Layout Experimental hall
Final status (?)
3rd HIE ISOLDE Physics Coordination Group meeting
CERN, 3 September 2012
HIE-ISOLDE
Erwin Siesling
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 2
History: summer 2011
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling
2 mDecoupe mur Plateforme prolongee
Courtesy: Stephane Maridor
Maximize space on floor
3
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling
4.1m
2 m
Courtesy: Stephane Maridor
4
All racks on platform
CV says NO...
Cooling restrictions
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 5
Hall 170 ventilation systems
platform
wall wall
wall
1st extension 2nd extension
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 6
platform
wall wall
wall
1st extension 2nd extension
Hall 170 ventilation systems
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 7
Max heat dissipation
platform
wall wall
wall
1st extension 2nd extension
Max 70kW
100kW ?Max 45kW
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling
Rack distribution
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling
6x3 RACKS “PC” 500A
DIPOLE 45˚20 RACKS “PC”
QUAD/STEERER
2x2 RACKS “PC” 250A
DIPOLE 22.5˚
3 spare RACKS dipole
5 VAC racks
2 BI racks(+3)
4 WIC racks
Electric. Dist. racks
Rack distribution
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling
Cable distribution
All EPC, BI and VAC cabling installed in stage 1 before experiments in place – cables for stage 2(b) rolled and stored on the hall floor
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling
All EPC, BI and VAC cabling installed in stage 1 before experiments in place – cables for stage 2(b) rolled and stored on the hall floor
Cable distribution
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 12
Minimizing floor occupancy
2x2 RACKS “PC” 250A
DIPOLE 22.5˚
3 spare RACKS dipole
6x3 RACKS “PC” 500A (+1 cabling rack)
DIPOLE 45˚
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 13
Minimizing floor occupancy
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 14
Heat to air dissipation
6x3 RACKS “PC” 500A (+1 cabling rack)
DIPOLE 45˚20 RACKS
QUAD/STEERER
2x2 RACKS “PC” 250A
DIPOLE 22.5˚
3 spare RACKS dipole
5 VAC racks
2 BI racks(+3)
4 WIC racks
Max 4x12.5=50kW
Max 29kW
Max 12.5kW Max 2x4kW
Max 5kW
or
Platform: Max 46.5kW to air (if spare runs for a 44.5 ˚ magnet)Floor: Max 50kW to air (if bend running at max) – leaving 20kW for experiments
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 15
Alignment platform
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 16
Nicole experiment?
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 17
Acknowledgement
• EN/MEF : STEPHANE MARIDOR, ELEFTHERIOS ZOGRAFOS• GS/SE : DANIEL PARCHET, ELISEO PEREZ-DUENAS• BE/OP : DIDIER VOULOT• EN/HDO: YACINE KADI• EN/CV : PAUL PEPINSTER, BENOIT LACARELLE• EN/EL : RENE NECCA• EN/STI : RICHARD CATHERALL, ANA-PAULA BERNARDES• TE/ABT : BRENNAN GODDARD• BE/RF : MATHEW FRASER• TE/EPC : MICHELE MARTINO
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 18
Extra slides
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling
STAGE 1
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling
STAGE 2a
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling
STAGE 2b
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling
1580
892
1344
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 26
Hie-Isolde Planning
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015 2016
Civil
Main servicesCryo
CM 1&2 CM 3&45.5MeV/u
10MeV/u
Beam Transfer Line
CM 5&6
17 Dec 2012 - Q3 2014
sd sd sdCM1&2
Isolde & REX Ops shutdown
LS1
Cryo Mod 1 & 2 install (Isolde normal operations)
Timeline:
sd
VentilationDemi waterElectrical syst.s
Start LS1 3 dec 201217
End LS1:Start Low E physics
Commissioning (Isolde normal operations)
Commissioning during shutdown (EBIS beam)
Beam commissioning Nov. + 5 months
Cryo only ready Feb 2014
Start-up 2015HIE physics at
5.5MeV/u
Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 27
Commissioning planning