Integrating the Project Life Cycle with Process Groups

Project Management Method

Mapping the PMBOK® Guide

to a Project Life Cycle

www.sukad.com | enter the name of the presentation or program

The Project Life Cycle

First: there is the project life cycle

• From idea to closure … or• From which ever point the organization

defines as start and end points

Project Life Cycle

Second: the project life cycle is subdivided into phases (stages)

IdeaProject Charter Handover

Final Accept

Intermediate Phases

Pre-Project

Final

Phase 1 Phase 2 Phase N

Project Life Cycle

Study

Start-up

This is the project life cycle from the SUKAD CAM2P™ Model

(the standard model with phases and stages)

The SUKAD CAM2P™ Model (Full View)

The PMBOK® Guide

There are five process groups

Integration

Scope

Time

Cost

Quality

HR

Communication

Risk

Procurement

Stakeholders

There are ten knowledge areas

PMBOK Process Groups, Processes, & Knowledge Areas

Knowledge AreasProject Management Process Groups

Initiating Process Group

Planning Process Group

Executing Process Group

Monitoring & Controlling Process Group

Closing Process Group

Project Integration Management

• Develop Project Charter • Develop Project Management Plan

• Direct and Manage Project Work

• Monitor and Control Project Work

• Perform Integrated Change Control

• Close Project or Phase

Project Scope Management

• Plan Scope Management• Collect Requirements • Define Scope• Create WBS

• Validate Scope• Control Scope

Project Time Management

• Plan Schedule Management• Define Activities• Sequence Activities• Estimate Activity Resources• Estimate Activity Durations• Develop Schedule

• Control Schedule

Project Cost Management

• Plan Cost Management• Estimate Costs• Determine Budget

• Control Costs

Project Quality Management

• Plan Quality Management • Perform Quality Assurance • Control Quality

Project Human Resource Management

• Plan Human Resource Management

• Acquire Project Team• Develop Project Team• Manage Project Team

Project Communications Management

• Plan Communications Management

• Manage Communications • Control Communications

Project Risk Management

• Plan Risk Management • Identify Risks• Perform Qualitative Risk

Analysis• Perform Quantitative Risk

Analysis• Plan Risk Responses

• Control Risks

Project Procurement Management

• Plan Procurement Management

• Conduct Procurements • Control Procurements • Close Procurements

Project Stakeholder Management

• Identify Stakeholders • Plan Stakeholder Management • Manage Stakeholder Engagement

• Control Stakeholder Engagement

Initiate Plan Execute Monitor & Control Close

Integration 1 1 1 2 1

Scope 4 2

Time 6 1

Cost 3 1

Quality 1 1 1

Human Resource 1 3

Communication 1 1 1

Risk 5 1

Procurement 1 1 1 1

Stakeholders 1 1 1 1

Process Groups Repeating

Notice the image from PMBOK

Process groups repeat in every phase

All together

Interactions of process groups and knowledge areas

to project life cycle and stages

Project Life Cycle

I P E MC C

I

S

T

C

Q

HR

C

R

P

S

Phase 1 Phase 2 Phase 3 Phase N

PMBOK Guide Process Groups Repeating

I P E MC C

I

S

T

C

Q

HR

C

R

P

S

Processes from the knowledge areas repeat as well

PMBOK Guide Knowledge Areas

and Process Groups

I P E MC C

I

S

T

C

Q

HR

C

R

P

S

PMBOK Guide Knowledge Areas

and Process Groups

PMBOK Guide Knowledge Areas

and Process Groups

I P E MC C

I

S

T

C

Q

HR

C

R

P

S

PMBOK Guide Knowledge Areas

and Process Groups

Initiate Plan Execute Monitor & Control Close

Integration

Scope

Time

Cost

Quality

Human Resource

Communication

Risk

Procurement

Stakeholders

However, for small projects

Project Life Cycle

Phase 1 Phase 2 Phase 3 Phase N

Initiate Plan Execute Close

Another Way of Looking at this integration

SUKAD CAM2P™ Project Life Span

Planning process group apply to the whole project

Executing process group apply to the whole project

Monitoring and controlling process group apply to the whole project

All process groups apply to a typical stage or phase as well

Project & Stage Perspective

SUKAD Information

www.sukad.com | enter the name of the presentation or program 29

SUKAD business divisions

www.sukad.com | enter the name of the presentation or program 30

http://learning.sukad.com

http://solutions.sukad.com

http://technology.sukad.com

http://multimedia.sukad.com

SUKAD knowledge sharing sites

www.sukad.com | enter the name of the presentation or program 31

http://sukadway.sukad.com

http://knowledge.sukad.com

http://blog.sukad.com

http://blog-ar.sukad.com

SUKAD social media sites

www.sukad.com | enter the name of the presentation or program 32

www.sukad.com | enter the name of the presentation or program 33

Thank You !