MOBILE DISTRICTFY 2007
DREDGING PROGRAM
MOBILE DISTRICTFY 2007
DREDGING PROGRAM
US Army Corps of EngineersMobile District
US Army Corps of EngineersMobile District
NAD/SAD REGIONAL DREDGING
MEETING/WEDA
NAD/SAD REGIONAL DREDGING
MEETING/WEDA
Mobile District Navigation Projects Mobile District Navigation Projects
5 Inland Waterways5 Inland Waterways
2200 Miles of Inland Waters2200 Miles of Inland Waters
7 Deep Water Harbors7 Deep Water Harbors
22 Shallow Draft22 Shallow Draft
FLFL
GAGA
TNTN
MSMS
Panama Panama City City
Port Port St. JoeSt. Joe
Bayou La BatreBayou La Batre PensacolaPensacola
PascagoulaPascagoula
GulfportGulfport
GIWW
FlintRiver
ALAlabamaRiver
Tenn-TomWaterway
TombigbeeRiver
MobileMobile
Black Warrior River
Chattahoochee River
Apalachicola River
SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT
FY07FY06 FY08Hopper Dredge
Maintenance Dredging
Scheduled FY07 Dredging Work in Mobile District
Mobile Hbr Bay/Bar (Rental)
Manson/ Glenn Edwards
Mobile Hbr Bay/Bar (Rental)
$4M IDIQB.O. OCT 06
Mobile Hbr Bay/Bar (Rental)
$4M IDIQB.O. JAN 07
Mobile Hbr Bay/Bar (Rental)
$4M IDIQB.O. Jun 07
Mobile Hbr Bay/Bar (Rental)
$4M IDIQ (Contingency)
Pascagoula Bar (Rental)
1MCY IDIQ
Used for emergency work, to be opened by amendment
B.O. MAR 07
Used for emergency work, to be opened by amendment
Mobile Hbr Bay/Bar (Rental)
$4M IDIQ (Contingency)
Panama City Beach Nourishment
Unit Price 500KCYB.O. FEB 07
Type of Work: MaintenanceDepth: 47’ Bar and 45’ BayWidth: 600’/400’Length: 42 MilesQuantity: 1.0/2.25 McyType of Material: Sand, Silt and ClayPlacement Area: Ocean D/ADistance to Placement Area: 30 MilesType of Equipment: HopperSmall Business Set Aside: NoLast Dredged: 2006Contract Amount: $1,000,000-$5,000,000Schedule: Continuous
Type of Work: MaintenanceDepth: 47’ Bar and 45’ BayWidth: 600’/400’Length: 42 MilesQuantity: 1.0/2.25 McyType of Material: Sand, Silt and ClayPlacement Area: Ocean D/ADistance to Placement Area: 30 MilesType of Equipment: HopperSmall Business Set Aside: NoLast Dredged: 2006Contract Amount: $1,000,000-$5,000,000Schedule: Continuous
Mobile HarborChannel
Mobile HarborChannel
Type of Work: MaintenanceDepth: 44’Width: 450’Length: 6.2 MilesQuantity: 1.0 McyType of Material: Sand, Silt and ClayPlacement Area: Ocean D/ADistance to Placement Area: 2-3 MilesType of Equipment: HopperSmall Business Set Aside: NoLast Dredged: 2004Contract Amount: $1,000,000-$5,000,000Schedule: Begin late March – End early
June
Type of Work: MaintenanceDepth: 44’Width: 450’Length: 6.2 MilesQuantity: 1.0 McyType of Material: Sand, Silt and ClayPlacement Area: Ocean D/ADistance to Placement Area: 2-3 MilesType of Equipment: HopperSmall Business Set Aside: NoLast Dredged: 2004Contract Amount: $1,000,000-$5,000,000Schedule: Begin late March – End early
June
Pascagoula BarChannel
Pascagoula BarChannel
SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT
FY07FY 06 FY08Hydraulic Pipeline Dredge
Maintenance Dredging
Scheduled FY07 Dredging Work in
Mobile District
Pascagoula Sound (Rental)
Mike Hooks Missouri H 27” 2M CY
Gulfport Sound Channel (Rental) 1.5M CY
Pascagoula Sound (Rental)
2MCY IDIQ
B.O. May 07
BWT/GIWW (Rental)
$15M IDIQ
Tenn-Tom/ Ala River (Rental)
$10M IDIQ
Mobile River (Rental)
800KCY IDIQ
B.O. MAY 07
B.O. FEB 07
B.O. FEB 07
Harrison County Beaches
Unit Price 800KCYB.O. NOV 06
Type of Work: MaintenanceDepth: 36’Width: 220’Length: 12 MilesQuantity: 1.5 McyType of Material: Silt, Clay and FluffPlacement Area: Open Water D/ADistance to Placement Area: 5-10 K FeetType of Equipment: Large CutterheadSmall Business Set Aside: NoLast Dredged: 2006Contract Amount: $1,000,000-$5,000,000Schedule: Begin early February – End mid
May
Type of Work: MaintenanceDepth: 36’Width: 220’Length: 12 MilesQuantity: 1.5 McyType of Material: Silt, Clay and FluffPlacement Area: Open Water D/ADistance to Placement Area: 5-10 K FeetType of Equipment: Large CutterheadSmall Business Set Aside: NoLast Dredged: 2006Contract Amount: $1,000,000-$5,000,000Schedule: Begin early February – End mid
May
Gulfport SoundChannel
Gulfport SoundChannel
On-Going Dredging Work inMobile District
Black Warrior and Tombigbee Rivers, Alabama River Tennessee-Tombigbee Waterway, GIWW
Black Warrior and Tombigbee Rivers, Alabama River Tennessee-Tombigbee Waterway, GIWW
Type of Work: MaintenanceDepth: 9’ – 12’Width: Various widthsLength: Various LengthsQuantity: RentalType of Material: Sand/GravelPlacement Area: Upland and Within BanksDistance to Placement Area: Various DistancesType of Equipment: 18” - 24” CutterheadLast Dredged: 2006Contract Amount: $1,000,000 - $5,000,000Schedule: Summer 2007
Type of Work: MaintenanceDepth: 9’ – 12’Width: Various widthsLength: Various LengthsQuantity: RentalType of Material: Sand/GravelPlacement Area: Upland and Within BanksDistance to Placement Area: Various DistancesType of Equipment: 18” - 24” CutterheadLast Dredged: 2006Contract Amount: $1,000,000 - $5,000,000Schedule: Summer 2007
Tenn-TomWaterway