Post on 16-Jan-2016
Mid-City ExpositionLight Rail Transit
ProjectClosed Session Presentation
March 2, 2006
Exposition Metro Line Construction Authority
Expo Line DB Contracting Authority
Public Utilities Code 132610
(a) The authority has all of the powers necessary for planning, acquiring, leasing, developing, jointly developing, owning, controlling, using, jointly using, disposing of, designing, procuring, and building the project, including . . .
(4) Contracting with public and private entities for the planning, design, and construction of the project. These contracts may be assigned separately or may be combined to include any or all tasks necessary for completion of the project.
Compliance with FTA Legal Requirements
FTA Best Practices Manual
▪ NEPA Compliance
▪ Thompson Colburn, LLP (Kent Woodman)
Best Value Procurement
A combination of price and technical (non-price) considerations.
▪ Provides greater assurance of performance resulting in:
▪ Enhanced Community and Stakeholder responsiveness.
▪ Cost effective design.
▪ Timely Project delivery.
▪ Recommended Proposer need not be the one with the overall lowest
Price in order to provide the Best Value
Procurement Background
• September 2005, Authority Board authorized solicitation of
proposals for Negotiated Design-Build Contract.
• January 2006, Proposals received and evaluated.
• February 2006, Authority Board authorized CEO to negotiate with
top ranked proposer, FCI/Fluor/Parsons.
• February 2006 negotiations focused on the following:
• Exceptions to the RFP identified by FCI/Fluor/Parsons
• Clarification of elements of their proposal.
• Review of price proposal to determine if fair and reasonable.
Best Value Evaluation Criteria and WeightsTECHNICAL FACTORS (70%)
Management and Organization Structure; Qualifications and Experience
Construction Plan, Project Management Plan, and Overall Approach
to the Work
Contracting Plan
Construction Safety Proposal and Record
Quality of the Community, Public and Business Mitigation
Commitments
PRICE (30%) Design Fee and additional cost
Professional Services Fee and additional cost
Construction Fee
Insurance Costs
Technical (non-price) factors rated on the basis of a 0 to 20 point scale
Instructions clearly laid out how to use this scale for each sub-criterion within the five evaluation criteria categories
Instructions clearly laid out how to use this scale for each sub-criterion within the five evaluation criteria categories
• EXCEPTIONAL (15 to 20)
• GOOD (10 to 15)
• ACCEPTABLE (5 to 10)
• UNACCEPTABLE TO BARELY ACCEPTABLE (1 to 5)
• NO INFORMATION PROVIDED (0 points)
• EXCEPTIONAL (15 to 20)
• GOOD (10 to 15)
• ACCEPTABLE (5 to 10)
• UNACCEPTABLE TO BARELY ACCEPTABLE (1 to 5)
• NO INFORMATION PROVIDED (0 points)
Technical (non-price) scores
• Scores determined by five independent subcommittees, one for
each major evaluation criterion
• 19 individuals served on these committees (3 or 4 per committee)
• Each person served on only one subcommittee
• Subcommittees chaired by one member and scores verified by
him/her
• All three proposers were consistently rated in the Good to
Exceptional range in all 5 evaluation criteria
• Scores determined by five independent subcommittees, one for
each major evaluation criterion
• 19 individuals served on these committees (3 or 4 per committee)
• Each person served on only one subcommittee
• Subcommittees chaired by one member and scores verified by
him/her
• All three proposers were consistently rated in the Good to
Exceptional range in all 5 evaluation criteria
1.) Los Angeles Metro, Rail Operations
2.) Los Angeles Metro, Executive Office Construction, Project Management
3.) Los Angeles Metro, Executive Office Construction, Engineering
4.) Los Angeles Metro, Construction Management
5.) Los Angeles Metro, Community Relations
6.) RTD/Denver
7.) Regional Transportation Commission of Southern Nevada/Las Vegas
8.) UTA/Salt Lake City
9.) San Diego Assoc. of Governments
10.) Los Angeles County Dept. of Public Works
1.) Los Angeles Metro, Rail Operations
2.) Los Angeles Metro, Executive Office Construction, Project Management
3.) Los Angeles Metro, Executive Office Construction, Engineering
4.) Los Angeles Metro, Construction Management
5.) Los Angeles Metro, Community Relations
6.) RTD/Denver
7.) Regional Transportation Commission of Southern Nevada/Las Vegas
8.) UTA/Salt Lake City
9.) San Diego Assoc. of Governments
10.) Los Angeles County Dept. of Public Works
Subcommittee Agencies
11.) Sound Transit/Seattle
12.) Caltrans District 7
13.) Los Angeles Department of Transportation
14.) Bay Area Rapid Transit (BART)/ San Francisco
15.) LA Department of Public Works
16.) Orange County Transportation Authority/ OCTA
17.) Culver City Transportation Dept
18.) City of Santa Monica Public Works
19.) Los Angeles City, Engineering
11.) Sound Transit/Seattle
12.) Caltrans District 7
13.) Los Angeles Department of Transportation
14.) Bay Area Rapid Transit (BART)/ San Francisco
15.) LA Department of Public Works
16.) Orange County Transportation Authority/ OCTA
17.) Culver City Transportation Dept
18.) City of Santa Monica Public Works
19.) Los Angeles City, Engineering
Subcommittee Agencies (continued)
Sealed price proposals opened only after all technical scoring was completed
• No visibility of prices by any of the 19 technical subcommittee
members
• Price proposals checked for completeness
• No visibility of prices by any of the 19 technical subcommittee
members
• Price proposals checked for completeness
Best Value Scores then were calculated per the RFP formula
• Technical (non-price score) worth 70%
• Price worth 30%
• Technical (non-price score) worth 70%
• Price worth 30%
Scoring Summary Sheets for Each Technical Subcommittee
Subcommittee 1
ScoresMember
1Member
2Member
3Member
4Overall Average
FCI/Fluor/Parsons 16.55 17.53 17.30 17.01 17.10
Kiewit/Stacey and Witbeck JV
19.27 18.92 18.57 19.78 19.14
Mid-City Constructors JV (Granite/Brutoco)
16.95 17.78 17.82 17.37 17.48
Management and Organization Structure; Qualifications and Experience (20 points)Management and Organization Structure; Qualifications and Experience (20 points)
Subcommittee 2
ScoresMember
1Member
2Member
3Overall Average
FCI/Fluor/Parsons 12.4 13.8 13.8 13.3
Kiewit/Stacey and Witbeck JV
13.1 13.9 13.8 13.6
Mid-City Constructors JV (Granite/Brutoco)
11.1 13.5 13.0 12.5
Construction Plan, Project Management Plan, and Overall Approach to the Work (20 points)Construction Plan, Project Management Plan, and Overall Approach to the Work (20 points)
Subcommittee 3
ScoresMember
1Member
2Member
3Member
4Overall Average
FCI/Fluor/Parsons 16 16 17 15 16.00
Kiewit/Stacey and Witbeck JV
15 15 14 13 14.25
Mid-City Constructors JV (Granite/Brutoco)
16 16 14 13 14.75
Construction Plan (20 points)Construction Plan (20 points)
Subcommittee 4
ScoresMember
1Member
2Member
3Overall Average
FCI/Fluor/Parsons 17.84 18.00 17.50 17.78
Kiewit/Stacey and Witbeck JV
17.65 18.00 18.15 17.93
Mid-City Constructors JV (Granite/Brutoco)
17.00 17.50 17.15 17.22
Construction Safety Proposal and Record Plan (20 points)
Construction Safety Proposal and Record Plan (20 points)
Subcommittee 5
ScoresMember
1Member
2Member
3Member
4Overall Average
FCI/Fluor/Parsons 12 14 11 10 12
Kiewit/Stacey and Witbeck JV
13 16 15 13 15
Mid-City Constructors JV (Granite/Brutoco)
16 20 16 17 18
Quality of the Community, Public and Business Mitigation Commitments (20 points)
Quality of the Community, Public and Business Mitigation Commitments (20 points)
Technical Evaluation Total Score
(1) (2) (3) (4) (5)
Sub-committee
1
Sub-committee
2
Sub-committee
3
Sub-committee
4
Sub-committee
5
Total Technical
Score (Sum of 1 thru 5)
Normalized Technical
Score
FCI/Fluor/Parsons 17.10 13.30 16.00 17.78 12.00 76.18 95.0Kiewit/Stacey and Witbeck JV 19.14 13.60 14.25 17.93 15.00 79.92 100.0Mid-City Constructors JV (Granite/Brutoco) 17.48 12.50 14.75 17.22 18.00 79.95 100.0
Price Score Calculation
(1) (2) (3) (4)
Design FeeProfessional Services Fee
Construction Fee
Insurance Costs
Total Price (Sum of 1
thru 4)Normalized Price Score
FCI/Fluor/Parsons 5,550,000 12,187,000 27,450,000 7,320,000 52,507,000 100.0
Kiewit/Stacey and Witbeck JV 11,161,827 56,876,843 15,094,179 5,874,699 89,007,548 30.5 Mid-City Constructors JV (Granite/Brutoco) 14,736,940 15,629,716 41,300,000 14,393,703 86,060,359 36.1
Best Value Total Score
Scores1 2 3 4 5
Technical Score
(0-100)
Weighted Technical
Score1
Price Score
(0-100)
Weighted Price
Score2
Total Score (2+4)
FCI/Fluor/Parsons 95.0 66.5 100.0 30.0 96.5
Kiewit/Stacey and Witbeck JV
100.0 70.0 30.5 9.2 79.2
Mid-City Constructors JV (Granite/Brutoco)
100.0 70.0 36.1 10.8 80.8
1 (x 0.7 to equal 70% of total score)2 (x 0.3 to equal 30% of total score)