8 The Esplanade – L Tower & 1 The Esplanade – Backstage
April 14 – 21, 2012
Detailed daily construction schedules are available at:
o h t t p : / / l t o w e r c o n s t r u c t i o n i n f o . c o m / o Updates are also available via Twitter from “ltowerinfo” or email us at
ltowerconstructioninfo@enconsulting.ca
L Tower – highlights: Saturday, April 14
o L Tower crane mast extension starting at 9:00 am
Tuesday, April 17 o Concrete slab pour, level 36, starting at 10:00
am, levels 33 – 34. Wednesday, April 18
o A wall and column concrete pour, levels 36 – 37 starting 1:00 pm
Thursday, April 19 o A wall and column concrete pour, levels 36 –
37, starting 1:00 pm Saturday, April 21
o L Tower, further crane mast extension starting at 9:00 am
Backstage – highlights: Daily, April 16 - 20
o Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons. o There will be two (2) concrete trucks
doing four rounds each (8 in total) in and out of the site.
o Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.