Post on 16-Oct-2015
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 1
Prepared by Reviewed by Safety Release QA/QC Approval
Approved by
Date Name
Section Engineer
Construction Manager
Safety manager
QA / QC Manager
Project Manager
Date Name
Site Manager
Project 1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
Method Statement No
CIVIL ELECTRICAL
MECHANICAL
INSTRUMENTATION
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 2
1. INTRODUCTION The following is the method statement for the erection of Carbon Steel storage tanks with roof by Jacking method and covers the following tanks. a) Fulisilic acid storage Tanks-2nos (234-R-01A/B). b) Sulphuric acid product storage tanks-3nos. c) Potable water tank-1nos (245-R-01). d) Diesel storage tank-1nos (246-R-01). e) Molten sulphur tank -1nos . It comes under Sulphuric & Phosphoric acid plant.
2. Function and location, General Description, Scope of Work a) Function and Location
The function of the storage tank is to store the Concentrated acid / Weak acid / Effluent for Maturation/Storage purposes, and it was located in phosphoric acid plant area.
b) General Description a) Fulisilic Acid storage Tank (234-R-01A/B) -2nos. (DIA 12000MM / HEIGHT 18000MM / NO OF SHELLS 8NOS). b) Potable water storage tank-1nos (245-R-01). (DIA 4800 / HEIGHT 6050MM / NO OF SHELLS 3NOS). c) Diesel Storage Tank- 1nos. (246-R-01) (DIA 11000MM / HEIGHT 8675MM / NO OF SHELLS 4NOS). d) Sulphuric Acid storage tank- 3nos. (DIA 28500MM / HEIGHT 10000MM / NO OF SHELLS 5NOS). e) Molten sulphur Storage tank 1nos. (DIA22000MM / HEIGHT7840MM / NO OF SHELLS 4NOS). I-BEAMS of IPE-270 Ladders, Walk ways Flat forms and handrails etc Baffle plates Tank roof
c) Scope of work Erection of I-Beams on the civil foundation and leveling. Erection, Alignment, Fit up and welding of bottom base plate. Inspecting welding with required NDT procedures like DP Test, Radiography, and Vacuum box UT etc (refer-ITP).
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 3
Erection, Alignment of Tank course shells by jockeying method. Erection of roof. Erection of Internal Baffle plates, Dip tube etc. Erection of Walk ways, staircase, Agitator support, Hand railing. Erection of Ladders, Flat forms and Hand rails.
3. Related Documents
a) Technical specifications. b) Approved construction drawings. c) Weld map. d) Release of material for construction form SNC Lavalin. e) Release certificate starting of erection over civil foundation from MID. f) Vendors instruction/manual required. g) I.T.P (Inspection Test Plan) h) All last revisions of Drawings, WPS, PQR, Welder certificated, etc
4. Required Material Testing, during and before work Material grade to be confirmed for WPS/PQR/WELD Qualification. Batch number, Heat number punched on the plate to be compared with Mill certificate.
5. Environmental and Safety All the lifting tools gear like slings, belts, D-Shackles etc are of Tested & Certified by the TPI. Cranes involved in Erection are certified by TPI. All the PPE used for the work is of approved quality. All the Workers, Staff, Engineers involved in work are geared with full basic PERSONAL PROTECTION EQUIPMENT. TOOL BOX TALK will be conducted on daily basis at the starting of the job. When working at height above 1.5mts from the ground every person to be wearing a safety belt. When working at height proper scaffolding will be provided for accessing, testing, inspection for the client. Scaffolding work will be done by properly trained and certified workers only under the supervision of Engineer. Entry Permit system for usage of scaffolding will be practiced.
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 4
While starting of welding, gas cutting, grinding, gouging operations HOT WORK permit system will be practiced. All the gas cutting torches are installed with approved Flash back arrestors. All the welders are with proper hand gloves, Apron, Face shield and other additional required safety gears. While working in confined space CONFINED SAPCE ENTRY PERMIT system will be practiced. All the power tools are of certified and tagged properly. All the power, welding cables are of certified and tagged properly. For handling Plates special lifting tools like horizontal and vertical plate lifting tools are used. Good housekeeping will be practices at all the time. Fire extinguishers are kept near the work for any fire incidents. Gas cylinders are stationed during work so that they maintain required distance from the heat source. Best engineering will be practiced to avoid accidents.
6. Detail of work supported with sketches and with special highlight for details Extension of I Beams to the required length. (Refer to QI(QUALITY INTERNATIONAL)
procedures). Inspection of welding. Erection of I-Beams on slab. Aligning & Leveling of I-Beams. Anchoring of I-Beams of to the concrete foundation.(Hold) Erection of Bottom base Plate on the I-Beams. Fit-up and Welding of Bottom base plate. Inspection of welding By Penetration, RT, and Vacuum test. Erection of Shell-5 plate on the bottom base plate and alignment with fit up Vertical welding of shell-5. Inspection of vertical & Horizontal by RT through 10% of the total length of the welding. Erection of shell-6 on the top of shell-5 and followed by alignment, fit up and welding of vertical
& horizontal welding. Inspection of vertical & Horizontal by RT through 10% of the total length of the welding and
100% RT of the T-Joints. Erection and fabrication of Roof.
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 5
Installation and fabrication of available Baffle plates. Erection of Hydraulic jacks inside the tank and distribute symmetrically such that every jack per
3 meter of the circumference. Installation, erection of walk ways and hand railings if advised. Lifting of the shell-5 by 2450mm height by hydraulic jacks. Erection, alignment and fit up of shell-4. Welding of horizontal and vertical welds. Inspection of vertical & Horizontal by RT through 10% of the total length of the welding and
100% RT of the T-Joints. Lifting of the shell-4 by 2450mm height by hydraulic jacks. Erection, alignment and fit up of shell-4. Welding of horizontal and vertical welds. Installation and fabrication of available Baffle plates. Inspection of vertical & Horizontal by RT through 10% of the total length of the welding and
100% RT of the T-Joints. Lifting of the shell-4 by 2450mm height by hydraulic jacks. Erection, alignment and fit up of shell-3. Welding of horizontal and vertical welds. Installation and fabrication of available Baffle plates. Inspection of vertical & Horizontal by RT through 10% of the total length of the welding and
100% RT of the T-Joints. Lifting of the shell-3 by 2450mm height by hydraulic jacks. Erection, alignment and fit up of shell-2. Welding of horizontal and vertical welds. Installation and fabrication of available Baffle plates. Inspection of vertical & Horizontal by RT through 10% of the total length of the welding and
100% RT of the T-Joints. Lifting of the shell-2 by 2450mm height by hydraulic jacks Erection, alignment and fit up of shell-1. Welding of horizontal and vertical welds. Installation and fabrication of available Baffle plates. Inspection of vertical & Horizontal by RT through 10% of the total length of the welding and
100% RT of the T-Joints. Welding of Bottom shell -1to the Bottom base plate.
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 6
Installation of Nozzle, pipe supports, flat forms, ladders, agitator supports and handrails.
7. Curing and Weather Protection All the plate will be supplied with sand blasted and primer coated by QI. All the welding edges will be protected by tape while painting. Any additional welding made on painted are will be power brushed and coated again. For locations with scratches, burns on painting etc during erection will be painted again.(rev-1)
8. Show hold points for internal and external required inspection including specified tests on products. Fit up inspection for levels, weld gaps, etc. Vacuum test of welding of the bottom base plate. While welding Test of root pass with penetration test. Horizontal and vertical welds 10 % of the total length by RT. RT test for the T-Joints by 100%.
9. Construction Equipment to be used , including standby Arrangement for breakage While the shells are erected by Jacking of the top shells with Hydraulic Lifting Jacks which are activated by a power pack. A standby power pack is available for breakage. And numbers of spare hydraulic hoses are available for breakage.
10. Lifting equipment, involved (where applicable, crash, tower cranetest and location). For handling of plates cranes will be used for shifting, lifting, erection and purposes.
11. Tools and associated other contractors Apparatus involved in this The following tools are involved in work
Welding Rectifiers machine. Gas cutting torch. Grinding machines of different sizes (100mm, 125mm and 150mm). Owen for baking of electrodes.
12. Manpower involved and Trades, who does what and when.
Supervisor for Tanks: - He takes care of all the activities associated in erection and fabrication of tanks and he involved in all the activities from staring to the finishing. Riggers: - These will involve in handling the plates for erection, alignment etc.
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 7
Fabricator/ Fitter: - He is responsible for fit ups, alignments, verticality and tolerances of the total tank. Lifting Forman/ Jacking Specialist: - He takes the takes the lead role in alignment and positioning of Hydraulic lifting Jacks, He takes the leading role in lifting of the tank shells at every step. Pipe Fitter: - He takes the fit up of nozzles and other pipe supports and structural items. Welders: - These will do all the welding operations. Grinders: - These will do grinding operation for the tank. Helpers: - These are the general helpers to skilled workers involving in job. Crane operator: - These will operate the crane. QA/QC Team: - These will guide the job for required QA/QC levels.
13. Work Schedule Requirements and Timing for This work. For this job the daily regular work hours will be 10 hrs excluding lunch time. From 7-00Am to 6-00PM. On weekly halfs required core skilled workers like welders will be engaged if necessary.
14. Training and Orientation for the Team For all the team members TOOL BOX TALK will be conducted at the beginning of activity on daily basis. The scaffolding team will be of trained and certified. The crane operator will be of trained and certified. The riggers involved will be of trained and certified. Regular monitor of welders and if necessary training will be given regularly.
15. Tests on Systems (QA /QC ) Radiographic Test of all T-Joints by 100%. Vertical & Horizontal welding RT by 10 % of the total length of the welding. Vacuum test for the Base plate. Dye Penetrate Test for all Root pass and Final. In case Repair is needed, extension shots (penalty) to be match with API650 To be advised for any other test is needed.
16. Logistics involved if work is expected to extend beyond normal working hours. Lighting while working at night. Shade protection while the wind velocity is very high.
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 8
17. Annexes and sketches lists.
WEIGHTS OF THE INDIVIDUAL MATERIALS for crane, lifting gear selection purpose.
1. IPE 270 TANK BOTTOM BEAMS
2. CS Plate of 2400mm Width X 12000mm Length mm X 16mm Thick = 3.617 Tones.
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 9
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 10
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 11
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 12
Isometric view of foundation after erection of I beams.
Close up view of foundation, I Beams and bottom plate.
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 13
Erection, fit up and welding of bottom plate segments.
Erection of 1st shell plate on bottom plate.
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 14
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 15
Complete erection, fit up & vertical welding of 5th shell.
Erection of 6th shell plate on 5th shell by conventional method.
Keeping vertical joints plates adjoining courses a minimum of 600mm apart.
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 16
Complete erection, fit up, vertical & horizontal welds of 6th shell.
Erection, fit up, welding of spiral stair case for the shells completed.
Erection, fit up, welding of Baffles and stair case subjected to availability of material for 5th & 6th shells.
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 17
Erection fabrication of Tank Roof before jacking
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 18
Lifting of 5th & 6th shells by hydraulic jacks.
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 19
4th shell 1st plate erection, alignment on bottom plate.
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 20
4th shell 2nd plate fit up.
Complete erection, fit up and vertical welding of 4th shell
Jockeying down the 5th shell to align with the 4th shell, fit up and completion of horizontal welding.
Erection, fit up, welding of Baffles plates, staircase etc subjected to availability of material and approval for 4th shell.
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 21
Lifting of 4thshell for 3rd shell erection.
Erection of 3rd shell first plate.
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 22
Erection fit up of 3rd shell 2nd plate
Complete erection, fit up and vertical welding of 3rd shell plates.
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 23
Jockeying down to align top shells with 3rd shell, horizontal welding of 4th & 3rd shells.
Erection, fit up, welding of Baffles plates, staircase etc subjected to availability of material and approval for 3rd shell.
Lifting the 3rd shell for 2nd shell erection
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 24
Erection of 2nd shell first plate.
Complete erection, fit up and vertical welding of 2nd shell.
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 25
Jockeying down for alignment, fit up & horizontal welding between 2nd shell & 3rd shell.
Erection, fit up, welding of Baffles plates, staircase etc subjected to availability of material and approval for 2nd shell.
Lifting 2nd shell for 1shell erection and fit up.
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 26
.
1st shell first plate erection, fit up.
1st shell complete erection, fit up & vertical welding of shell.
1500 MTPD Phosphoric Acid plant 4500 MTPD Sulphuric Acid plant
METHOD STATEMENT
METHOD STATEMENT FOR STORAGE TANKS WITH ROOF Rev-0 Page 27
Jockeying down 2nd shell to align, fit up and horizontal welding of 2nd shell and 1st shell.
Erection, fit up, welding of Baffles plates, staircase etc subjected to availability of material and approval
Fillet welding of bottom plate to 1st shell.