time based maintenance)
o CBM (condition based maintenance)
o RCM (reliability based maintenance)
At your fingertips: budgeting of RCM and TBM can be easily compared
8/2/2019 NEPLAN Maintenance Descr
5/9
Chart Evaluation Tool in NEPLAN-Maintenance
The integrated chart manager shows for example the influence of each criterion to
the overall conditions of all components. Each criterion can be assigned to a cluster(e.g. operating condition, component type, etc.). NEPLAN allows evaluating theoverall conditions according to these clusters.
This chart shows the influence ofdifferent clusters to the overallconditions of all components.It shows for example the effectof all criterions which belong tothe Operating Conditions clustercompared to the other effectsof the other clusters.
8/2/2019 NEPLAN Maintenance Descr
6/9
Integration with NEPLAN-Reliability Module
The NEPLAN-Maintenance module can make use of the calculated results of ourfamous NEPLAN-Reliability module. The NEPLAN-Maintenance module integratessmoothly to the NEPLAN single line diagram. The conditions C, importance I and thedistances D (function of condition and importance, D = f(C, I)) can be displayed onthe single line diagram. The coloring according to C, I and D shows very quicklywhich components must be replaced or maintained first.
The NEPLAN-Maintenance module is at the moment the only RCM module on
the market, which integrates, with a robust network reliability module.
Integration of the NEPLAN-Reliability module with the NEPLAN-Maintenance module
8/2/2019 NEPLAN Maintenance Descr
7/9
Display of the maintenance and reliability results in the single line diagram
Result displayedat the circuit breakers
The results from the reliability calculation are combined with the condition evaluationof the maintenance module and displayed in the NEPLAN single line diagram. Thecoloring shows which equipment have to be replaced or maintained or just observed.
RUR_C3I=0.360C=33.0D=23.6
Itot=0.360
RUR_C4
I=0.360C=36.0D=25.7
Itot=0.360
RUR_C6I=0.376C=39.0D=27.8
Itot=0.376
RUR_C8I=0.376C=42.0D=30.0
Itot=0.376
RUR_C5
I=0.360C=60.0D=42.7
Itot=0.360
RUR_L1I=42.534C=63.0D=74.6
Itot=42.534
MVRUR1_AI=0.316
C=52.1D=37.1
Itot=0.239
MVRUR1_LT=3.991 h
Pr=18.712 min/yrW=0.153 MWh/yrC=811.135 /yr
MVRUR2_AI=0.316
C=33.7D=24.1Itot=0.239
MVRUR2_LT=3.991 h
Pr=18.712 min/yrW=0.153 MWh/yrC=811.135 /yr MVRUR3_A
I=0.187
C=44.4D=31.6
Itot=0.142
MVRUR3_LT=3.986 h
Pr=18.685 min/yr
W=0.076 MWh/yrC=403.811 /yr
MVRUR4_AI=0.474
C=50.5D=36.1
Itot=0.360
MVRUR4_L
T=1.395 hPr=49.590 min/yrW=0.247 MWh/yrC=2032.542 /yrMVRUR5_A
I=0.318C=48.7D=34.7
Itot=0.241MVRUR5_L
T=1.395 hPr=49.564 min/yrW=0.405 MWh/yrC=3331.212 /yr
MVRUR6_LT=6.786 h
Pr=241.163 min/yrW=0.985 MWh/yrC=7353.095 /yr
DORF-LS1I=0.357
C=66.0D=46.9
Itot=0.001
DORF-LS2I=0.371
C=11.0D=8.0
Itot=0.001
DORF-LS3I=1.627C=5.0D=4.7
Itot=0.006
DORF-LS4I=1.695C=14.0D=11.1
Itot=0.006
DORF-LS1I=0.357C=66.0D=46.9
Itot=0.001
DORF-LS2I=0.371C=11.0D=8.0
Itot=0.001
DORF-LS3I=1.627C=5.0
D=4.7Itot=0.006
DORF-LS4I=1.695C=14.0
D=11.1Itot=0.006
RCM Condition C
x >= 0.00000.0000
x >= 40.0040.00
x >= 60.0060.00
8/2/2019 NEPLAN Maintenance Descr
8/9
Display of the maintenance and reliability results in table form
The results from the reliability calculation are combined with the condition evaluationof the maintenance module and displayed in the NEPLAN table, which can also bepasted into MS-Excel.
8/2/2019 NEPLAN Maintenance Descr
9/9
More Information
More information can be found here:
NEPLAN:www.neplan.com
NEPLAN Brochure:http://www.neplan.ch/downloads/public/NeplanElectricity.pdf
Maintenance strategies:www.neplan.ch/downloads/public/NEPLAN-Maintenance-Strategies_e.pdf
Reliability:http://www.neplan.ch/sites/en/neplan_elec_calcmod_reliability_analysis.asp