Post on 14-Aug-2020
Integration of Electric Vehicles in Extreme Suburban Grids with the Support of Extended Functionality of PV Storage Systems Jonas Wussow, E-Mobility Power System Integration Symposium, 14.10.2019, Dublin
14.10.2019 | Jonas Wussow | Extended Functionality of PV Storage Systems | Page 2
Agenda
Introduction Challenges in Residentials Areas Impact of Charging Processes PV-Storage Systems as Approach Advanced Reactive Power Supply Multiple-Use of Storage Losses Conclusion
14.10.2019 | Jonas Wussow | Extended Functionality of PV Storage Systems | Page 3
Introduction
2040 55 % new vehicle registrations 550 million EV
(33 % of global fleet)
Change in „refuel“ Charging at home Wallbox with charging power
up to 11/22 kW Hotspots with high number
of EV possible
Ramp-up of Electromobility
14.10.2019 | Jonas Wussow | Extended Functionality of PV Storage Systems | Page 4
Agenda
Introduction Challenges in Residentials Areas Impact of Charging Processes PV-Storage Systems as Approach Advanced Reactive Power Supply Multiple-Use of Storage Losses Conclusion
14.10.2019 | Jonas Wussow | Extended Functionality of PV Storage Systems | Page 5
Challenges in Residentials Areas Changes at Household Sector
0:00 4:00 8:00 12:00 16:00 20:00 0:00
Uhrzeit
-15
-10
-5
0
5
10
15
Leis
tung
in k
W
Haushalt Elektrofahrzeug PV-Anlagen Auslastung Netzanschlusspunkt
Conventional Household
Consumer
Producer
Storage
Household Electric Vehicle PV System Load on Grid Connection Point
14.10.2019 | Jonas Wussow | Extended Functionality of PV Storage Systems | Page 6
Challenges in Residentials Areas Investigated Grid and Scenarios
MV
/LV
(630 kVA)
MV grid
Remaining grid 75 households in 4 strings and 1 single household
Critical S
tring
~ ~
1 2
69
EV-Modell Realistic Charging Behaviour No Provision of Reactive Power by EV No Charging Delaying or Power Reduction
Further conditions Synthetic Household Profiles Voltage at Slack Bus: 1, 1.02 and 1.04 p.u. Consideration of Voltage Drop in MV grid
14.10.2019 | Jonas Wussow | Extended Functionality of PV Storage Systems | Page 7
Agenda
Introduction Challenges in Residentials Areas Impact of Charging Processes PV-Storage Systems as Approach Advanced Reactive Power Supply Multiple-Use of Storage Losses Conclusion
14.10.2019 | Jonas Wussow | Extended Functionality of PV Storage Systems | Page 8
Impact of Charging Processes 26 EVs without Measures possible
12:00 14:00 16:00 18:00 20:00 22:00 24:00
Hour of Day
0.84
0.86
0.88
0.9
0.92
0.94
0.96
0.98
1
Vol
tage
in p
.u.
Voltage at slack bus
in p.u.
Minimum voltage at the end of the critical string in p.u.
Number of simultaneous charging processes*
0 4 8 1.00 0.910 0.876 0.852 1.02 0.924 0.900 0.882 1.04 0.952 0.922 0.906
*18 additional simultaneous charging processes in remaining grid
Limits according to EN 50160 are not exceeded
Without EV
With EV
14.10.2019 | Jonas Wussow | Extended Functionality of PV Storage Systems | Page 9
Agenda
Introduction Challenges in Residentials Areas Impact of Charging Processes PV-Storage Systems as Approach Advanced Reactive Power Supply Multiple-Use of Storage Losses Conclusion
14.10.2019 | Jonas Wussow | Extended Functionality of PV Storage Systems | Page 10
PV-Storage Systems as Approach Many Points in Time without Using the Storage
Power
Reactive Power
Capacity assumed to be 8 kWh
Non-Use especially in winter and on bad weather days Use of reactive power so far very low Charging: cos φ=1, Discharging: cos φ=0.9/0.95
14.10.2019 | Jonas Wussow | Extended Functionality of PV Storage Systems | Page 11
Agenda
Introduction Challenges in Residentials Areas Impact of Charging Processes PV-Storage Systems as Approach Advanced Reactive Power Supply Multiple-Use of Storage Losses Conclusion
14.10.2019 | Jonas Wussow | Extended Functionality of PV Storage Systems | Page 12
Advanced Reactive Power Supply Further EV possible at STATCOM
𝑈 in p.u.
0.93 0.97
1.03 1.07
𝑄
𝑄max
-𝑄max
𝑃
𝑄
𝑆
cos 𝜑 = 0,9/0,95
𝑃n
-𝑃n
𝑃
𝑄
𝑆𝑃n
-𝑃n
Q(V)-Characteristic
Provision of Reactive Power
according to demand
Operating Points Q(V) control
No Improvements:
P = 0 => Q = 0 No further EV
Operating Points STATCOM Mode
Reactive Power can always be
provided (Phase Shifter)
26 EV => 38 EV
14.10.2019 | Jonas Wussow | Extended Functionality of PV Storage Systems | Page 13
Agenda
Introduction Challenges in Residentials Areas Impact of Charging Processes PV-Storage Systems as Approach Advanced Reactive Power Supply Multiple-Use of Storage Losses Conclusion
14.10.2019 | Jonas Wussow | Extended Functionality of PV Storage Systems | Page 14
Multiple-Use of Storage Charging Storage from Grid enables a high Number of EV
12:00 14:00 16:00 18:00 20:00 22:00 24:00
Hour of Day
0.84
0.86
0.88
0.9
0.92
0.94
0.96
0.98
1
Vol
tage
in p
.u.
Normal Operation Multiple-Use
Green-dotted: Eight EV Blue: 16 EV (both Critical String) A total of 65 EV possible in the Grid
14.10.2019 | Jonas Wussow | Extended Functionality of PV Storage Systems | Page 15
Agenda
Introduction Challenges in Residentials Areas Impact of Charging Processes PV-Storage Systems as Approach Advanced Reactive Power Supply Multiple-Use of Storage Losses Conclusion
14.10.2019 | Jonas Wussow | Extended Functionality of PV Storage Systems | Page 16
Losses Incentives necessary for Storage Charging from the Grid
92 % 92 %
85 %
STATCOM 0.22 kWh (Charging Process at end of critical string) Multiple-Use 0.05 kWh (Charging Process at end of critical string) (Provision Reactive Power)
1 kWh 1.18 kWh
14.10.2019 | Jonas Wussow | Extended Functionality of PV Storage Systems | Page 17
Agenda
Introduction Challenges in Residentials Areas Impact of Charging Processes PV-Storage Systems as Approach Advanced Reactive Power Supply Multiple-Use of Storage Losses Conclusion
14.10.2019 | Jonas Wussow | Extended Functionality of PV Storage Systems | Page 18
Conclusion
Without Measures STATCOM Mode STATCOM Mode
and Multiple-Use
0
20
40
60
80
100
Sim
ulta
neou
s ch
argi
ng p
roce
sses
+48 %
+150 %
Extreme Suburban Grid was investigated Penetration of 18 % possible without Measures Extended Functionality of PV Storage Systems are necessary Penetration can be increased
o STATCOM Mode: 26 % o STATCOM Mode and
Multiple-Use: 45 % Losses for Provision of Reactive Power
very low Incentives are necessary for Multiple-Use Grid expansion can be prevented
Thank you for your attention!
Jonas Wussow, TU Braunschweig - elenia Phone: +49 531 / 391 – 7707, Mail: J.Wussow@TU-BS.de