NBO H4 Development
Monthly Coordination Meeting
October 2020 (Microsoft Team Meeting)
November 17th, 2020
1
AGENDA
❖Introduction / Safety Moment Video
❖Project Overview & Scope
❖Project Status Update
❖Project Contracting / Procurement
❖EPCI Water Injection Pipeline (UMD)
❖Onshore Fabrication / HUC (SFSB)
❖AOB
NBO H4 Development
Project Overview & Scope
4
NBO-4 well was drilled in 2Q-2017 to appraise the H4 discovery and
test upside targets
THE H4 RESERVOIR WAS FOUND OIL BEARING BY WELLS BOC-19/22 IN 2014
PM3 Northern Fields and H4 Reservoir▪ The H4 reservoir was found oil bearing in 2014
by the “near field” appraisal wells BOC-19 and
BOC-22 drilled from the BO-C platform
▪ Both wells were completed to oil producers in
2014 and have recovered approx. 4.9 mmstb (as
of Sept 2020)
▪ The NBO-4 appraisal well was drilled in Q2
2017 to appraise the H4 reservoir while testing
potential upside targets deeper horizons. NBO-4
has confirmed the H4 oil column. The upside
targets were found wet / uneconomic
▪ NBO-4 was successful in achieving the
objective to provide sufficient information to
continue the full development of H4
▪Early water injection required to protect
pressure depletion and maximize recovery
NBO H4 Development Project
5
5
Future development:
• 2 oil producers
• 4 water injectors
Well Spacing:
• 1.5 - 2.0 km
Depletion Mechanism:
• Water injection as secondary recovery
(pressure maintenance and sweep)
Base Case Volumetric:
• STOIIP: 46.6 MMSTB
• Incremental: 10.3 MMSTB (@ PSC
2027) and 17.6 MMSTB (@ field life
2050)
• EUR: 15.1 MMSTB (@ PSC 2027)
and 22.3 MMSTB (@ field life)
• Cumulative Production: 4.9 MMSTB
(as of Sept. 2020)
POWC 1998m TVDss
BO-B
BO-C
BO-D
NBO-4
NBO-4ST1 (EXISTING)
NBO-4ST2 (EXISTING)
0 2 km
N
BOC-22 – (EXISTING)
BOC-19 (NBO-3 - EXISTING)
LEGEND
Oil Producer
Water Injector
P&A well
Platform
Development Plan
(Post-Drill NBO-4)
TE (WI-ERD)
6B (OP-ERD)
3B (WI-ERD)
3C (OP)
RR (WI)
DD (WI)
NEW
NEW
NEW
NEW
NEW
NEW
EXISTING
EXISTING
EXISTING
NBO H4 Development Project NBO H4 Development Plan
6
NBO H4 development Project (2019-2021)
• 6 infill wells ( 4 Water Injectors, + 2 Oil Producers)
• New Flexible Water Injection pipeline from BOD to BOC
Platform.
• Brownfield works on BOD and BOC; BOC requiring
deck extension to accommodate 4 new slots
Existing Facilities
BOC Platform : Spare slots, requirement for Deck
extension for more slots.
BOC – BOD 6 km, 12” Oil Pipeline with available
ullage.
BOD Platform :
• Water Injection Facilities with spare ullage.
• Separation and processing facilities
BOA CPP
BOD WHRP
BOC WHRPBOB WHRP
12”, 5km
18”, 2km
Legend:
Oil Pipeline
Water Injection Pipeline
6”, 5km
NBO H4 Development Project Project Scope
7
TOPSIDES
MODIFICATION & HUC
DRILLING &
COMPLETIONS
UMD
Cost + Materials
SUBSEA
PIPELINE
SAPURA SCOPE
• Brownfield Works on BOD & BOC for the connection of the
new water pipeline.
• Deck Extension at BOC to accomodate 4 new Well Slots.
• Brownfield Works for the Hook Up & Commisioning of the
new Wells
+ +
TIME &
RESOURCES
CONTRACT
TIME & RESOURCES
CONTRACT
LUMP SUM
(MILESTONES)
DRILLING SCOPE
• 6 new infill Wells
4 Water Injectors
2 Oil producers
• PVD 3 drilling rig.
PIPELINE SCOPE• 6 km Water Injection Flexible Pipeline (6”)
• Transport water from BOA/BOD to BOC
• Lump Sum contract for the Supply & Installation of subsea
flexible pipeline and J Tubes & connections.
NBO H4 Development Project Project Scope
NBO H4 Development
Project Status Update
9
Target First Water: July 2020(Baseline)
First Oil: Mar 2022 (Forecast)
First Water: Dec 2021 (Forecast)
Target First Oil: Nov 2020(Baseline)Time Now
Sanction Award EPCI Rig Arrival
R2
WTGCUMMULATIVE
PLAN R0 PLAN R2 ACTUAL VAR R2Progress as of 26-Oct-20
TOPSIDE MODS-BOC/BOD/BOA 6.90% 97.60% 92.41% 92.54% 0.13%
BEC (DDE) 5.79% 100.00% 100.00% 100.00% 0.00%
SFSB (PROC/FAB/HUC) 78.15% 96.93% 90.29% 90.46% 0.17%
RML SUPPLIED ITEM 16.06% 100.00% 100.00% 100.00% 0.00%
SUBSEA EPCI 11.13% 100.00% 100.00% 99.87% -0.14%
WELLS / DRILLING 78.48% 70.95% 12.74% 12.74% 0.00%
OWNER 3.49% 72.36% 51.35% 51.35% 0.00%
Overall Progress 100.00% 75.97% 29.30% 29.29% -0.01%
* Based on Schedule Rev.2
NBO H4 Development Project
Overview of Current Progress
10
NBO H4 Development Project
Overall Project Schedule Rev 2*Based on drilling defers to Q4 2021 (WP&B 2021 Submission)
2018 2019 2020 2021 2022
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
PRCO
Petronas Milestone Reviews
Drilling & Completion Definition Studies
Brownfield Modifications
MR4 MR5WMRC
Hook-up & Commissioning
MR3MR2
FDP Preps.submission & Approval
Project Sanction
Conceptualization & Definition
Drilling Program WINJ wells
Flow Line tie-ins
Repsol Technical Review
Execute scope (Drilling)Contracting
PSUA
Procurement & Delivery of LLI
Vis. & Concept Select Studies
PRSU
Drilling Program OP
NBO H4 Development
PREP
WMRC Preparation
CA
Contracting of FEED studies
Opcom
FEED
1st Oil1st Water
Execute scope (Facilities)
MonsoonMonsoon
EPCI Contracting
MR1 Update
Detailed Engineering EPCI
First Water / First Oil
Detailed Engineering Brownfield
Transport & Installation of Flexi/Non-Metal
Procurement & Delivery of Flexi/Non-Metal
Milestones
PRD
Platform Ready for Rig move-in
Procurement of Delivery of Other LLI
Monsoon
TR3D
Brownfield Onshore Fabrication
11
Progress Highlights/Overview
PROJECT MANAGEMENT
▪ EPCI Lessons Learnt session held at Maya Hotel on 1-Oct-20 with attendance from MPM/ PCSB/
RML/ UMD. EPCI Completion Ceremony (Hi-Tea) was held at The Duchess Place in the afternoon
with all the top management present.
▪ EPCI Lessons Learnt draft issued by UMD for review. Final EPCI lessons learnt register issued on 9-
Oct-20 after incorporating comments.
▪ Letter notifying MPM (RDM) about deferment of rig move in October 2021 issued on 8-Oct-20 by
Technical Services Manager.
▪ Based on expected HUC completion by mid Nov 2020, RML to present the Close Out presentation
slides to MPM by end December 2020 and issue the Close Out Report by end Jan 2021.
▪ EEZ Submission Review and Notification to MKN packages issued to MPM via SharePoint as per
road-map requirements.
▪ Flowline tie-in scope is minor and does not warrant bidding of another new HUC Contract. As the
scope can be performed by TMM Contractor, PMT have proposed OCS Revision specific to HUC
Services for RML SCM further action – SCM has sent letter to MPM (Procurement Group) informing
on the latest contracting strategy.
▪ Received comments from Production Operation Manager on PRSU and PSUA - proposed to have
an internal fit-for-purposes sessions for these rather than a full blown review.
▪ Engaged MPM for Technical Concurrence of Covid-19 ABR (Additional Budget Request). 2 sessions
were conducted and Minutes of Meeting (MoM) was submitted to MPM on 26th Oct 20. Received
signed MoM on 28th Oct 20 which was given to Planning group.
NBO H4 Development Project
12
Progress Highlights/Overview
PROJECT MANAGEMENT (Cont.)
▪ Blackstone Eng (BEC) submitted Org chart & CV of the proposed personnel for as-builting works.
The quotation seems to be on high side and BEC was asked to provide better manhours/cost for the
as-builting exercise. A negotiation meeting to be scheduled for BEC to provide the final quotation
accordingly.
▪ All offshore workers (Malaysian + Foreign) to perform rtPCR test for sign on/sign off based on new
Ministry Of Health (MOH) directive. For sign-off, workers will be quarantine until the result is
available. MOH agreed to waive the requirement for 14 days quarantine for sign-on after
engagement between MPM HSE/POM with MOH/MKN – Covid-19 rtPCR implemented for offshore
crew mob/demob.
▪ Sapura has been instructed to start compiling HUC Lesson Learnt and Final Documentation.
Similarly, Repsol personnel was asked to also provide the input for LL. Format for LL and sample has
been forwarded for references.
▪ Completed compilation of vendor data softcopy for RML supplied items (only hardcopy outstanding)
which will be incorporated into the final documentation.
▪ Oct. 2020 Monthly Coordination meeting is tentatively planned for 17-Nov-20 via Microsoft Teams
NBO H4 Development Project
13
Progress Highlights/Overview (cont’d.)
EPCI WI PIPELINE
▪ EPCI Lessons Learnt session & Completion Ceremony held on 1-Oct-20 with attendance from
MPM/ PCSB/ RML/ UMD.
▪ EPCI Final Doc 95% completed. Reviewed draft of UMD project close out report and progressively
incorporated final comments from RML (As built schedule and schedule analysis)
▪ UMD is agreeable to the arrangement of deferred payment tax invoices submission by 1st./2nd. Dec
2020.
▪ UMD received RO from RML for Covid-19 cost.
NBO H4 Development Project
14
Progress Highlights/Overview (cont’d.)
HUC / HTI
▪ Offshore HUC team completed all pipe supports installation on 13th Oct and also completed all the
mods (fit up & welding) for conductor guide/cone at cellar deck. Remaining works only to clear
punchlist for Structural, Piping and E&I.
▪ Surveyors for the vertical misalignment checks were mobilized offshore on 21-Oct-20. Completed
dimensional survey for Conductor guide/guard and new deck extension on 26th Oct 20. Finding
show misalignment were well within tolerance and survey team demob from offshore site on 28-
Oct-20.
▪ Completed HUC piping punchlist clearing (marking pipe spool, touch up paint, etc) on 26th Oct 20.
▪ Mobilized E&I personnel (3pax) on 28th Oct 20 for Instrument punchlist clearance. Expected to
complete all punchlist clearance by early/mid Nov 20.
▪ Sapura progressively retrieve and backload all equipment and material from offshore. Target for
demob of personnel on 4th. Nov as per planned except for E&I crews to complete the punchlist
(late mob due to new regulation by MOH). Expected full completion and demob by 11th Nov. 2020.
▪ Ongoing data population for ITR check sheet in Omega PCS.
▪ Ongoing handover piping material (Surplus & Flowline spools) from Sapura yard to RML
Marshalling yard in Kemaman supply base (KSB).
NBO H4 Development Project
15
Budget Overview
▪ PCSB Approval of H4 Execution AFE on 6-Sep-19
▪ Received approval letter from MPM on 23-Sep-19 for Budget request conversion from "Contingent to
Firm"
▪ Received PVEP Approval Letter of the revised 2019 WP&B and 2020 WP&B on 25-Sep-19
▪ Received PVEP Approval Letter for FEED Supplemental and Execution AFEs (Facilities) on 26-Sep
▪ Received H4 drilling budget approval for 2020 WPB end Dec 2019.
▪ Drilling AFE - to be resubmitted
▪ Received Final Investment Approval (FIA) for H4 development project with a total of US$ 147.51 Mil
on 28-May-20.
▪ 2021 WP&B for Facilities & Drilling has been submitted to MPM.
▪ Drilling rig existing contract has been terminated and new competitive bidding is in-progress –
Tender Plan Plan approved and the Bid documents have been sent to bidders on 30th Oct
20. Bids closing date on 30 Nov 2020
NBO H4 Development Project
16
EPCI Lessons Learnt session and Completion Ceremony held on 1-Oct-20 with attendance from
MPM/ PCSB/ RML/ UMD. ✓
Letter notifying MPM (RDM) about deferment of rig move in October 2021 issued on 8-Oct-20 by
Technical Services Manager. ✓
Received Technical Concurrence of Covid-19 cost by MPM line department. ✓
Flowline tie-in scope is minor and does not warrant bidding of another new HUC Contract. The scope
will be performed by TMM Contractor (Tanjong T7) ✓
EPCI Final Doc 95% completed ✓
Completed all the mods (fit up & welding) for conductor guide/cone at cellar deck. Completed
dimensional survey and HUC piping punchlist clearing (marking pipe spool, touch up paint, etc) on
26th Oct 20 ✓
Target for demob of personnel on 4th. Nov as per planned except for E&I crews to complete the
punchlist. Expected full completion and demob by 11th Nov. 2020. ✓
Project Value
➢ CAPEX @ Sanction 153.6 MUSD (Gross – including FEED) ✓
➢ FIA 147.51 MUSD (Execution) ✓
➢ First Oil Target Q4 2020, forecasted now to be Q1 2022 ✓
(based on latest 2021 WPB submission)
➢ PSC Fullfill Remaining PSC Commitment ✓
NBO H4 Development Project
H4 Developments Update Summary
17
▪ Outstanding official resolution letter from PVN on PSC Minimum work commitment issue - Deliberation
on this matter is up to ministerial level in Vietnam. However, a jointly written letter has been issued by
MPM/PVN acknowledging H4 project is viable and implying work should proceed accordingly.
▪ Impact on deferment of Drilling on H4 project– ensure continuity of experienced team to perform the
complex ERD wells.
▪ Impact due to falling prices of oil worldwide - Deferment of drilling campaign to optimize Capex
▪ Availability of rig on time and within expected rates in 2021. Early start for competitive bidding of new
rig contract and to negotiate for rates in tandem with present market oil prices.
Areas of Concern
NBO H4 Development Project
18
Areas of Concern
➢ Follow up with SCM on the info letter to MPM / Procurement Council on HUC Services flowline
installation will be performed by TMM Contractor (T7).
➢ Oct Monthly Coordination Meeting planned for 17th Nov. 2020 via Microsoft Teams.
➢ To complete remaining punchlist works by early Nov. before the monsoon season sneaks in.
➢ Completion of Final Documentation and Close-Out Report from UMD & Sapura
➢ Kick start the H4 Facilities Project Close out presentation and report
Next Step:
NBO H4 Development Project
NBO H4 Development
Project Contracting/Procurement
20
Procurement StatusNBO H4 Development Project
RML PROCURED ITEMS
No. Packages Material Status ETA
1 DBB DELIVERED. Item closed. 16-Mar-20
2 SDSS Pipe DELIVERED. Item closed. 19-Jan-20
3 SDSS & HSCS Fitting Flanges DELIVERED. Item closed. 23-Dec-19
4 SDSS Clamp DELIVERED. Item closed. 28-Feb-20
5 Choke Valve DELIVERED. Item closed 9-July-20
6 SDV DELIVERED. Item closed. 13-May-20
7 PCSS DELIVERED. Item closed. 28-Feb-20
8 WHCM DELIVERED. Item closed. 11-Feb-20
SAPURA PROCURED ITEMS
1. Delivery Completed for all 56 packages.
21
Procurement Status (cont.)NBO H4 Development Project
DRILLING & COMPLETION CONTRACTS STATUS
Package Status QtyPackage Status as of
28/08/2020
Current
Contract
Expiry Date
Estimated
Contract Require
ment Date
Remark
TOTAL REQUIRED CONTRACT REQUIRED FOR H4 = 36
1
CONTRACT IN
PLACE /
EXISTING PA /
CONTRACT
EXTENSION
APPROVED
12
Tubular Handling 10.11.2021 20-Dec CONTRACT IN PLACE
Mud Logging 31.10.2022 21-Feb CONTRACT IN PLACE
Liner Hanger 13.10.2021 21-Feb CONTRACT IN PLACE
QA/QC Consultation 31.12.2021 21-Mar CONTRACT IN PLACE
Mud Consultancy Services 14.02.2022 21-Mar CONTRACT IN PLACE
OCTG 31.12.2021 20-Dec CONTRACT IN PLACE
Completion Equipment 30.05.2022 20-Dec CONTRACT IN PLACE
Base Oil 18.03.2023 21-Feb CONTRACT IN PLACE
Automotive Diesel Oil 20.03.2025 21-Feb CONTRACT IN PLACE
Casing & Cementing Accessories 31.12.2022 20-Dec CONTRACT IN PLACE
Cementing Equipment Services 18.06.2022 20-Dec CONTRACT IN PLACE
Tubing Conveyed Perforation (TCP) (Mini bid) 28.07.2021 21-Mar CONTRACT IN PLACE
2PREPARATION
OF PAPER8
EWL (New Tender - Comp. Bid) - 20-DecReceived PETRONAS' further comment on 24/08 and to respond by
26/08. ITB Preparation.
Debris Survey (New Tender - Comp. Bid) - 21-FebTP signed. Presented at TC3 25/08. To relook the technical eval
criteria, list of bidders and SOW. Issued screening 27/08.
Relief Well & Well Control Studies (Sole
Source) - 20-Dec
Pre-Qualification validation sent to bidders 25/08. Closing 27/08.
User to raise PR.
Jack-Up Drilling Rig (New Tender - Comp.
Bid))- 21-Mar
TP signed and submitted to PETRONAS. Submitted Draft ITB
Version 2 to George. Discussion on the rig TP ( 12/8) on the rigs
requirement. Pending technical comments from MPM Tech review.
PVN approved on TP 19/8.
Gyro (New Tender) - ITB - 21-FebTP routed for approval on 5/8. Paper all signed on 10/8 . TC3 on
18/8. Amended paper approved 25/08. To issue ITB
API Barite (New Tender - Comp Bid) - TP - 21-Jan ITB issued on 24/8. Closing 7/9.
Machine Shop (New Tender - Comp Bid or
Extension)- 21-Mar
Screening/market survey to postpone till end of August as we are
awaiting primary discount rate from OMS by 21/8 & also as contract
is expiring by 26/5/2021- no response from OMS as of 25/8/2020
22
Procurement Status (cont.)NBO H4 Development Project
DRILLING & COMPLETION CONTRACTS STATUS
3 IN PROGRESS 12
Managed Pressure Drilling (New
Tender - Comp Bid) - Pre-Q- 21-Jan
Technical review for screening result on going. To launch tender in
mid Sept.
Cased Hole Downhole Tractoring
(New Tender - Comp Bid) - TBE- 21-Jan
ITB issued to bidders on 10/7. Bid closing extended to 17/8. TBE on
going.
Hole Enlargement Tool (Mini Bid) -
RFP- 21-Mar
RFP issued on 15/7; closing 12/8. Technical review. Target to compete
Technical evaluation stage (5 weeks ) - 9/9)
Rig Positioning (New Tender - Comp.
Bid) - Screening- 21-Mar
Screening/market survey on 5/8. Closing on 13/8. Received response
from Vendor and 7 bidders replied to market survey including Vendor.
(To discuss on further action) To complete market survey analysis.
Drilling Fluid (Mini Bid Pan Mal) - TBE 21-FebITB issued on 17/07. Closing 10/08. Bid opened 11/08. Technical
evaluation ongoing. Target TER 29/09.
DD/MWD/LWD (Mini Bid) - ITB - 20-Dec
ITB issued on 17/07. Bid closing date extended to 24/08. Exceptions
forwarded to Legal on 04/08. Bid opened 25/08. Technical evaluation
ongoing. Target TER 14/10.
Wellhead and Christmas Tree (Sole
Source) - ITB- 20-Nov
ITB issued on 30/07, closing on 24/08. Bid opened 25/08. Evaluation
ongoing. Target TCEAR 24/09.
Drilling Rental Tools (New Tender -
Comp. Bid) - ITB- 20-Dec ITB issued on 10/08. Closing on 01/09.
Conductor Installation (New Tender -
Comp. Bid) - ITB- 20-Dec ITB issued 21/8. Closing 17/9.
Fishing Equipment & Service (New
Tender - Comp. Bid) – TBE- 20-Dec
Bid closed on 6 /7. Tech bids opened on 7/7. Tech evaluation ongoing (
45 days ). Target TER on 15/09.
Drill Bits (Mini bid) – RFP - 21-Feb RFP issued on 05/08. closing on 07/09.
Supply Vessels (AHTS & PSV) (Mini
Bid) – WRP- 21-Mar Technical requirement in preparation.
23
Procurement Status (cont.)NBO H4 Development Project
DRILLING & COMPLETION CONTRACTS STATUS
4
NOT YET STARTED
(Competitive Bidding/Single
Source/Farm in)
4
Permanent Downhole Gauge (PDG) -
for Service & Material (sole source
proprietary with Halliburton - service)
21-Feb To start TP in November 2020
Drilling Performance - PRONOVA (sole
source proprietary)- 21-Nov To prepare PR and launch tender – by Nov 2020
Marine Consultancy (New Tender - Comp.
Bid)- 21-Mar To prepare PR and launch tender – by Sept 2020
Seabed Assurance (New Tender - Comp.
Bid)- 21-Mar To prepare PR and launch tender – by Sept 2020
5CANCELED
(included in other contract)2
Liquid Mud Plan - -Included in Drilling Fluid Chemical, Equipment & Service contract
- Mini Bid
Class G Cement - -
To include the scope in Cementing Contract. Petronas Catman to
proceed with Change To Contract to include Class G Cement in
Cementing Contract.
24
NBO H4 Project Development PlanProject Photos – Project Completion Ceremony
NBO H4 DevelopmentA
25
NBO H4 Project Development PlanProject Photos – Project Completion Ceremony
NBO H4 DevelopmentA
26
NBO H4 Project Development PlanProject Photos – Project Completion Ceremony
NBO H4 DevelopmentA
27
NBO H4 Project Development PlanProject Photos – Project Completion Ceremony
NBO H4 DevelopmentA
28
NBO H4 Project Development PlanProject Photos – Project Completion Ceremony
NBO H4 DevelopmentA
29
NBO H4 Project Development PlanProject Photos – Project Completion Ceremony
NBO H4 DevelopmentA
30
NBO H4 Project Development PlanProject Photos – Lesson Learnt in Session
NBO H4 DevelopmentA
31
NBO H4 Project Development PlanProject Photos – Flexible Pipeline Offshore Campaign
NBO H4 DevelopmentA
32
NBO H4 Project Development PlanProject Photos – Flexible Pipeline Offshore Campaign
NBO H4 DevelopmentA
33
NBO H4 Project Development PlanProject Photos – Flexible Pipeline Offshore Campaign
NBO H4 DevelopmentA
34
NBO H4 Project Development PlanProject Photos – Onshore –Consolidation of Flowline Tie-in spool for Handover
NBO H4 DevelopmentA
View of spool to be handover to T7 – well head tie-in spool secured into skid for storage
View of spool to be handover to T7 – well head tie-in spool stored at HUC marshalling yard
35
NBO H4 Project Development PlanProject Photos – Onshore –Consolidation of Flowline Tie-in spool for Handover
NBO H4 DevelopmentA
Fabricated pipe rack for storage
36