SERIES 800 ROAD PAVEMENTS - (11/04) UNBOUND, CEMENT AND OTHER HYDRAULICALLY BOUND MIXTURES
ContentsClause Title Page
(11/04)Unbound Mixtures for Subbase801 (11/04)GeneralRequirementsfor UnboundMixtures 2
802 (11/04)Transport,Laying,Compaction andTraffickingofUnboundMixtures 4
803 (11/04)Type1UnboundMixtures 7
804 (11/04)Type2UnboundMixtures 8
805 (11/04)Type3(opengraded) UnboundMixtures 9
806 (11/04)CategoryB(closegraded) UnboundMixtures 9
807 (11/07)Type4(asphaltarisings) UnboundMixture 10
808and809(05/09)NotUsed 10
(05/09)Cement and Other Hydraulically Bound Mixtures810 (11/04)GeneralRequirementsfor CementandOtherHydraulically BoundMixtures 10
811 (05/09)BinderConstituents 11
812 (05/09)StorageofConstituents 12
813 (05/09)GeneralRequirementsfor ProductionandLayerConstruction 12
814 (05/09)Mix-in-PlantMethodof ConstructionUsingBatchingbyMass 15
815 (05/09)Mix-in-PlantMethodof ConstructionUsingVolumeBatching 15
816 (05/09)Mix-in-PlaceMethodof Construction 15
817 (05/09)MethodStatementand DemonstrationArea 15
818 (11/04)InducedCrackingofHBM 16
819 (05/09)NotUsed 16
820 (05/09)Aggregates 16
MANUAL OF CONTRACT DOCUMENTS FOR HIGHWAY WORKS VOLUME 1 SPECIFICATION FOR HIGHWAY WORKS
Amendment-November2009 1
Clause Title Page
821 (05/09)CementBoundGranular MixturesA(CBGMA) 17
822 (05/09)CementBoundGranular MixturesB(CBGMB) 17
823 (05/09)CementBoundGranular MixturesC(CBGMC) 18
824to829 (05/09)NotUsed 18
830 (05/09)FlyAshBoundMixture1 (FABM1)andHydraulicRoad BinderBoundMixture1(HRBBM1) 18
831 (05/09)SlagBoundMixtureB2 (SBMB2),FlyAshBound Mixture2(FABM2)and HydraulicRoadBinderBound Mixture2(HRBBM2) 18
832 (05/09)SlagBoundMixtureB3 (SBMB3),FlyAshBound Mixture3(FABM3)andHydraulic RoadBinderBoundMixture3 (HRBBM3) 19
833 (11/04)NotUsed 19
834 (11/04)FlyAshBoundMixture5 (FABM5) 19
835 (05/09)SlagBoundMixturesB1-1, B1-2,B1-3andB1-4(SBMB1) 19
836to839 (05/09)NotUsed 19
840 (05/09)SoilTreatedbyCement(SC), SoilTreatedbySlag(SS),Soil TreatedbyFlyAsh(SFA)andSoil TreatedbyHydraulicRoadBinder (SHRB) 20
841to869 (11/04)NotUsed 21
870 (05/09)Testing,ControlandChecking ofHBM 21
871 (05/09)Determinationofthe CoefficientofLinearExpansion 23
872to879 (05/09)NotUsed 24
880 (05/09)LaboratoryMixtureDesign Procedure 24
Volume1 Series800SpecificationforHighwayWorks RoadPavements-Unbound,CementandOtherHydraulicallyBoundMixtures
ROAD PAVEMENTS - (11/04) UNBOUND, CEMENT AND OTHER HYDRAULICALLY BOUND MIXTURES
(11/04) Unbound Mixtures for Subbase
801 (11/04) General Requirements for Unbound Mixtures
1 (11/04)UnboundmixturesshallbemadeandconstructedtoconformtoBSEN13285,the
requirementcategoriesinTable8/1andClauses802to806.ThepermittedalternativesforeachpartofthePermanentWorksshallbeasdescribedinAppendix7/1.
Amendment-November2009 2
Table 8/1:(11/07)Mixture and Grading Requirement Categories for Unbound Mixtures
Unbound mixture Type 1 Type 2 Type 3 (open graded)
Category B (close graded)
Type 4 (asphalt arisings)
Clause 803 804 805 806 807Standard BSEN13285CategoriesforunboundmixturepropertiesMixture requirement category-Designation 0/31,5 0/31,5 0/40 0/31,5 0/31,5-Maximumfines UF9 UF9 UF5 UF9 UF9
-Oversize OC75 OC75 OC80 OC80 OC75
Grading requirement category-Overallgrading GP GE GO GB GP
2 (11/07)Unboundmixturesshallnotbedepositedwithin500mm,oranyotherdistancesdescribedinAppendix7/1,ofconcrete,cementboundmaterials,othercementitiousmixturesorstabilisedcappingformingpartofthePermanentWorksif,whentestedinaccordancewithTRLReport447either:
(i) (11/05)thewater-solublesulfate(WS)contentexceeds1500mgofsulfate(asSO4)perlitre(TestNo.1);or
(ii) (11/09)theoxidisablesulfides(OS)contentexceeds0.5%ofsulfate(asSO4)(TestNo.2andTestNo.4);or
(iii) (11/09)the2:1watertosoilextractpreparedforthedeterminationofwater-solublesulfatein(i)hasapHvalueoflessthan7.2,whentestedusingtheelectrometricmethodofpHdeterminationinaccordancewithBS1377-3.
(11/09)AtleastfivesamplesofeachmaterialshallbetestedforWS,OSandpHvalue.Themeanofthehighesttwovaluesshallbeusedforcomparisonwiththelimitingvalues.Thisalsoappliesifsixtonine
resultsareavailable.Iftenormoreresultsareavailable,themeanofthehighest20%oftheresultsshallbeusedforcomparisonwiththelimitingvalues.
3 (11/07)Unboundmixturesshallnotbedepositedwithin500mm,oranyotherdistancesdescribedinAppendix7/1,ofmetallicstructuralelementsformingpartofthePermanentWorksif,whentestedinaccordancewithTRLReport447either:
(i) (11/05)thewater-solublesulfate(WS)contentexceeds300mgofsulfate(asSO4)perlitre(TestNo.1);or
(ii) theoxidisablesulfides(OS)contentexceeds0.06%ofsulfate(asSO4)(TestNo.2andTestNo.4).
(11/05)AtleastfivesamplesofeachmaterialshallbetestedforWSandOS.Themeanofthehighesttwovaluesshallbeusedforcomparisonwiththelimitingvalues.Thisalsoappliesifsixtonineresultsareavailable.Iftenormoreresultsareavailable,themeanofthehighest20%oftheresultsshallbeusedforcomparisonwiththelimitingvalues.
Volume1 Series800SpecificationforHighwayWorks RoadPavements-Unbound,CementandOtherHydraulicallyBoundMixtures
Table 8/2:(05/09)Requirements for Aggregates Used in Unbound Mixtures
Unbound mixture Type 1 Type 2 Type 3 (opengraded)
Category B (closegraded)
Type 4 (asphaltarisings)
Clause 803 804 805 806 807Standard BSEN13242Categoriesforaggregateproperties
Crushed,orbrokenandtotallyroundedparticles-crushedrock,crushedartificialandcrushedrecycledaggregates-seeNOTE1-crushedgravel
C90/3
C50/10-seeNOTE2
C90/3
CNR(norequirement)
C90/3
Notpermitted
C90/3
Notpermitted
Resistancetofragmentation-LosAngelestest
LA50 LA50 LA40-seeNOTE3
LA50
Resistancetowear-micro-Devaltest
MDENR(norequirement).Thesuppliershallstatethevaluefortheaggregateused.
Resistancetofreezingandthawingmagnesiumsulfatesoundness
MS35
Waterabsorption WA24NR(norequirement).Thesuppliershallstatethevaluefortheaggregateused.
Volumestabilityofblastfurnaceslags
Freefromdicalciumsilicateandirondisintegration.
Volumestabilityofsteel(BOFandEAF)slags
V5 Notpermitted V5
AllotherBSEN13242aggregaterequirements
CategoryNR(norequirement).
NOTES:1.BSEN13242assumesthatcrushedrockaggregatescomplywithcategoryC90/3withoutfurthertesting.2.WherepermittedbyAppendix7/1.3.Seesub-Clauses805.3and806.3foradditionalrequirements.
Amendment-November2009 3
(11/07)Therequirementsin(i)and(ii)aboveshallnotapplytometallicitemsprotectedbyconcreteandancillarymetallicitemssuchasthetopsofchambersandgullies.4 ThepropertiesofaggregatesusedinunboundmixturesshallcomplywiththeselectedrequirementsofBSEN13242listedinTable8/2.
5 (11/07)WhererecycledcoarseaggregateorrecycledconcreteaggregateisusedinunboundmixturesinaccordancewithClauses802to807asappropriate,itshallhavebeentestedinaccordancewithClause710.RecycledcoarseaggregateandrecycledconcreteaggregateusedinunboundmixturesinaccordancewithClauses803,804and807shallalsocomplywiththeadditionalrequirementsofTable8/3.
TABLE 8/3:(11/09)Additional Requirements for Recycled Coarse Aggregate and Recycled Concrete Aggregate Used in Type 1, Type 2 and Type 4 Unbound Mixtures
Unbound Mixture Type 1 Type 2 Type 4 (asphalt arisings)
Component Identified by Clause 710
Maximum Permitted Content (%bymass)
Asphalt(ClassRa) 50 50 100Glass(ClassRg) 25Othermaterials(ClassX),includingwood,plasticandmetal
1
Volume1 Series800SpecificationforHighwayWorks RoadPavements-Unbound,CementandOtherHydraulicallyBoundMixtures
6 (11/04)WhenrequiredbyAppendix7/1andClauses803and804asappropriate,theunboundmixtureshallsatisfytheminimumCBRrequirementofAppendix7/1whentestedinaccordancewithclause7ofBS1377-4,withsurchargediscs.Thespecimensshallbetestedinasoakedcondition.Themixtureshallbetestedatthedensityandmoisturecontentlikelytodevelopinequilibriumfieldconditionswhichshallbetakenasbeingthedensityrelatingtotheuniformairvoidscontentof5%andthevalueofoptimumwatercontentdeclaredwhentestedasrequiredbyBSEN13285.
Frost Heave
7 SubjecttothetolerancesgiveninTable7/1andunlessotherwisestatedinAppendix7/1,materialshallnotbefrostsusceptibleifitisusedwithin450mmofthedesignedfinalsurfaceofaroadorpavedcentralreserve,or350mmiftheMeanAnnualFrostIndex(MAFI)ofthesiteislessthan50.
8 (11/09)Materialshallbeclassifiedasnon-frost-susceptibleifthemeanheaveis15mmorless,whentestedinaccordancewithBS812-124.ComparatorspecimensinaccordancewithAnnexBofBS812-124shallbeused.
802 (11/04) Transport, Laying, Compaction and Trafficking of Unbound Mixtures
Transporting
1 (11/04)Unboundmixturesshallbeprotectedfromdryingoutandsegregationbothduringtransittothepointwhereitistobelaidandwhilstawaitingtipping.
Laying
2 UnboundmixturesinafrozenconditionshallnotbeincorporatedintheWorksbutmaybeused,ifacceptable,whenthawed.Unboundmixturesshallnotbelaidonanysurfacewhichisfrozenorcoveredwithice.
3 Allunboundmixturesshallbeplacedandspreadevenly.Spreadingshallbeundertakeneitherconcurrentlywithplacingorwithoutdelay.Unboundmixturesshallbespreadusingapavingmachineorasuitablespreaderboxandoperatedwithamechanismwhichlevelsoffthematerialtoanevendepth.
4 ExceptwhereotherwisestatedinAppendix7/1,materialupto225mmcompactedthicknessshallbespreadinonelayersothataftercompactionthetotalthicknessisasspecified.Materialofcompactedthicknessgreaterthan225mmshallbelaidintwoormorelayersandtheminimumcompactedthicknessofanysuchlayershallbe110mm.Wherethelayersof
unboundmixturesareofunequalthickness,thelowestlayershallbethethickestlayer.
Compaction
5 Compactionshallbecompletedassoonaspossibleafterthemixturehasbeenspreadandinaccordancewiththerequirementsfortheindividualmixtures.
6 Fullcompactionshallbeobtainedoverthefullareaincludinginthevicinityofbothlongitudinalandtransversejoints.
7 CompactionofunboundmixturesshallbecarriedoutbyamethodspecifiedinTable8/4,unlesstheContractordemonstratesatsitetrialsthatastateofcompactionachievedbyanalternativemethodisequivalenttoorbetterthanthatusingthespecifiedmethod.
8 Thesurfaceofanylayerofmaterialshalloncompletionofcompactionandimmediatelybeforeoverlaying,bewellclosed,freefrommovementunderconstructionplantandfromridges,cracks,loosematerial,potholes,rutsorotherdefects.Allloose,segregatedorotherwisedefectiveareasshallberemovedtothefullthicknessofthelayer,andnewmateriallaidandcompacted.
9 ForthepurposesofTable8/4thefollowingshallapply:
(i) Thenumberofpassesisthenumberoftimesthateachpointonthesurfaceofthelayerbeingcompactedshallbetraversedbytheitemofcompactionplantinitsoperatingmode(orstruck,inthecaseofpowerrammers).
(ii) ThecompactionplantinTable8/4iscategorisedintermsofstaticmass.Themasspermetrewidthofrollisthetotalmassontherolldividedbythetotalrollwidth.Whereasmooth-wheeledrollerhasmorethanoneaxle,thecategoryofthemachineshallbedeterminedonthebasisoftheaxlegivingthehighestvalueofmasspermetrewidth.
(iii) Forpneumatic-tyredrollersthemassperwheelisthetotalmassoftherollerdividedbythenumberofwheels.Inassessingthenumberofpassesofpneumatic-tyredrollerstheeffectivewidthshallbethesumofthewidthsoftheindividualwheeltrackstogetherwiththesumofthespacingsbetweenthewheeltracksprovidedthateachspacingdoesnotexceed230mm.Wherethespacingsexceed230mmtheeffectivewidthshallbethesumofthewidthsoftheindividualwheeltracksonly.
Amendment-November2009 4
Volume1 Series800SpecificationforHighwayWorks RoadPavements-Unbound,CementandOtherHydraulicallyBoundMixtures
(iv) Vibratoryrollersareself-propelledortowedsmooth-wheeledrollershavingmeansofapplyingmechanicalvibrationtooneormorerolls:
(a) Therequirementsforvibratoryrollersarebasedontheuseofthelowestgearonaself-propelledmachinewithmechanicaltransmissionandaspeedof1.5-2.5km/hforatowedmachineoraself-propelledmachinewithhydrostatictransmission.Ifhighergearsorspeedsareusedanincreasednumberofpassesshallbeprovidedinproportiontotheincreaseinspeedoftravel.
(b) Wherethemechanicalvibrationisappliedtotworollsintandem,theminimumnumberofpassesshallbehalfthenumbergiveninTable8/4fortheappropriatemasspermetrewidthofonevibratingrollbutifonerolldiffersinmasspermetrewidthfromtheother,thenumberofpassesshallbecalculatedasfortherollwiththesmallervalue.Alternativelytheminimumnumberofpassesmaybedeterminedbytreatingthemachineashavingasinglevibratingrollwithamasspermetrewidthequaltothatoftherollwiththehighervalue.
(c) Vibratoryrollersoperatingwithoutvibrationshallbeclassifiedassmooth-wheeledrollers.
(d) Vibratoryrollersshallbeoperatedwiththeirvibratorymechanismoperatingatthefrequencyofvibrationrecommendedbythemanufacturer.Allsuchrollersshallbeequipped,orprovidedwithdevicesindicatingthefrequencyatwhichthemechanismisoperatingandthespeedoftravel.Bothdevicesshallbecapableofbeingreadbyaninspectoralongsidethemachine.
(v) Vibrating-platecompactorsaremachineshavingabase-platetowhichisattachedasourceofvibrationconsistingofoneortwoeccentrically-weightedshafts:
(a) Themasspersquaremetreofbase-plateofavibrating-platecompactoriscalculatedbydividingthetotalmassofthemachineinitsworkingconditionbyitsareaincontactwithcompactedmaterial.
(b) Vibrating-platecompactorsshallbeoperatedatthefrequencyofvibrationrecommendedbythemanufacturer.Theyshallnormallybeoperatedattravellingspeedsoflessthan1km/hbutifhigherspeedsarenecessary,thenumberofpassesshallbeincreasedinproportiontotheincreaseinspeedoftravel.
(vi) Vibro-tampersaremachinesinwhichanenginedrivenreciprocatingmechanismactsonaspringsystem,throughwhichoscillationsaresetupinabase-plate.
(vii) Powerrammersaremachineswhichareactuatedbyexplosionsinaninternalcombustioncylinder;eachexplosionbeingcontrolledmanuallybytheoperator.Onepassofapowerrammershallbeconsideredtohavebeenmadewhenthecompactingshoehasmadeonestrikeontheareainquestion.
(viii) Combinationsofdifferenttypesofplantordifferentcategoriesofthesameplantwillbepermitted;inwhichcasethenumberofpassesforeachshallbesuchproportionoftheappropriatenumberinTable8/4aswilltogetherproducethesametotalcompactiveeffortasanyoneoperatedsingly,inaccordancewithTable8/4.
Amendment-November2009 5
Volume1 Series800SpecificationforHighwayWorks RoadPavements-Unbound,CementandOtherHydraulicallyBoundMixtures
TABLE 8/4:(11/04)Compaction Requirements for Unbound Mixtures
Type of CompactionPlant Category Number of passes for layers not exceeding the following compacted thicknesses:110 mm 150 mm 225 mm
Smooth-wheeledroller(orvibratoryrolleroperatingwithoutvibration)
Masspermetrewidthofroll:over2700kgupto5400kgover5400g
168
unsuitable16
unsuitableunsuitable
Pneumatic-tyredroller Massperwheel:over4000kgupto6000kgover6000kgupto8000kgover8000kgupto12000kgover12000kg
1212108
unsuitableunsuitable1612
unsuitableunsuitableunsuitableunsuitable
Vibratoryroller Masspermetrewidthofvibratingroll:over700kgupto1300kgover1300kgupto1800kgover1800kgupto2300kgover2300kgupto2900kgover2900kgupto3600kgover3600kgupto4300kgover4300kgupto5000kgover5000kg
166433222
unsuitable16655443
unsuitableunsuitable1098765
Vibrating-platecompactor Masspersquaremetreofbaseplate:over1400kg/m²upto1800kg/m²over1800kg/m²upto2100kg/m²over2100kg/m²
853
unsuitable86
unsuitableunsuitable10
Vibro-tamper Mass:over50kgupto65kgover65kgupto75kgover75kg
432
864
unsuitable108
Powerrammer Mass:100kg-500kgover500kg
55
88
unsuitable12
Amendment-November2009 6
Use of Surfaces by Construction Plant and Other Traffic
10 Constructionplantandothertrafficusedonpavementsunderconstructionshallbesuitableinrelationtothematerial,conditionandthicknessofthecoursesittraversessothatdamageisnotcausedtothesubgradeorthepavementcoursesalreadyconstructed.Thewheelsortracksofplantmovingoverthevariouspavementcoursesshallbekeptfreefromdeleteriousmaterials.
11 (11/04)WheretheContractorproposestousetheunboundmixturelayersforconstructionplantheshallimprovetheselayerswherenecessary,toaccommodatethemethodofconstructionandthetypeofplantandvehicleswhichheproposestouse,inordertoavoiddamagetothelaidlayer(s),anycappingandthesubgrade.Anypermanentthickeningshallbeacrossthewholewidthofthepavement.Temporarythickeningshallnotimpededrainageofanylayerorthesubgrade.
Trafficking Trial
12 WhenrequiredbyAppendix7/1,theContractorshallundertakeaTraffickingTrialincorporatingtheunboundmixtureproposedforuseinthePermanentWorks.Atrialareashallbeconstructed,traffickedandassessedinaccordancewiththeproceduredescribedinsub-Clauses13to18ofthisClause.Themeanverticaldeformationafter1000equivalentstandardaxlesshallbelessthan30mmwhenmeasuredinaccordancewiththeprocedurestatedinsub-Clause17ofthisClause.
ProposalsfortraffickingtrialsshallbesubmittedtotheOverseeingOrganisationforreviewandacceptancefivedaysinadvanceofconstruction.
Trial Procedure
13 ThetrialareashallbelocatedonaformationpreparedinaccordancewiththeSpecification.ThetrialareamaybelocatedsothatitcanbeincorporatedwithinthePermanentWorksiftheresistancetowheel
Volume1 Series800SpecificationforHighwayWorks RoadPavements-Unbound,CementandOtherHydraulicallyBoundMixtures
trackruttingisdemonstratedtocomplywithsub-Clause12ofthisClause.
14 (11/04)Thetrialareashallbeatleast60mlong,andofsufficientwidththatwhentrafficked,thewheelpathsofthetestvehicleshallbeatleast1mfromeitheredgeofthetopoftheunboundmixturelayer.TheunboundmixturelayershallbecompactedtothethicknessspecifiedinAppendix7/1.Theformationshallextendforafurther1meithersideoftheunboundmixturelayer.
15 Asufficientrunoff/runonareashallbeconstructedateachendofthetrialareaofthesamewidth,andcompactedtothesamelevel,asthetrialarea,toensurecorrecttrackingbythetestvehicleandminimisedynamiceffectsofthevehiclebouncingonitssprings.Suitableguidanceshallbegiventoassistthedriverinmaintainingthesametrackineachpassandtoachievechannelledtrafficking.Examplesofsuitableguideswouldbeastringorpaintedline.
Mixtures
16 (11/04)Theunboundmixtureusedinthetrialshallbetransported,laidandcompactedusingtheequipmentproposedforuseintheWorks.
17 Maximumverticaldeformationshallbemeasuredinbothwheeltracksusingopticalorlaserlevelsatpre-determinedmonitoringpointsonfivetransverse
linesspacedequallyalongthelengthofthetrialbay.Thetransverselinesattheendsofthetrialareashallbeatleast5mfromtherunoff/runonareas.Theaveragedeformationofthetwowheeltracksafter1000standardaxlesshallberecorded.
Reporting and Acceptance of Trafficking Trial Area
18 TheContractorshallprovidetheOverseeingOrganisation,foracceptance,withareportontheTraffickingTrial,statinghowtheuseoftheunboundmixturewasvalidated.ThemainconstructionofthePermanentWorksshallnotstartuntiltheTraffickingTrialareahasbeenacceptedbytheOverseeingOrganisationwithintwoworkingdaysofreceivingtheTraffickingTrialareareport.
803 (11/04) Type 1 Unbound Mixtures
1 (11/04)Type1unboundmixtureshallbemadefromcrushedrock,crushedslag,crushedconcrete,recycledaggregatesorwellburntnon-plasticshaleandmaycontainupto10%bymassofnaturalsandthatpassesthe4mmtestsieve.WherepermittedbyAppendix7/1,crushedgravelcomplyingwithsub-Clause803.7maybeused.
2 ThemixtureshallcomplywithBSEN13285andtherequirementsofTable8/1.ThegradingrequirementsforthemixturearesummarisedinTable8/5.
Amendment-November2009 7
Table 8/5:(11/07)Summary Grading Requirements for Type 1 and Type 4 Unbound Mixtures
Percentage by mass passingSieve size, mm Overall grading range Supplier declared value
grading rangeTolerance on the suppler
declared value63 10031.5 75-9916 43-81 54-72 ±158 23-66 33-52 ±154 12-53 21-38 ±152 6-42 14-27 ±131 3-32 9-20 ±10
0.063 0-9Gradingofindividualbatches-differencesinvaluespassingselectedsieves
Retainedsievesize,mm Passingsievesize,mm PercentagebymasspassingNotlessthan Notmorethan
8 16 7 304 8 7 30
Volume1 Series800SpecificationforHighwayWorks RoadPavements-Unbound,CementandOtherHydraulicallyBoundMixtures
3 ThepropertiesofaggregatesusedinthemixtureshallbeinaccordancewithBSEN13242andtherequirementsofTable8/2.
4 (11/04)Thesizefractionoftheunboundmixturepassingthe0.425mmsizetestsieveshallbenon-plasticasdefinedbyBS1377-2andtestedincompliancetherewith.
5 Wherethemixturecontainsrecycledcoarseaggregateorrecycledconcreteaggregate,itshallcomplywithsub-Clause801.5.
6 Themixtureshallbetransported,laidandcompactedwithoutdryingoutorsegregation.
Additional Requirements for Mixtures Containing Crushed Gravel
7 ForthepurposesofthisClause,gravelisdefinedasaggregatederivedfromanatural,unconsolidated,coarse-grainedsedimentarydepositconsistingofwater-wornrockfragments.Crushedgravelaggregateshallbederivedfromnaturalcobblesretainedonthe63mmtest
Amendment-November2009 8
sieveandcomplywiththecrushed,brokenandtotallyroundedparticlesrequirementinTable8/2.
8 WhererequiredbyAppendix7/1,mixturescontainingcrushedgravelcoarseaggregateshallcomplywiththeminimumCBRrequirementinsub-Clause801.6.WhererequiredbyAppendix7/1,mixturescontainingcrushedgravelcoarseaggregateshallbeassessedusingatraffickingtrialcomplyingwithsub-Clause802.12.
804 (11/04) Type 2 Unbound Mixtures
1 (11/07)Type2unboundmixtureshallbemadefromnaturalsands,gravels,crushedrock,crushedslag,crushedconcrete,recycledaggregatesorwellburntnon-plasticshale.
2 ThemixtureshallcomplywithBSEN13285andtherequirementsofTable8/1.ThegradingrequirementsforthemixturearesummarisedinTable8/6.
Table 8/6:(11/04)Summary Grading Requirements for Type 2 Unbound Mixtures
Percentage by mass passingSieve size, mm Overall grading range Supplier declared value
grading rangeTolerance on the suppler
declared value63 10031.5 75-9916 50-908 30-75 Norequirement Norequirement4 15-601 0-35
0.063 0-9Gradingofindividualbatches-differencesinvaluespassingselectedsieves
Retainedsievesize,mm Passingsievesize,mm PercentagebymasspassingNotlessthan Notmorethan
8 16 5 354 8 5 35
3 ThepropertiesofaggregatesusedinthemixtureshallbeinaccordancewithBSEN13242andtherequirementsofTable8/2.
4 (11/04)Thesizefractionoftheunboundmixturepassingthe0.425mmsizetestsievewhentestedincompliancewithBS1377-2shallhaveaplasticityindexoflessthan6.
5 Wherethemixturecontainsrecycledcoarseaggregateorrecycledconcreteaggregate,itshallcomplywithsub-Clause801.5.
6 WhererequiredbyAppendix7/1,themixtureshallsatisfytheminimumCBRrequirementwhentestedinaccordancewithsub-Clause801.6.
Volume1 Series800SpecificationforHighwayWorks RoadPavements-Unbound,CementandOtherHydraulicallyBoundMixtures
7 Themixtureshallbetransported,laidandcompactedwithoutdryingoutorsegregation,atamoisturecontentwithintherange1%aboveto2%belowthedeclaredvalueofoptimumwatercontentwhentestedasrequiredbyBSEN13285.
805 (11/04) Type 3 (open graded) Unbound Mixtures
1 (11/09)Type3(opengraded)unboundmixtureshallbemadefromcrushedrock,crushedblastfurnaceslagorrecycledconcreteaggregate.WhentestedinaccordancewithClause710,recycledconcreteaggregateusedinType3(opengraded)unboundmixturesshallnotcontainmorethan5%asphalt(ClassRa)andnotmorethan1%othermaterials(ClassX).
2 ThemixtureshallcomplywithBSEN13285andtherequirementsofTable8/1.ThegradingrequirementsforthemixturearesummarisedinTable8/7.
3 ThepropertiesofaggregatesusedinthemixtureshallbeinaccordancewithBSEN13242andtherequirementsofTable8/2.EvidenceofsatisfactoryperformanceinsimilarmixturesshallbeprovidedwhenaggregateswithavalueofLosAngelescoefficientgreaterthan30areused.
4 (11/04)Thesizefractionoftheunboundmixturepassingthe0.425mmsizetestsieveshallbenon-plasticasdefinedbyBS1377-2andtestedincompliancetherewith.
5 Themixtureshallbetransported,laidandcompactedwithoutdryingoutorsegregation.
Amendment-November2009 9
Table 8/7: (11/04)Summary Grading Requirements for Type 3 (open graded) Unbound Mixtures
Percentage by mass passingSieve size, mm Overall grading range Supplier declared value
grading range
Tolerance on the suppler
declared value80 10040 80-9920 50-78 58-70 ±810 31-60 39-51 ±84 18-46 26-38 ±82 10-35 17-28 ±71 6-26 11-21 ±5
0.500 0-20 5-15 ±50.063 0-5
Gradingofindividualbatches-differencesinvaluespassingselectedsievesRetainedsievesize,mm Passingsievesize,mm Percentagebymasspassing
Notlessthan Notmorethan10 20 10 254 10 10 252 4 7 201 2 4 15
806 (11/04) Category B (close graded) Unbound Mixtures
1 (11/09)CategoryB(closegraded)unboundmixtureshallbemadefromcrushedrock,crushedblastfurnaceslagorrecycledconcreteaggregate.WhentestedinaccordancewithClause710,recycledconcreteaggregateusedinCategoryB(closegraded)unboundmixturesshallnotcontainmorethan5%asphalt
(ClassRa)andnotmorethan1%othermaterials(ClassX).
2 ThemixtureshallcomplywithBSEN13285andtherequirementsofTable8/1.ThegradingrequirementsforthemixturearesummarisedinTable8/8.
Volume1 Series800SpecificationforHighwayWorks RoadPavements-Unbound,CementandOtherHydraulicallyBoundMixtures
Table 8/8:(11/04)Summary Grading Requirements for Category B (close graded) Unbound Mixtures
Percentage by mass passingSieve size,
mmOverall grading range
Supplier declared
value grading range
Tolerance on the suppler
declared value
6331.5168421
0.5000.063
10080-9955-8535-6822-6016-479-405-350-9
63-7743-6030-5223-4014-3510-30
±8±8±8±7±5±5
Gradingofindividualbatches-differencesinvaluespassingselectedsieves
Retainedsievesize,mm
Passingsievesize,mm
PercentagebymasspassingNotlessthan Notmorethan
8421
16842
101074
25252015
3 ThepropertiesofaggregatesusedinthemixtureshallbeinaccordancewithBSEN13242andtherequirementsofTable8/2.EvidenceofsatisfactoryperformanceinsimilarmixturesshallbeprovidedwhenaggregateswithavalueofLosAngelescoefficientgreaterthan30areused.
4 Thesizefractionoftheunboundmixturepassingthe0.425mmsizetestsieveshallbenon-plasticasdefinedbyBS1377-2andtestedincompliancetherewith.
5 Themixtureshallbetransported,laidandcompactedwithoutdryingoutorsegregation.
807 (11/07) Type 4 (asphalt arisings) Unbound Mixtures
1 (11/07)Type4unboundmixtureshallbemadefromrecycledaggregatescontainingasphaltarisings,andmaycontaincrushedrock,crushedslag,crushedconcreteorwellburntnon-plasticshaleandupto10%bymassofnaturalsandthatpassesthe4mmsizetestsieve.
2 (11/07)Asphaltarisingsshallbeeitherasphaltroadplaningsorgranulatedasphalt,butexcludingmaterialscontainingtarortar-bitumenbinders.Asphaltplaningsaredefinedasmaterialsderivedfromtheasphaltlayersofthepavementusingamobilemachinefittedwith
millingcutters.Granulatedasphaltisdefinedasasphaltboundmaterialrecycledfromroadsunderreconstructionorsurplusasphaltmaterialdestinedforboundpavementlayers,butunused,whichhasbeengranulated.
3 (11/09)Type4unboundmixtureshallhaveanasphalt(ClassRa)contentgreaterthan50%whentestedinaccordancewithClause710,andtherecoveredbitumencontentoftheasphaltshallbenotmorethan10%whentestedinaccordancewithBS598102.
4 (11/07)Type4unboundmixtureshallcomplywithBSEN13285andtherequirementsofTable8/1.ThegradingrequirementsforthemixturearesummarisedinTable8/5.
5 (11/07)ThepropertiesofaggregatesusedinthemixtureshallbeinaccordancewithBSEN13242andtherequirementsofTable8/2.
6 (11/07)Thesizefractionoftheunboundmixturepassingthe0.425mmsizetestsieveshallbenon-plasticasdefinedbyBS1377-2andtestedincompliancetherewith.
7 (11/07)Wherethemixturecontainsrecycledcoarseaggregateorrecycledconcreteaggregate,itshallcomplywithsub-Clause801.5.
8 (11/07)Themixtureshallbetransported,laidandcompactedwithoutdryingoutorsegregation,atamoisturecontentwithintherange1%aboveto2%belowthedeclaredvalueofoptimumwatercontentwhentestedasrequiredbyBSEN13285.Themoisturecontentshallbedeterminedbyovendryingatareducedtemperaturesettingof45ºCto50ºC.
9 (11/07)WhererequiredbyAppendix7/1,Type4unboundmixturesshallbeassessedusingatraffickingtrialcomplyingwithsub-Clause802.12.
808 and 809 (05/09) Not Used
(05/09)Cement and Other Hydraulically Bound Mixtures
810 (11/04) General Requirements for Cement and Other Hydraulically Bound Mixtures
1 (05/09) Cementandotherhydraulicallyboundmixtures(HBM)shallbeproduced,constructedandtestedinaccordancewiththefollowingClauses.ThepermittedalternativesforeachpartoftheWorksshallbeasdescribedinAppendix7/1.
2 (05/09) Attributesshallbedeemedtohavea‘Norequirement’classificationunlessstatedotherwise.
Amendment-November2009 10
Volume1 Series800SpecificationforHighwayWorks RoadPavements-Unbound,CementandOtherHydraulicallyBoundMixtures
3 (05/09) ThetermslistedbelowshallapplytotheHBMClausesofthisspecification:
ASS aircooledsteelslag
CBGM cementboundgranularmixture
CBR Californiabearingratio
CFA cementtreatedflyash
E modulusofelasticity
FA flyash(alsoknownas‘pulverizedfuel ash’)
FABM flyashboundmixture
Gvxx volumetricexpansioncategory
GBS granulatedblastfurnaceslag
ggbs groundgranulatedblastfurnaceslag
HBM hydraulicallyboundmixture
HRB hydraulicroadbinder(factoryblended hydraulicbinderforroaduse)
HRBBM ‘hydraulicroadbinder’boundmixture
IBI immediatebearingindex
Immxx immersioncategory
IPIxx immediatebearingindexcategory
LA LosAngelescoefficient
LFA limetreatedflyash
MCV moistureconditionvalue
NR norequirement
OWC optimumwatercontent
PTR Pneumatictyredroller
Pulvxx pulverisationcategory
Rc compressivestrength
Rt directtensilestrength
Rit indirecttensilestrength
Rt,E methodofperformanceclassificationbased onthecombinationRtandE.Classesof Rt,EaredesignatedT0toT5,in BSEN14227,whereTdesignatesRt,Eand thenumberindicatestheperformanceclass
SBM slagboundmixture
SC soiltreatedbycement
SFA soiltreatedbyflyash
SHRB soiltreatedbyhydraulicroadbinder
SS soiltreatedbyslag
t time(hours)atconstanttemperaturein definingmaturityforcalculatingthe constructionperiod
TºC ambientairtemperatureindefining maturityforcalculatingconstruction period
Wxx watercontentcategory
4 (05/09) HBMshallbetestedinaccordancewithClause870andthetestmethodsspecifiedinthefollowingClauses.
5 (05/09)Beforeworkcommences,theContractorshallsubmitastatementtotheOverseeingOrganisationthatincludes:
i. Theinformationdetailedinthe‘DesignationandDescription’clauseoftherelevantBSENStandardforthespecifiedHBM,confirmingcompliancewiththerequirementsofthisSeriesandAppendix7/1.
ii. Targetproportionsofconstituents,includingwater.
iii. Mixturedesigndetailsandresults,inaccordancewithClause880.
iv. Methodstatementforthedemonstrationareaandthemainworks,inaccordancewithClause817.
6 (05/09)WhenrequiredbyAppendix7/1,thecoefficientoflinearexpansionofthemixtureshallbedeterminedinaccordancewithClause871.
811 (05/09) Binder Constituents
1 (05/09)BinderconstituentsshallcomplywithBSEN14227exceptthat,unlessotherwiseagreedbytheOverseeingOrganisation:
i. flyashshallbesiliceousflyashcomplyingwithBSEN14227-4;
ii. quicklimeshallcomplywithBSEN14227-11andhaveagradingthatcomplieswithparticlesizeCategory1.
2 (05/09)ThebindercontentshallcomplywithTable8/9,unlessotherwiseagreedbytheOverseeingOrganisation.ThemixtureproportionsusedforproductionshallbebasedonalaboratorymixturedesignprocedureinaccordancewithClause880.
Amendment-November2009 11
Volume1 Series800SpecificationforHighwayWorks RoadPavements-Unbound,CementandOtherHydraulicallyBoundMixtures
TABLE 8/9: (05/09) Minimum Binder or Binder Constituent Additions for HBM
Binder or binder constituent
Application Minimum addition for mix-in-plant method of construction using batching by mass (by dry mass of mixture)
Minimum addition for mix-in-plant method of construction using volume batching and for mix-in-place construction (by dry mass of mixture)
Lime(quicklimeorhydratedlime)
whenusedwithanotherbinderconstituent
1.5% 2%
whenusedastheonlybinderinFABM5
3% 4%
Cement whenusedwithanotherbinderconstituent
2% 3%
whenusedastheonlybinderconstituentinCBGM
TheappropriatevaluefromBSEN14227-1,Table1
1%+(theappropriatevaluefromBSEN14227-1,Table1)
whenusedastheonlybinderconstituentinsoiltreatedbycement(SC)
3% 4%
Groundgranulatedblastfurnaceslag(ggbs)
whenusedwithcement 2% 3%whenusedwithlime 3% 4%
Air-cooledsteelslag(ASS)
whenusedwithGBS(seeNote)
2.5% 3%
Dryflyash(FA) whenusedwithcement 4% 5%whenusedwithlime 5% 6%
Granulatedblastfurnaceslag(GBS)
whenusedwithlime 6% 8%whenusedwithASS(seeNote)
2.5% 3%
Wet(conditioned)flyash(FA)
Allapplications 6% 8%
Hydraulicroadbinder Allapplications 3% 4%NOTE:WhenGBSandASSareusedincombination,thesumofthetwoshallbenotlessthan11%.
Amendment-November2009 12
812 (05/09) Storage of Constituents
1 (05/09) Aggregatesshallbestoredonafirmandcleansubstrateavoidingcontaminationwithotherconstituents.Fineaggregateshallbestoredattheproductionlocationforatleast24hoursbeforeuse.
2 (05/09) Lime,cement,ggbs,HRBanddryFAshallbestoredinsilos.
3 (05/09)Wet(conditioned)FAshallhavenoagglomerationsgreaterthan10mmsize.Thisshallbedeterminedbysievingsamplesthrougha10mmsizetestsieveusingnotmorethan10secondsofgentleagitationbyhand.Wet(conditioned)flyashshallbestoredatthesourceorattheproductionlocationforat
least72hoursbeforeuse,andhaveaminimumwatercontentof10%.
4 (05/09) GBSandASSshallbestoredasspecifiedinsub-Clause812.1andusedwithin3monthsofdeliverytotheproductionlocation.
813 (05/09) General Requirements for Production and Layer Construction
1 (05/09) HBMshallbeproducedandlaidusingoneofthefollowingmethods,asspecifiedinthefollowingmixtureClauses:
(i) mix-in-plantmethodofconstructionusingbatchingbymass,inaccordancewithClause814;
Volume1 Series800SpecificationforHighwayWorks RoadPavements-Unbound,CementandOtherHydraulicallyBoundMixtures
(ii) mix-in-plantmethodofconstructionusingvolumebatching,inaccordancewithClause815;
(iii) mix-in-placemethodofconstruction,inaccordancewithClause816.
2 (05/09)Constructionoflayers,includingmultipleliftlayers,andanyreworkingandreuse,shallbecompletedwithinthelesserof8hours,theconstructionperiod
specifiedinTable8/10orthemixturesettingtime.ThetimeshallbemeasuredfromtheadditioneventdefinedinTable8/10tocompletionofcompaction.
3 (05/09)Theconstructionperiod,indegreehours,shallbethesummationoftheproductsoftheaverageairtemperatureabove3ºC(TºC)andtimeforeachperiod(thours):i.e.constructionperiodlimit=Σ(T.t).Theairtemperatureduringtheinterval,t,shallnotfluctuatebymorethan4ºC.
Amendment-November2009 13
TABLE 8/10: (05/09) Construction Period for HBM Layers
Binder Addition event defining the start time for calculating maximum construction period
Maximum construction period (ºC hours)
Cement,cementwithFAorcementwithggbs
Additionofcement 35
LimewithGBSorFA Additionoflime 1,600LimeandgypsumforFABM5 Additionoflimeandgypsum 70GBS+ASS AdditionofASSandGBS 3,000Limewithggbs Additionofggbs 200ifggbsaddedafterlime
1,600ifggbsaddedbeforelimeHRB AdditionofHRB WorkabilityPeriodat20°C
determinedinaccordancewithBSEN13286-45multipliedby17
4 (05/09)Mixturesusedinbaselayersshallbebatchedbymassandpaverlaidinasinglelift.Constructionofbasesbyothermethodsshallonlybepermittedinconfinedspaceswhereitisimpracticableforapavertooperate,whenagreedbytheOverseeingOrganisation.
5 (05/09)Whenquicklimeisused,fullhydrationshallbecompletepriortofinalcompaction.
6 (05/09)Layingshallbecarriedoutinawaythatavoidssegregationanddryingofthesurface.Thetemporaryintermediatesurfaceswithinamultipleliftlayershallbesprayedwithwatertopreventsurfacedrying.
7 (05/09)Theminimumcompactedliftthicknessinamultipleliftlayershallbe150mm.
8 (05/09)Making-upoflevelafterinitialcompactionshallnotbepermittedforsingleliftworkingortheuppermostliftofmultipleliftworking.
9 (05/09)TheedgeofpreviouslycompactedHBMorothermaterialshallbeverticalandstraightbeforefreshHBMislaidagainstit.
10 (05/09)CompactionofHBMlayers,includingtheintermediateliftsofmultipleliftworking,shallbecompletedwithoutdryingoutandbeforesettingofany
partofthelayerandshallmeettherequirementsfordensityinclause870.
11 (05/09)CompactionofHBM,otherthanFABM5,shallbecarriedoutbyvibratingrollerand/orpneumatic-tyredroller(PTR).WherevibratingrollercompactionisusedonmixturesspecifiedinClauses830to835itshallbefollowedbyatleast8passesofaPTRwithawheelloadingofnotlessthan30kN.OnlyPTRcompactionwithawheelloadingofnotlessthan30kNshallbeappliedtoFABM5.
12 (05/09)Oncompletionofcompactionthesurfaceshallbeclosed,freefromridges,cracks,loosematerial,visiblevoids,ruts,shearplanesandotherdefects.Alldefectiveareasshallberectifiedwithinthetimeperiodspecifiedinsub-Clause813.2.Ifrectificationisnotcompletedwithinthespecifiedtimeperiod,thedefectiveareashallberemovedtothefullthicknessofthelayer,andnewmixturelaidandcompacted.
(05/09)Cold and Wet Weather Working
13 (05/09)Duringcoldweather:
(i) thetemperatureofHBMshallnotbelessthan5ºCatthetimeoflaying;
Volume1 Series800SpecificationforHighwayWorks RoadPavements-Unbound,CementandOtherHydraulicallyBoundMixtures
(ii) HBMshallnotbelaidonafrozensurface;
(iii) layingofHBMshallceasewhentheairtemperaturefallsbelow3ºC,andlayingshallnotberesumeduntiltherisingairtemperaturereaches3ºC;
(iv) thelayingofHBMusingbinderscontaininglessthan3%ofCEM1cement,bydrymassofmixture,shallberestrictedinusetotheperiodfrom1Mayto30September,unlessotherwiseagreedbytheOverseeingOrganisation.
14 (05/09)Inthecaseofheavyorpersistentrain,productionshallceaseandanylaidmaterialshallbecompactedimmediately.
(05/09)Curing, Protection and Trafficking
15 (05/09)Oncompletionofcompactionthelayershallbecuredtopreventlossofmoistureby:
Amendment-November2009 14
(i) applicationofabitumenemulsionspraycomplyingwithClassC40B4,asspecifiedintheNationalForewordtoBSEN13808toproduceanevenandcompletecoverageofatleast0.2kg/m2ofresidualbitumen.Beforesprayingcommences,thesurfaceshallbefreeofallloosematerialandstandingwater.Thecuringmembraneshallbeprotectedfromanydamageuntiltheconstructionoftheoverlayinglayer;
(ii) applicationofamist/fog/lightsprayofwater,sufficienttokeepthesurfacecontinuouslywetuntilthespecifiedstrengthoftheHBMhasbeendevelopedorthelayerisoverlaid.
16 (05/09)TraffickingofHBMlayersshallcomplywiththerequirementssetoutinTable8/11andsub-Clause813.17.ShouldanyHBMlayerexhibitsignsofdamage,traffickingshallceaseimmediatelyandshallonlyberesumedoncethelayerhasgainedsufficientstabilitytoresistdamage.
(05/09)TABLE 8/11: Trafficking of HBM Layers
HBM Designation Clause reference TraffickingCBGM 821,822and823 Sub-Clause813.17.HBM 830,831,and835 Notrestricted.
832 NotrestrictedprovidedthattheIBIrequirementofsub-Clause832.6issatisfied.
FABM5withcement 834 Notpermittedfor7daysunlessoverlaidbyatleast150mmofboundmaterialwithintheconstructionperiod.
FABM5withlime 834 Onlytheminimumamountoftrafficrequiredtoconstructthenextlayerispermitted.
SC,SS,SHRBandSFA 840 NotrestrictedprovidedthattheIBIrequirementsofTable8/13aresatisfied.
Formixturescontainingcohesivesoilorchalk,thetestspecimensmadeatthesametimeasthespecimensrequiredinClause870butcuredunderthesameconditionsastheinsitutreatedsoilshallalsohaveachievedanaveragestrengthofatleastClassC0.8/1.0.
17 (05/09)CBGMshallnotbetraffickedfor7daysunlessthelayercomplieswiththefollowing:
(i) thelayeriscompactedbybothvibratingrollerandPTRinaccordancewithsub-Clause813.11tocomplywiththerequirementsofsub-Clause813.12;
(ii) themixturecontainsatleast50%bymassofcoarseaggregatecomplyingwithBSEN13242,CategoryC90/3for‘crushedorbrokenparticles’;
(iii) testspecimensmadeatthesametimeasthespecimensrequiredinClause870butcuredunderthesameconditionsasthein-situCBGMhaveachievedanaveragestrengthofatleastClassC3/4.
18 (05/09)Surfacecontaminationshallbeavoidedasfarasispracticableandanyunavoidablecontaminationshallberemovedpriortooverlaying.Reworkingandre-compactionofthelayershallonlybepermitted
Volume1 Series800SpecificationforHighwayWorks RoadPavements-Unbound,CementandOtherHydraulicallyBoundMixtures
withintheconstructionperiodsetoutinTable8/10.Reworkingshallonlybepermittedwhenthewatercontentrequirementsofthereworkedmaterialaremaintainedwithinthelimitsstatedinthemethodstatement.
19 (05/09)Beforeoverlaying,anyloosematerialshallberemovedandreplacedtothefulldepthofthelayeror,ifwithintheconstructionperiodsetoutinTable8/10,reworkedasspecifiedinsub-Clause813.18.
20 (05/09)Dailyrecordsheetscomplyingwithsub-Clause817.4shallbesubmittedtotheOverseeingOrganisationbystartofworkonthenextworkingday,detailing:
(i) spreadrate/batchingrecordresults;
(ii) depthmeasurements;
(iii) densitytestmeasurements;
(iv) sampleandtestlocations;
(v) constructionperiodrecordsshowingthetime(s)ofmixing,wateraddition,completionofcompactionandapplicationofcuringmembrane.
814 (05/09) Mix-in-Plant Method of Construction Using Batching by Mass
1 (05/09)TheHBMshallbeproducedinastationarymixingplantthatbatchesbymassandmixesinaforced-actionmixer,allowingsufficienttimeinthemixertoproduceahomogenousmixture.
2 (05/09)Themixingplantshallhaveanautomatedsurveillanceanddatacollectionsystem.
3 (05/09)HBMshallbetransporteddirectlytothepointwhereitistobelaidandprotectedfromtheweatherduringtransitandwhilstawaitingtipping,unlessotherwiseagreedbytheOverseeingOrganisation.
815 (05/09) Mix-in-Plant Method of Construction Using Volume Batching
1 (05/09)TheHBMshallbeproducedinastationarymixingplantthatbatchesbyvolumeandmixesinaforcedactionmixer,allowingsufficienttimeinthemixertoproduceahomogenousmixture.
2 (05/09)HBMshallbetransporteddirectlytothepointwhereitistobelaidandprotectedfromtheweatherduringtransitandwhilstawaitingtipping,unlessotherwiseagreedbytheOverseeingOrganisation.
3 (05/09)Dispensingaccuracyshallbeverifiedbyreconciliationbetweenconstituentdeliveriesandtheareaanddepthofcompletedlayerforeach5000m2ofwork,orpartthereof,duringeachday’soperations.
816 (05/09) Mix-in-Place Method of Construction
1 (05/09)Mixed-in-placeHBMshallbeproducedbyanin-situpulverizing-mixingprocesswiththeaddedmixingwaterinjecteddirectlyintothemixtureduringthemixingprocess.Thepulverizing-mixingprocessshallberepeateduntilahomogenousmixtureisproduced.
2 (05/09)Whenbinderconstituentsaredispensedontothesurfacetobepulverized-mixed,therateofspreadshallbeconfirmedbysitecheckscarriedoutinaccordancewithClause870.Foreachgroupof5readingsthemeanrateofspreadofmaterialshallbewithin±10%ofthestatedtargetrateandeachindividualvalueshallbewithin±15%ofthemeanvalueofthegroupof5readings.
3 (05/09)Theaccuracyofthesystemusedtodispensebinderconstituentsshallbeverifiedbyreconciliationbetweenconstituentdeliveriesandtheareaanddepthofcompletedlayerforeach5000m2ofwork,orpartthereof,duringeachday’soperations.
4 (05/09)Mixingoffreshmaterialshallensureaminimumoverlapof200mmwithpreviouslymixedmaterial.
5 (05/09)Wherelimeisusedtogranulatecohesivesoilsitshallbeaddedandmixedwiththesoilusingatleasttwopassesofthepulverizer-mixerbetween24and96hoursbeforethesubsequentadditionofcement,FA,HRBorggbs.Thesurfaceofthelayershallbesealedbyrollingimmediatelyafteraddingandmixinglime.TheMCVduringthisperiod,knownasthemellowingperiod,shallcomplywithClause840.
817 (05/09) Method Statement and Demonstration Area
Method Statement
1 (05/09)Atleast10dayspriortoconstructingthedemonstrationareaspecifiedinsub-Clause817.5,theContractorshallprovideafullmethodstatementfortheapprovaloftheOverseeingOrganisation.Thestatementshalldetailtheoperatives,plant,materialsandproceduresfortheconstructionofdemonstrationarea(s)andoftheworks,includingprocedures.Thestatementshallalsoincludeproceduresforinducedcracking,if
Amendment-November2009 15
Volume1 Series800SpecificationforHighwayWorks RoadPavements-Unbound,CementandOtherHydraulicallyBoundMixtures
requiredbyAppendix7/1,andtheprocedurestobeappliedduringinclementweather,plantbreakdownsandotherunscheduledevents.
2 (05/09)Themethodstatementshallincludetheintendedmixtureproportionswithsupportingdatafromtrialmixresultsand/orhistoricrecordstojustifytheproportions,thewatercontent(orMCV)limitsand(ifapplicable)spreadratesforallstagesoftheWork.
3 (05/09)Wheremultipleliftworkingisused,themethodstatementshalldetailthemethodsusedtoassurethatbondbetweentheindividualliftsisachieved.Themethodstatementshallalsodetailtheprocedurestobeusedtoconfirmthatbondhasbeenachievedinthedemonstrationareaandintheworks.
4 (05/09)Themethodstatementshallincludeasamplerecordsheetforthesubmissionofthedatarequiredbysub-Clause813.20.
(05/09)Demonstration Area
5 (05/09)Priortothecommencementofthemainworks,theContractorshallconstructademonstrationareaofatleast800m2conformingtothesubmittedmethodstatement.Thedemonstrationareashallincludeatransverseend-of-dayjointand(ifappropriate)multipleliftworking.Thedemonstrationareamaybeacceptedintothepermanentworks,whereagreedbytheOverseeingOrganisation.WheretheContractorcanproducedocumentaryevidenceofsimilarworkcarriedouttothisspecificationduringtheprevious6months,theOverseeingOrganisationmayallowtheworkstoproceedwithoutthedemonstrationarea.
6 (05/09)Wheremultipleliftworkingisused,thedemonstrationareashallconfirmtheeffectivenessoftheproceduresusedtoassurethatbondbetweentheindividualliftscanbeachieved.
7 (05/09)Whereinducedcrackingisrequired,thedemonstrationareashallincludecrackinductionatthespecifiedspacing.Theeffectivenessoftheprocedureusedshallbecheckedwithin28daysofconstruction,byrecoveringfourevenlyspaced150mmdiacoresfromthelineoftheinducedcracksandassessingeachcoreforcompliancewithsub-Clause818.2.
8 (05/09)Themixtureconstituents,proportions,layingandcompactionplantandconstructionproceduresusedforthedemonstrationareashallnotbechangedunlesstheContractorlaysafurtherdemonstrationareaorthechangesareagreedbytheOverseeingOrganisation.
818 (11/04) Induced Cracking of HBM
1 (05/09)WhererequiredbyAppendix7/1,transversecracksshallbeformedatthespecifiedspacingwithatoleranceof±150mm.WherethepavementismadeupoftwoormorelayersofHBMwithinducedcracks,thecracksintheoverlyingHBMlayershallalignwiththeinducedcracksinthelayerbelowwithatoleranceof±100mm.
2 (05/09)Cracksshallbeinducedinfreshmaterialafterinitialcompaction.Thetransversecracksshallbeinducedbygroovingthefreshmaterialtoformstraightverticalgroovesnotmorethan20mmwide,toadepthofbetweenonehalfandtwothirdsofthelayerthicknessoverthefullwidthofthepavement.Bitumenemulsionshallbepouredorsprayedintothegroovespriortofinalcompaction,toformacrackinducingmembrane.ThebitumenemulsionshallcomplywithClassC40B4,asspecifiedintheNationalForewordtoBSEN13808.Duringfinalcompactionofthemixture,thesurfaceofthegrooveshallbefullyclosedthroughoutitsfulllength.Thebitumeninthegrooveshallbefullyencasedandremaincontinuous,withnotlessthan70%ofthesidesofthegroovecoatedwithbitumen.
3 (05/09)WhererequiredbyAppendix7/1,longitudinalcracksshallbeinducedusingtheprocedurespecifiedinsub-Clause818.2.
819 (05/09) Not Used
820 (05/09) Aggregates
1 (05/09)TheaggregatesusedinHBMshallcomplywithBSEN13242andtheselectedrequirementslistedinTable8/12.WhererecycledcoarseaggregateorrecycledconcreteaggregateisusedinHBM,itshallalsobetestedinaccordancewithClause710andcomplywiththeadditionalrequirementsfortheproportionofthecomponentslistedinTable8/12.
2 (05/09)WhenrequiredbyAppendix7/1,anexistingpavementlayerthatistousedtoproduceHBMshallbetestedtoconfirmcompliancewithsub-Clause820.1.
Amendment-November2009 16
Volume1 Series800SpecificationforHighwayWorks RoadPavements-Unbound,CementandOtherHydraulicallyBoundMixtures
(11/09)Table 8/12: Aggregate Requirements for HBM
Clause reference 821 822 823 830 831 832 835
HBM designation CBGM A CBGM B CBGM C FABM 1 HRBBM 1
SBM B2, FABM 2
HRBBM 2
SBM B3, FABM 3
HRBBM 3
SBM B1-1, B1-2, B1-3 &
B1-4Categories for aggregate properties, BS EN 13242
Crushedorbrokenparticlesandtotallyroundedparticlesincoarseaggregate
CNR(Note1)
CNRunlessotherwisespecifiedin
Appendix7/1
C90/3orC50/30,asspecifiedinAppendix7/1
(Note2)
CNR(Note1)
C90/3orC50/30asspecifiedinAppendix
7/1Resistancetofragmentationofcoarseaggregate
LANR
LA50
orLA60
asspecifiedinAppendix
7/1
LA50
LA50
orLA60
asspecifiedinAppendix
7/1
LA50 LANR LA50
Acid-solublesulfatecontent(Note3)
Air-cooledblast-furnaceslag-AS1,0
Otheraggregates-AS0,2
Totalsulfurcontent(Note3)
Air-cooledblast-furnaceslag-S2
Otheraggregates-S1
Other requirements, BS 1377-2Finesquality(Note4)
NR(Note1)
Non-plastic NR(Note1)
Non-plastic
Proportion of components, Clause 710Maximumglasscontent(ClassRg) 40 40 40 40 40 40 40
Maximumimpuritiescontent(ClassX) 5 3 3 3 3 5 3
NOTES:1.ThesuffixNRdenotesthatthe‘Norequirement’categoryapplies.2.CNRifFABM1containsatleast3%CEM1cementbydrymassofthemixtureandtraffickingispreventedfor7days.3.WheretheContractorisabletoprovideevidenceofmixturestabilityoveranextendedperiodthentheOverseeingOrganisationmayconsidertheuseofhigherlimits.4.Whererequired,thesizefractionoftheaggregatepassingthe0.425mmsizetestsieveshallbenon-plasticasdefinedbyandtestedincompliancewithBS1377-2.
Amendment-November2009 17
821 (05/09) Cement Bound Granular Mixtures A (CBGM A)
1 (05/09) CementboundgranularmixturesA(CBGMA)shallcomplywithBSEN14227-1andhavebinderconstituentproportionscomplyingwiththerequirementsofClause811.
2 (05/09) AggregateshallcomplywiththerequirementsofClause820andshallhaveacombinedgradingthatcomplieswithEnvelopeAfromBSEN14227-1,Figure1.
3 (05/09)Thestrengthafterimmersionshallbeatleast80%ofthenon-immersedstrength,whentestedinaccordancewiththelaboratorymixturedesignrequirementsspecifiedinClause880.
4 (05/09)ThemethodofconstructionshallbeinaccordancewithClause813andeitherClause814,Clause815orClause816.
5 (05/09)ThelaboratorymechanicalperformanceshallcomplywiththerequirementsofAppendix7/1,whensampledandtestedinaccordancewithClause870.
822 (05/09) Cement Bound Granular Mixtures B (CBGM B)
1 (05/09)CementboundgranularmixturesB(CBGMB)shallcomplywithBSEN14227-1,andhavebinderconstituentproportionscomplyingwiththerequirementsofClause811.
Volume1 Series800SpecificationforHighwayWorks RoadPavements-Unbound,CementandOtherHydraulicallyBoundMixtures
2 (05/09)AggregatesshallcomplywiththerequirementsofClause820andshallhaveacombinedgradingthatcomplieswithEnvelopeBfromBSEN14227-1,Figure1.Alternatively,thetotalmixturegradingshallcomplywiththegradingenvelopeCategoryG2fromBSEN14227-1,AnnexB,FigureB2.
3 (05/09)Thestrengthafterimmersionshallbeatleast80%ofthenon-immersedstrength,whentestedinaccordancewiththelaboratorymixturedesignrequirementsspecifiedinClause880.
4 (05/09)ThemethodofconstructionshallbeinaccordancewithClause813andClause814.
5 (05/09)ThelaboratorymechanicalperformanceshallcomplywiththerequirementsofAppendix7/1,whensampledandtestedinaccordancewithClause870.
823 (05/09) Cement Bound Granular Mixtures C (CBGM C)
1 (05/09)CementboundgranularmixturesC(CBGMC)shallcomplywithBSEN14227-1,andhavebinderconstituentproportionscomplyingwiththerequirementsofClause811.
2 (05/09)AggregatesshallcomplywiththerequirementsofClause820andshallhaveatotalmixturegradingthatcomplieswithgradingenvelopeCategoryG1fromBSEN14227-1,AnnexB,FigureB2for0/20sizemixtures,FigureB3for0/14mmsizemixturesorFigureB4for0/10mmsizemixtures.
3 (05/09)Thecompacityofthemixtureshallbeatleast0.8,whencalculatedinaccordancewithBSEN14227-2,AnnexC.ThemaximumdrydensityvalueusedforthecalculationshallbedeterminedinaccordancewithBSEN13286-50,usingthemodifiedProctor(4.5kgrammer)procedurefromBSEN13286-2.
4 (05/09)Thestrengthafterimmersionshallbeatleast80%ofthenon-immersedstrength,whentestedinaccordancewiththelaboratorymixturedesignrequirementsspecifiedinClause880.
5 (05/09)ThemethodofconstructionshallbeinaccordancewithClause813andClause814.
6 (05/09)ThelaboratorymechanicalperformanceshallcomplywiththerequirementsofAppendix7/1,whensampledandtestedinaccordancewithClause870.
824 to 829 (05/09) Not Used
830 (05/09) Fly Ash Bound Mixture 1 (FABM 1) and Hydraulic Road Binder Bound Mixture 1 (HRBBM 1)
1 (05/09)ThemixtureshallcomplywiththerequirementsofBSEN14227-3forFlyAshBoundMixture1ortherequirementsofBSEN14227-5forHydraulicRoadBinderBoundMixture1,asspecifiedinAppendix7/1,andhavebinderconstituentproportionscomplyingwiththerequirementsofClause811.
2 (05/09)AggregateshallcomplywiththerequirementsofClause820.
3 (05/09)Thestrengthafterimmersionshallbeatleast80%ofthenon-immersedstrength,whentestedinaccordancewiththelaboratorymixturedesignrequirementsspecifiedinClause880.
4 (05/09)ThemethodofconstructionshallcomplywithClause813andClause814.
5 (05/09)ThelaboratorymechanicalperformanceshallcomplywiththerequirementsofAppendix7/1,whensampledandtestedinaccordancewithClause870.
831 (05/09) Slag Bound Mixture B2 (SBM B2), Fly Ash Bound Mixture 2 (FABM 2) and Hydraulic Road Binder Bound Mixture 2 (HRBBM 2)
1 (05/09)ThemixtureshallcomplywiththerequirementsofBSEN14227-2forSlagBoundMixtureB2ortherequirementsofBSEN14227-3forFlyAshBoundMixture2ortherequirementsofBSEN14227-5forHydraulicRoadBinderBoundMixture2,asspecifiedinAppendix7/1,andhavebinderconstituentproportionscomplyingwiththerequirementsofClause811.
2 (05/09)AggregateshallcomplywiththerequirementsofClause820.
3 (05/09)SBMB2shallhaveatotalmixturegradingthatcomplieswithgradingenvelopeCategoryG1orG2fromBSEN14227-2,Figure5for0/20sizemixtures,Figure6for0/14mmsizemixturesorFigure7for0/10mmsizemixtures..
4 (05/09)FABM2shallhaveatotalmixturegradingthatcomplieswithgradingenvelopeCategoryG1orG2fromBSEN14227-3,Figure3for0/20sizemixtures,Figure5for0/14mmsizemixturesorFigure7for0/10mmsizemixtures.
5 (05/09)HRBBM2shallhaveatotalmixturegradingthatcomplieswithgradingenvelopeCategoryG1orG2fromBSEN14227-5,Figure2for0/20mmsize
Amendment-November2009 18
Volume1 Series800SpecificationforHighwayWorks RoadPavements-Unbound,CementandOtherHydraulicallyBoundMixtures
mixtures,Figure3for0/14mmsizemixturesandFigure4for0/10mmsizemixtures
6 (05/09)Thestrengthafterimmersionshallbeatleast80%ofthenon-immersedstrength,whentestedinaccordancewiththelaboratorymixturedesignrequirementsspecifiedinClause880.
7 (05/09)ThemethodofconstructionshallbeinaccordancewithClauses814and813.
8 (05/09)ThelaboratorymechanicalperformanceshallcomplywiththerequirementsofAppendix7/1,whensampledandtestedinaccordancewithClause870.
832 (05/09) Slag Bound Mixture B3 (SBM B3), Fly Ash Bound Mixture 3 (FABM 3) and Hydraulic Road Binder Bound Mixture 3 (HRBBM 3)
1 (05/09)ThemixtureshallcomplywiththerequirementsofBSEN14227-2forSlagBoundMixtureB3ortherequirementsofBSEN14227-3forFlyAshBoundMixture3ortherequirementsofBSEN14227-5forHydraulicRoadBinderBoundMixture3,asspecifiedinAppendix7/1,andhavebinderconstituentproportionscomplyingwiththerequirementsofClause811.
2 (05/09)AggregateshallcomplywiththerequirementsofClause820.
3 (05/09)Thestrengthafterimmersionshallbeatleast80%ofthenon-immersedstrength,whentestedinaccordancewiththelaboratorymixturedesignrequirementsspecifiedinClause880.
4 (05/09)ThemethodofconstructionshallbeinaccordancewithClause813andeitherClause814,Clause815orClause816.
5 (05/09)ThelaboratorymechanicalperformanceshallcomplywiththerequirementsofAppendix7/1,whensampledandtestedinaccordancewithClause870.
6 (05/09)ThemixturedesignproceduresspecifiedinClause880shallincludethedeterminationoftheimmediatebearingatthetargetwaterandbindercontent.ThemixtureshallcomplywithImmediateBearingIndexCategoryIPI40.WhenapprovedbytheOverseeingOrganisation,andwherethemixtureisnotsubjecttodirecttrafficking,themixtureshallcomplywithImmediateBearingIndexCategoryIPI25.
7 (05/09)TherequirementsofClause832.6shallnotapplyifthemixturecontainsatleast3%cementbymassofthedrymixtureandtrafficisnotpermittedtousethelayerforthefirst7days.
Amendment-November2009 19
833 (11/04) Not Used
834 (11/04) Fly Ash Bound Mixture 5 (FABM 5)
1 (05/09)ThemixtureshallcomplywithBSEN14227-3forFlyAshBoundMixture5,andhavebinderconstituentproportionscomplyingwiththerequirementsofClause811.
2 (05/09)Thestrengthafterimmersionshallbeatleast80%ofthenon-immersedstrength,whentestedinaccordancewiththelaboratorymixturedesignrequirementsspecifiedinClause880.
3 (05/09)Forlime-treatedflyashmixtureswithgypsumaddedasanadditionalconstituent,themethodofconstructionshallbeinaccordancewithClause813and814.Forothermixtures,themethodofconstructionpermittedshallcomplywithClause813andeitherClause814,Clause815orClause816.
4 (05/09)ThelaboratorymechanicalperformanceshallcomplywiththerequirementsofAppendix7/1,whensampledandtestedinaccordancewithClause870.
835 (05/09) Slag Bound Mixtures B1-1, B1-2, B1-3 and B1-4 (SBM B1)
1 (05/09)ThemixtureshallcomplywithBSEN14227-2forSBMB1-1,SBMB1-2,SBMB1-3orSBMB1-4,asspecifiedinAppendix7/1,andhavebinderconstituentproportionscomplyingwiththerequirementsofClause811.
2 (05/09)AggregatesshallcomplywiththerequirementsofClause820.
3 (05/09)Thestrengthafterimmersionshallbeatleast80%ofthenon-immersedstrength,whentestedinaccordancewiththelaboratorymixturedesignrequirementsspecifiedinClause880.
4 (05/09)ThemethodofconstructionshallbeinaccordancewithClause813and814.
5 (05/09)ThelaboratorymechanicalperformanceshallcomplywiththerequirementsofAppendix7/1,whensampledandtestedinaccordancewithClause870.
836 to 839 (05/09) Not Used
Volume1 Series800SpecificationforHighwayWorks RoadPavements-Unbound,CementandOtherHydraulicallyBoundMixtures
840 (05/09) Soil Treated by Cement (SC), Soil Treated by Slag (SS), Soil Treated by Fly Ash (SFA) and Soil Treated by Hydraulic Road Binder (SHRB)
1 (05/09)ThemixtureshallbeasspecifiedinAppendix7/1andcomplywiththeappropriaterequirementsselectedfromTable8/13andthefollowing:
(i) BSEN14227-10,forsoiltreatedbycement(SC);
(ii) BSEN14227-12,forsoiltreatedbyslag(SS);
(iii) BSEN14227-13,forsoiltreatedwithhydraulicroadbinder(SHRB)
(iv) BSEN14227-14,forsoiltreatedbyflyash(SFA).
ThemixtureshallalsohavebinderconstituentproportionscomplyingwiththerequirementsofClause811.
2 (05/09)Notlessthan95%ofthesoilshallpassthe63mmsizetestsievewhentestedinaccordancewithEN933-1andthemaximumparticlesizeofthesoilshallnotexceed25%ofthelayerdepth.
3 (05/09)WhentestedinaccordancewithTRLReport447,TestNo.4,soilwithatotalpotentialsulfate(TPS)contentlessthan0.25%sulfate(asSO4)shallbedeemedsuitablefortreatment,ifthelaboratorymixturedesignprocedureconfirmsthatthemixturecomplieswiththe‘resistancetowater’requirementsspecifiedinTable8/13.Soilwithatotalpotentialsulfate(TPS)equaltoorgreaterthan0.25%sulfate(asSO4)shallonlybedeemedsuitablefortreatmentwhereagreedbytheOverseeingOrganisation.
4 (05/09)ThemethodofconstructionshallbeinaccordancewithClause813andeitherClause814,Clause815orClause816.
5 (05/09)ThelaboratorymechanicalperformanceshallcomplywiththerequirementsofAppendix7/1,whensampledandtestedinaccordancewithClause870.
Amendment-November2009 20
TABLE 8/13:(05/09)Requirements for Soil Treated by Cement (SC), Slag (SS) and Fly Ash (SFA)
Mixture parameter Requirement Category BS EN 14227 -10, -12, -13, -14 reference
Non-cohesive soil mixtures
Cohesive soil mixtures and chalk mixtures
Minimumwatercontent
(Expressedasaproportionoftheoptimumwatercontent,determinedinaccordancewithBSEN13286-4,Vibrating
hammermethod)
W0,9
WNR(Note1) Table1W1,0
formixturescontainingquicklime
DegreeofPulverization(DeterminedinaccordancewithBSEN13286-48)
PulvNR(Note1)
Pulv60 Table2
ImmediateBearingIndex(Note2)
(DeterminedinaccordancewithClause880)
IPI40(Note3)
IPI15 Table3
MoistureConditionValue
(DeterminedinaccordancewithBSEN13286-46)
MCVNR(Note1)
MCV8/12atfinalmixingandcompaction(Note4)
Table4
Laboratorymechanicalperformance
(Compressivestrengthortensilestrength)
RcorRt,E,asspecifiedinAppendix7/1
Table6forRcFigure1for
Rt,EResistancetowater-strengthafterimmersion
(Ri/Rratio,determinedinaccordancewithClause880)I0,8 Table7
Resistancetowater-volumetricswelling
(DeterminedinaccordancewithBSEN13286-49)
NR(Note1)
SC-GV5 Table9(EN14227-10)
SS,SRBandSFA–GVtobenotgreaterthan
5%
Clause9.1.4(EN14227-12,-13and-14)
NOTES:1.ThesuffixNRdenotesthatthe‘Norequirement’categoryapplies.2.WhereSCisnottobetraffickedwithin7days,IPINRmaybeused.3.IPI25wherethemixtureisnotsubjecttodirecttrafficking.4.Forcohesivesoilmixtures,therequirementalsoappliesduringthemellowingperiod.
Volume1 Series800SpecificationforHighwayWorks RoadPavements-Unbound,CementandOtherHydraulicallyBoundMixtures
Amendment-November2009 21
841 to 869 (11/04) Not Used
870 (05/09) Testing, Control and Checking of HBM
General
1 (05/09)Tests,controlsandchecksshallbecarriedoutinaccordancewiththerequirementsinTable8/14andthefollowingsub-ClausesatlocationsdeterminedbytheOverseeingOrganisation,unlessotherwisestatedinAppendix1/5.WheretheOverseeingOrganisationissatisfiedthataconsistentqualityofworkisbeingachieveditmayorderthefrequencyoftestingtobereducedtohalfthatrequiredinTable8/14.WhereatestreferenceisshowninTable8/14,thetestingshallbecarriedoutincompliancewiththerequirementsofClause105andbeundertakenbyanorganisationaccreditedinaccordancewithBSENISO/IEC17025forthetestmethod.
Sampling
2 (05/09)SamplingshallbeinaccordancewithBS1924-1.WhereabulksampleofHBMistakenfromalayer,itshallbetakenfromthefulldepthofthelayer,usedwithoutfurthermixing,andnotcombinedwithotherbulksamples.
Spread Checks for the Mix-in-Place Method of Construction
3 (05/09)Therateofspreadofaddedconstituentsshallbedeterminedbyweighingtheamountofmaterialretainedonfivetrays(ormats)ofknownarealaidinthepathofthespreadingmachine.Thetrays(ormats)shallbepositionedatpointsequallyspacedalongadiagonalbisectinglinetheareaofcoveragesoastoassessthefullwidthofdischargefromthespreadingmachine.
Depth of Mixing for the Mix-in-Place Method of Construction
4 (05/09)Thedepthofmixingshallbecheckedbyexcavationandinspectiononcompletionofeachstageofthepulverizing-mixingprocess.Thedepthofmixingshallbereferencedtothedesignlevelsforthepavementbypreciselevelingofthestabilizedsoilinterface(orothertechniquesapprovedbytheOverseeingOrganisation)toensurethatthelevelattheundersideofthestabilizedlayerisinaccordancewiththespecifiedrequirements.
(05/09) Standardisation of Nuclear Density Gauges and Measurement of In-situ Wet Density
5 (05/09)Thein-situwetdensityofacompactedmixtureshallbemeasuredusingacalibratednucleardensitygaugeinaccordancewithBS1924-2andthefollowingsub-Clauses,exceptthateachtestshallconsistofatleast3measurementsat120degreestoeachotherusingthesamesourcerodholeandthedensitytakenastheaverageofthehigher2results.
6 (05/09)Theoperation,warming-upperiodifany,andstandardisationofthegaugeshallbecarriedoutincompliancewiththemanufacturer’srecommendations.ThegaugeshallbecalibratedinaccordancewithBS1924immediatelypriortotheconstructionofthedemonstrationareaandatleastonceevery28daysthereafter.
7 (05/09)Thegaugeshallbeusedinthedirecttransmissionmodeofoperationwiththesourcerodloweredtowithin25mmofthebottomsurfaceofthelayer.Thein-situwetdensityshallbedeterminedwithintwohoursofcompletingcompaction.
8 (05/09)Thein-situwetdensityofasubbaselayershallbetakenastheaveragevalueoffivedeterminationsequallyspacedalongalinethatbisectseach1000m2orpartthereoflaideachday.Thefirstandfifthpositionsshallbelocated300mmfromtheedgesofthelaidarea,orotherpositionsagreedbytheOverseeingOrganisation.
9 (05/09)Forasubbaselayer,theaveragein-situwetdensityoftheareaspecifiedinsub-Clause870.8shallbenotlessthan95%oftheaveragewetdensityofthetestspecimenstakentodeterminethelaboratorymechanicalperformanceofthesamearea.
10 (05/09)Forabaselayer,theaveragein-situwetdensityoftheareaspecifiedinsub-Clause870.8shallbenotlessthan95%ofthewetdensityoftheHBMatitsoptimummoisturecontent,measuredusingthevibratinghammermethoddetailedinBS13286-4.Theresultofeachsingledeterminationofin-situwetdensityshallbenotlessthan92%ofthewetdensityoftheHBMatitsoptimummoisturecontent.
(05/09)Laboratory Mechanical Performance
11 (05/09)AbulksampleofHBMshallbetakenfromeachofthelocationsinsub-Clause870.8,afterthein-situwetdensityhasbeendetermined.Testspecimensusedtodeterminelaboratorymechanicalperformanceshallbemadeusingvibratoryhammercompaction,inaccordancewithBSEN13286-51.Wherecubesareusedforthedeterminationofcompressivestrength,thespecimensshallbe150mmsize,unlessagreedotherwisebytheOverseeingOrganisation.
Volume1 Series800SpecificationforHighwayWorks RoadPavements-Unbound,CementandOtherHydraulicallyBoundMixtures
TABLE 8/14:(05/09)Requirements for Testing, Control and Checking of HBM
Test/control/check Test frequency Test referenceWatercontentofaggregateorsoilsourcesonsite
3per1000m2 BS1924-1,Clause7.1
Gradingofaggregateorsoilsourcesonsite
1per1000m2 Aggregates:EN1097-5Soils:BS1924-1,Clause7.1
Plasticityofaggregateorsoilsourcesonsite
1per1000m2 BS1924-1,Clause7.3
Constituentssourcedoff-site Aggregates-ResultsofroutinecontroltestsfromthefactoryproductioncontrolsystemrequiredbyBSEN13242,AnnexCtobeprovidedweekly.Cement-Certificatestobeprovidedmonthlyforeachcementtype,inaccordancewithEN197-1,NationalAnnexNB.Slag-CertificatestobeprovidedweeklytoconfirmthedeclaredvaluesrequiredbyBSEN14227-2,Clause5.Flyash-CertificatestobeprovidedweeklytoconfirmcompliancewiththerequirementsofBSEN14227-4.Otherconstituents-certificatestobeprovidedweeklytoconfirmcompliancewiththespecificationagreedaspartofthefactoryproductioncontrolsystemforthemixture.
-
Batchingrecordsfor‘mix-in-plant’methodofconstructionusingbatchingbymass
Continuouslyusingtheautomatedsurveillanceanddatacollectionsystem
-
Batchingrecordsfor‘mix-in-plant’methodofconstructionusingbatchingbyvolumeandmix-in-place
Dispensingaccuracyshallbeverifiedbyreconciliationbetweenconstituentdeliveriesandtheareaanddepthofcompletedlayerforeach5000m2ofwork,orpartthereof,duringeachday’soperation
-
Spreadchecksfor‘mix-in-place’methodofconstructionateachstageofthemixingprocess(sub-Clause870.3)
1determinationper1000m2butnotlessthan4perday -
Mixturegrading,includingbinder 1per1000m2butnotlessthan3perday BSEN933-1Watercontentatfinalcompaction 1per1000m2butnotlessthan3perday BS1924-2,
Clause1.3MCVatmixingandfinalcompactionand,inthecaseofcohesivemixtures,duringthemellowingperiod
3per1000m2butnotlessthan4perday BSEN13286-46
Pulverization(cohesivemixturesonly) 2per1000m2butnotlessthan4perday BSEN13286-48Depthofmixingfor‘mix-in-place’methodofconstructionateachstageofthemixingprocess(sub-Clause870.4)
5per1000m2butnotlessthan4perday -
In-situwetdensity 5per1000m2orpartthereoflaideachday(measuredatthelocationsdetailedinsub-Clause870.8)
Sub-Clause870.5
Laboratorymechanicalperformance 5per1000m2orpartthereoflaideachday(withtestspecimenspreparedfromabulksampletakenfromeachofthelocationsdetailedinsub-Clause870.8)
AsrequiredbyTable8/15
Strengthafterimmersioninwater Laboratorymixturedesignprocedure AsrequiredbyClause880
Amendment-November2009 22
Volume1 Series800SpecificationforHighwayWorks RoadPavements-Unbound,CementandOtherHydraulicallyBoundMixtures
Table 8/15:(05/09)Laboratory Mechanical Performance Testing Requirements for HBM
Clause Mixture Curing regime Curing temperature
Test method Age at test
821,822&823GBGMA,
CBGMBandCBGMC
RegimeAfrom,BSEN14227-1,
AnnexC20°C
RC-BSEN13286-41
28days-orotherageagreedbytheOverseeingOrganisation(seeNote)
830,831,832&835
SBM,HRBBMandFABM,
(exceptFABM5)BSEN13286-51 40°C
834
FABM5treatedwithlime BSEN13286-51 40°C
Rit-BSEN13286-42FABM5treated
withcement BSEN13286-51 20°C
840SC
RegimeA1fromBSEN14227-10,
AnnexB20°C Ec-
BSEN13286-43SS&SFA BSEN13286-51 40°C
NOTE:
Forsitecontrolpurposed,HBMmaybeassessedonthebasisof7daysstrength(orotheragreedage)wheretheContractorsorequests,providedthatarobustcorrelationisestablishedbetween7daysand28daysstrengthusingrepresentativesamplesoftheaggregatesandbinderusedintheworks.
Amendment-November2009 23
12 (05/09)Complianceoftheareaspecifiedinsub-Clause870.8shallbeassessedusingtheresultsfortestspecimensthatarecuredandtestedinaccordancewithTable8/15usingeithercompressionorindirecttensiletestingasappropriatetotheclassofmechanicalperformancespecifiedinAppendix7/1.Assessmentshallbemadeusingthefollowingcriteria:
(i)Compressivestrength:
TherequirementspecifiedinAppendix7/1shallbedeemedtobesatisfiediftheaveragecompressivestrengthofthegroupofspecimensinTable8/14isequaltoorgreaterthantheminimumforthespecifiedRcclassandnoindividualtestresultislessthan67%oftheminimumstrengthrequirementfortheRcclass.(ii)Indirecttensilestrength:
TherequirementspecifiedinAppendix7/1shallbedeemedtobesatisfiediftheaverageindirecttensilestrengthofthegroupofspecimensinTable8/14isequaltoorgreaterthantheminimumrequirementandnoindividualresultislessthan67%oftheminimumrequirementappropriatetotheEvaluedeterminedduringthelaboratorymixturedesignprocedurespecifiedinClause880.
Forthepurposesofthisspecification,anyreferenceto‘characteristicstrength’inBSEN14227-1shallbesupersededbytherequirementsofthissub-Clause.
871 (05/09) Determination of the Coefficient of Linear Thermal Expansion
Scope
1 (05/09)ThetestmethoddescribedinthisClauseshallbeusedtodeterminethecoefficientoflinearthermalexpansionofHBMwithinthenormalrangeoftemperatureforpavementlayers.Thetestmethodshallbecarriedoutusinghardenedspecimens.
Apparatus
2 (05/09)Thefollowingapparatusshallbeused:
(i) Awaterbathwithsufficientcapacitytoaccommodatethreetestspecimensandcapableofmaintainingpredeterminedtemperaturesbetween15ºCand60ºC.
(ii) Adevicecapableofmeasuringlineardimensionsofnotlessthan275mmtoanaccuracyof±0.002mm,withaknowntemperaturecorrectionfactor.
(iii) Vibratinghammercompactionapparatuscapableofproducing150mmdiametercylindricaltestspecimens,inaccordancewithBSEN13286-51.Theapparatusshallbesuitablymodifiedtomanufacture300mmlongtestspecimens.
Volume1 Series800SpecificationforHighwayWorks RoadPavements-Unbound,CementandOtherHydraulicallyBoundMixtures
Test procedure
3 (05/09)Thefollowingtestprocedureshallbefollowed:
(i) Compactthree150mmdiametertestspecimens,300mminlength,inaccordancewithBSEN13286-51butusingsixlayers,eachwithanominaldepthof50mm.
(ii) Markeachspecimenwith3pairsofpermanentreferencepoints,alignedlongitudinally.Oneofeachpairshallbeatoppositeendsofthespecimen.Eachpairshallbelocatedat120ºaroundthecircumferenceofthespecimens,alignedparalleltotheaxis,andnotmorethan30mmfromeachendofthespecimen.
(iii) CurethespecimensusingtheprocedurespecifiedforthedeterminationofmechanicallaboratoryperformanceinTable8/15.
(iv) Saturatethetestspecimens,eitheratatmosphericpressureorundervacuum,untiltheincreaseinthesurfacedriedmassofeachspecimen,determinedusingtworeadingstakenatleast24hoursapart,islessthan1%.
(v) Immersethespecimensinthewaterbathataconstanttemperature(T1),maintainedtoanaccuracyof±2ºC,for24±2hours.Thenmeasurethelength(L1)ofeachtestspecimenatthelocationsdefinedbythethreepairsofreferencepoints.Repeatthemeasurementoflengthevery24hours,untilthechangeinlengthbetweensuccessivemeasurementsislessthan0.004mm.
(vi) Raisethetemperatureofthewaterbathbyatleast30ºCandrecordthetemperature(T2).T2shallnotexceed55ºC.MaintainthetemperatureatT2±2ºCfor24±2hoursandmeasurethelength(L2)usingtheprocedurein(v).
(vii) Lowerthetemperatureofthewaterbathbyatleast30ºCandrecordthetemperature(T3).MaintainthetemperatureatT3±2ºCfor24±2hoursandmeasurethefinallength(L3)usingtheprocedurein(v).
Amendment-November2009 24
Calculations
4 (05/09)CalculatetheCoefficientofLinearThermalExpansion(CLE)asfollows:
(i) Foreachpairofreferencepointsfortheheatingsequencecalculate:
CLE´=(L2–L1)/(T2–T1),giving9resultsintotal.
(ii) RejectthehighestandlowestresultsandrecordthemeanvalueofCLE´fortheremaining7results.
(iii) Foreachpairofreferencepointsforthecoolingsequencecalculate:
CLE´´=(L2–L3)/(T2–T3),giving9resultsintotal.
(iv) RejectthehighestandlowestresultsandrecordthemeanvalueofCLE´´fortheremaining7results.
(v) Calculate:
CLE=0.5((MeanvalueofCLE´)+(MeanvalueofCLE´´)).
(vi) CheckthatthemeanvaluesofCLE´andCLE´´lieintherange0.95CLEto1.05CLE.Ifthemeanvalueslieoutsidethisrange,repeattheprocedureinsub-Clause871.3.
Reporting of Results
5 (05/09)ReportthevalueofCLEusingunitsofm.10-6/ºC,expressedtothenearestwholenumber.
872 to 879 (05/09) Not used
880 (05/09) Laboratory Mixture Design Procedure
1 (05/09)Priortothecommencementoftheworkoranychangeinmixtureconstituents,theContractorshalldeterminethetargetproportionsoftheconstituents,includingwater,forthespecifiedHBM,basedonthemixturedesignproceduredescribedinthisClause.
2 (05/09)ThemixturedesignprocedureshalldeterminethepropertiesoftheHBMataminimumof3valuesofbindercontents,andaminimumof2valuesofwatercontentforeachvalueofbindercontent.
Volume1 Series800SpecificationforHighwayWorks RoadPavements-Unbound,CementandOtherHydraulicallyBoundMixtures
Immediate Stability
3 (05/09)Whenrequired,themixturedesignprocedureshallincludethedeterminationoftheimmediatebearingindex(IBI)attheselecteddesignwaterandbindercontent,measuredinaccordancewithBSEN13286-47.TheIBIvalueshallbetakenastheaveragevalueforasetof3testspecimens.
(05/09) Resistance to Water – Strength After Immersion
4 (05/09)Thestrengthafterimmersioninwatershallbeassessedbycomparingtheaveragestrengthandconditionof:
(i) 3specimensinitiallycuredinasealedconditionfor14daysatthetesttemperature;andthenremovedfromtheirmouldsandimmersedinaeratedwaterfor14daysatthesametesttemperature.
(ii) 3specimenscuredinsealedconditionfor28daysatthesametesttemperature.
Theimmersedspecimensshallbeunconfinedandhavewaterincontactwithallsurfaces.Oncompletionoftheimmersionstageofthetestthespecimensshallshownosignsofcrackingorswelling.
5 (05/09)Formixturescontaininglessthan3%bydrymassofthemixtureofcement,thetesttemperatureshallbe(40±2)ºC.Formixturescontaining3%ormorecement,thetesttemperatureshallbe(20±2)ºC.
Resistance to Frost Heave
6 (05/09)HBMshallbedeemedresistanttofrostheavewherethecompressivestrengthclassisC3/4orgreaterorRitisgreaterthan0.25MPa,whencuredinaccordancewithTable8/15.
Amendment-November2009 25F