Management Forum Oct 31st 2012
Grangegorman UpdatePaul Horan
Implementation Programmes
Guiding Principles
1 Optimise Existing
Property Potential & EHSI
(2012 – 2016)
2Significant New
Build(s)PPPs / Other
Programme 1 (2012-2014)
Outline:
• ~10,000m2 of existing protected structures brought back into use for educational purposes
• New build 2,500m2 research (PRTLI)• €36M incl VAT (DIT €16, PRTLI €10, DoES €10)
• Consolidation of Art, Design, Photography & Social Sc• New research capacity• Over 1,000 students and staff on site by 2014• Development of matching support, recreation, and sporting
facilities
2013 – Q2
Q2 2013• Commence SIPR Works
Including:• Site Clearance• Soil Removal• Temp Works• Archaeology• Site profiling • Trenching etc.
• Demolitions to continueNotes: • One access / egress point for
HSE / DIT & GDA site users• Principal construction access
via NCR• Sports clubs / DIT Sports no
longer using site• Timeline for re-aligning
Bradogue to be agreed
Remove Soil Compounds
Key• Demolitions• Occupied Building to be
decanted• Building under construction• Building occupied / completed• PPP site outline• Boundary between occupied
site and unoccupied / construction site(s)
````
Approx line of Bradogue
Lawn
2013 – Q4
Q3 2013• Commence Adaptive Re-use,
EHSI and HSE Primary Care• Boundary Wall with Park SC
built with controlled access • Demolitions completeNotes: • Cross site water-main and main
drainage interface with external sites to be considered (incl. Broadstone)
EHSI
Key• Demolitions• Occupied Building to be
decanted• Building under construction• Building occupied / completed• PPP site outline• Boundary between occupied
site and unoccupied / construction site(s)
````
Outline of Ivy Ave
Primary Care
North
Circ
ular
Road Grangegorm
an Lower
EHS
I
2015 – Q2
Q2 2015• Central and East Quad PPPs
commence on-site• EHSI commences operations• DIT to occupy Goirtin space (c.
400 sq m)?Notes: • Principal Construction access
taken across Grangegorman Lower through Orchard View site
• Should Bradogue be diverted at this stage? Does this imply earlier demolition of DCC Cleansing Depot
• Goirtin have decanted off site
Key• Demolitions• Occupied Building to be
decanted• Building under construction• Building occupied / completed• PPP site outline• Boundary between occupied
site and unoccupied / construction site(s)
````
Luas BXD
Progress• Protected structures/Stablisation
– Surveys advanced, initial works commenced• Brief development
– Complete– Great cooperation
• Protected Structures Design team – Appointed– Working– Prelim ideas sketch received
• Very tight programme
EHSI Design Team
Architects RKD ArchitectsProject Management
Sweett Group
Civil & Structural Engineering Ove Arup Civil & Structural
Quantity Surveying Bruce Shaw
PSDPBSSM Safety Management
Fire Safety Consultant J Gardner & Associates
Science Centre UCD
23 tenders submitted, six shortlisted & evaluated for contract > € ½ million
EHSI SITE PLAN
EHSI Research • Lab Workstation Design and
Configuration• Room Data Sheets• Exemplar facilities• Room layout sign-off
• Potential to expand and include HotHouse and incubation space with EI support
PPP Finances• Irish finances and recent PPP history
– Very difficult to get reasonable PPP bids• Stimulus programme
– high level financing arrangements:• EIB
• Infrastructure Cash +VAT and Fees
• EIB involvement =>– Recasting of Outline Business Case (OBC) and Cost Benefit
Analysis CBA– GDA have engaged Mazars to “rework” original FGS document– Draft complete this week
Infrastructure• Cash funding
– Infrastructure– VAT– Fees and levies
• Master-planning team re-engaged• Public Realm & Site Infrastructure planning
application to be lodged.
Site Infrastructure & Public Realm
• SDZ formally published• Planning Application lodged!• Two parts
– “Simple” demolitions– “Complex” full SI & PR
• Infrastructure• Levels• Roads• Boundaries• .......
PPP Technical Advisors
• Tender issued• ITT issued• Tender submission 30/10• Appoint 13/12• Initial Briefing - week 17-21 Dec• Jan – July
– Output spec– Inputs to Public Sector Benchmark PSB
• Aug 2013 – Hand-over to NDFA
• Contract award July 2015• Handover April 2017
1.INTRODUCTION
2. BACKGROUN
D
Parties
Site
Scope of the PPP
PPP Project
Org Chart
3. PROCUREME
NT PROCEDURE
ITT/Confirmation of PQQThe Competiti
onThe
ServicesThe
Agreement
Other Advisors
Programme
4. GENERAL INFORMATIO
N
Standard condition
s
Query/Clarificati
on Process
5. INVITATION TO TENDER
Form of Tender
Award Criteria
Completeness/
Compliance/
Validity
6. SUBMISSION OF TENDER DOCUMENT
S
Tender timetable
7. AWARD OF AGREEMENT
Notification to
tenderers
Conditions
Precedent
Schedules to the ITT
Indicative Programme for the ProjectAward Criteria
and EvaluationForm of
TenderDeclaration by
TendererASITE
Disclosed Data
Agreement
Self funding developmentsProvision of basic infrastructure will allow self
funding elements to progress:• Student Accommodation:
– Immediate opportunity for ~600 beds/ 20,000m2 / €70M– Capacity on site for 1,600 beds– Commercial outlets- shops etc
• Sports facilities – student levy and sinking fund– Ideally incorporated with major infrastructure works
• Science Park – with third parties
Next Phases• 50% DIT on site Sept 2017
– Need for adequate Library– Need for student services
• Top House will provide ~4000m2
– Need for additional library provision and Academic Hub• Integrated student services
– New build?
• Kevin St, Cathal B St available for disposal 2018• New national capital programme 2017-2022
• Improved property market – FOCAS– Aungier St. – Bolton St
Masterplan Delivery
&
LUAS Broombridge/ Broadstone Gate
20
•Join Red and Green LUAS lines and extend to Broombridge•Positive decision by An Bord Pleanala•Railway order granted•Working Group looking at detailed design of DIT Broadstone stop•NTA, GDA, RPA, DCC, CIE, Dublin Bus, Bus Eireann•GDA/DMOD developing detailed visualisations•Issues of site transfer/purchase, and planning to be addressed.
Broombridge Sports Development• Site purchased• Infrastructure works
– Loose GG pitches for 2013/2014
• Plan:– All weather GAA floodlit pitch– Team changing– Redevelop a number of indoor bays
as 5-a-side/7-a-side/training areas (subject to additional funding)
– Investigating use of one bay for academic use.
• Planning granted• Initial cost plan• Move to appoint design team
Health
• Replacement mental health nearing completion
• Decant from existing buildings Dec 2012/Jan 2013
• Grangegorman Primary Care sanctioned as part of stimulus
• Site options review underway– Laundry– Initial discussion - optometry
Primary School
• Dublin 7 Educate Together• Temporary school opened 2010• 16 classrooms with special
needs students• Permanent school to be located
at Grangegorman Upper• In project development• Initial discussions with HSE
on site transfer• Outline funding approval