KANE COUNTY DIVISION OF TRANSPORTATION
STEARNS ROAD WETLAND MITIGATION SITE
SECTION NO.06-00214-03-BR
PRE-BID MEETING
PROJECT LOCATION
• NEW ALIGNMENT WEST OF IL ROUTE 25 AND EAST OF THE FOX RIVER
• SOUTH OF CNIC TRACKS AND NORTH OF MIDWEST GROUNDCOVERS
• ST. CHARLES TOWNSHIP, KANE COUNTY• THIS PROJECT IS LOCATED IN A SENSITIVE
ENVIRONMENTAL AREA
PROJECT LOCATION
PROJECTLOCATION
PROJECT DESCRIPTION
• 11.7 ACRES OF WETLAND MITIGATION• 12.8 ACRES OF COMPENSATORY
FLOODPLAIN STORAGE• 1,500 FT OF STREAMBANK
RESTORATION• 3,417 FT (0.65 MI) OF NEW ALIGNMENT• ROADWAY EMBANKMENT• THE PROJECT INCLUDES SPECIAL
WASTE REMOVAL
STEARNS ROAD DIRECT IMPACT MITIGATION SITE
PROJECT DESCRIPTION
• THIS IS A WETLAND MITIGATION PROJECT FIRST AND FOREMOST.
• THIS PROJECT ALSO INCLUDES:– ROADWAY EMBANKMENT– COMPENSATORY FLOODPLAIN STORAGE– TEMPORARY AND PERMANENT
STABILIZATION– SPECIFC TREE PROTECTION AREAS
CONSTRUCTION ENGINEERINGKANE COUNTY DIVISION OF TRANSPORTATION• COUNTY ENGINEER CARL SCHOEDEL• PROJECT MANAGER MARK BAGHERPOUR• CONSTRUCTION MGR DAVE BOESCH
CONSULTANT - CHRISTOPHER BURKE ENGINEERING• ENGINEER OF RECORD MIKE KERR, CBBEL• CONSTRUCTION DAN CROSSON, CBBEL• ENVIRONMENTAL PAT KELSEY, CBBEWL
PHASING• PHASE 1 – ALL WORK, EXCEPT FOR LANDSCAPING
AND TEMPORARY SESC SHALL BE COMPLETED BY OCT 15, 2007
• PHASE 2 – ALL SEEDING SHALL BE COMPLETED BY DECEMBER 1, 2007
• PHASE 3 – ALL PLANTINGS SHALL BE COMPLETED BY JUNE 1, 2008
• PHASE 4 -- ALL CONTRACT WORK INCLUDING PUNCH LIST, SHALL BE COMPLETED BY OCTOBER 15, 2008
FAILURE TO COMPLETELIQUIDATED DAMAGES
• PHASE 1 -- $1,100.00/DAY
• PHASE 2 -- $ 550.00/DAY
• PHASE 3 -- $ 725.00/DAY
• PHASE 4 -- $1,300.00/DAY
404 PERMIT COMPLIANCE
• USACE SECTION 404 INCLUDING SECTION 401 WATER QUALITY CERTIFICATION
• KANE-DUPAGE SOIL & WATER CONSERVATION DISTRICT OVERSIGHT
• KANE COUNTY STORMWATER ORDINANCE SESC -- NPDES PHASE II
404 PERMIT COMPLIANCE• CONTRACTOR SHALL MEET ALL
REQUIREMENTS OF 404 PERMIT INCLUDING SOIL EROSION AND SEDIMENT CONTROL AND PROTECTION OF HIGH QUALITY AQAUTIC RESOURCES
• NO DIRECT DISCHARGES TO THE EAST BRANCH OR NORTH ARM OF BREWSTER CREEK
• NO DIRECT DISCHARGES TO THE FOX RIVER
KEY SPECIAL PROVISIONS
• DEBRIS REMOVAL– BREWSTER CREEK CONCRETE REMOVAL
• SELECTIVE CLEARING– LIMITED ACCESS TO SOME AREAS
• SEEDING, CLASS 4 AND 5 MODIFIED– 8 SEED TYPES FOR CLASS 4– 8 SEED TYPES FOR CLASS 5– 4 INTERSEEDING SEED TYPES– LOCAL GENOTYPE – 150 MI RADIUS
KEY SPECIAL PROVISIONS
• PERENNIAL PLANTS– WETLAND EMERGENT TYPE– WETLAND TYPE
• PERENNIAL PLANTS– IDOT WILL TAG TREES & SHRUBS– IDOT & RE WILL INSPECT ALL PLANTS ON
ARRIVAL TO THE JOBSITE.
KEY SPECIAL PROVISIONS
• COORDINATION BETWEEN CONTRACTORS
• MANAGEMENT OF SOIL EROSION AND SEDIMENT CONTROL
OTHER CONSIDERATIONS
• ELECTRIC SERVICE TO MIDWEST GROUNCOVERS SHALL BE UNINTERUPPTED
• CONTRACTOR AND RESIDENT ENGINEER TO WORK WITH MIDWEST GROUNDCOVERS ON TREE REMOVAL NEAR PROPERTY LINE
• USACE TO MAKE REGULAR SITE VISITS ALONG WITH KDSWCD