Post on 07-Jul-2018
Integrated Planning and the Last Planner
Adam Frandson, UC Berkeley PhD student, NTNU researcher working at Total
1
Overview
• Background
o Integrated Planning: structure and focus
o Last Planner system: structure and focus
• Last Planner complements to Integrated Planning
o Screening, shielding, metrics and learning
2
Integrated Planning
• Developed to improve and support Integrated Operations
• Focus is on prioritizing offshore activities through coordinating and collaborating with the different departments
3
Integrated Planning - structure
4
Operations and
maintenance
Drilling
Project team
Logistics
Geosciences
External
suppliers
Contracts and
Procurement
Integrated Planning – structure example
5
Strategic
Daily site execution
Operational Front- End Loading
20 week site execution Look ahead
8 week site execution Look ahead
Master
2 week site execution Look ahead
Last Planner system
6
Information
Project Objective
Planning the work SHOULD
CAN Last Planner Process
WILL
Resources Production
DID
Ballard 2000, PHD Dissertation
Last Planner system Structure
7
Master
schedule
Phase
schedule
Lookahead
(6-12
weeks)
Commitment
meeting
Daily check-
in
Should
Will
Can
Did
LP complement #1 - Screening
• The lookahead schedule is not simply a horizon of activities ‘n weeks’ out
• Assess the activities and only put them on the lookahead if they can completed on schedule with reasonable certainty
8
LP complement #2 - Shielding
• Allow the Last Planner to only commit to tasks that they know can be completed
• If you can't say no, then you can't make a promise.
12
Who is the Last Planner?
13
Master
schedule
Phase
schedule
Lookahead
(6-12
weeks)
Commitment
meeting
Daily check-
in
Should
Will
Can
Did
Last Planner complement #3 - Metrics
1. Planned percent complete – A measure of plan attainment
2. Tasks anticipated – A measure of plan predictability
3. Tasks made ready – A measure for making tasks ready
14
Metrics - PPC
15
Area A Activities Complete Not Complete Reason
Install Scaffolding X
Painting X
Fire sprinkler pretest X
Fire spinkler Inspection X Material
Painting inspection X
Remove scaffolding X Space not available
Of the 6 tasks, 4 were completed. PPC = 66%
Tasks Made Ready - Example
17
Of the 4 activities on the 9/24 lookahead for week 3, 2 were made ready.
TMR3-2 = 2/4 = 50%
9/24
10/1
Tasks Anticipated- Example
18
Of the 3 activities on the 10/1 lookahead for week 2, 2 were anticipated.
TA3-2 = 2/3 = 66%
9/24
10/1
Complement #4 - Continuous Learning in the Last Planner
• Follow the metrics and identify root causes
• Use Toyota’s 5 Whys to get to the root cause of problems
19
Conclusion
• From observation Integrated Planning has a strong focus on what activities should be done.
• The Last Planner system has a strong focus on executing what should be done.
• The Last Planner system can complement Integrated Planning via screening, shielding, metrics, and learning.
• The Last Planner system is a system, it is not a tool or piece of software, but a system with principles and rules.
22
Acknowledgements
• Special thanks to Jeroen Schils, Rune Teigland, and Karl – Ernst Karlsen from Total
• A very special thanks to Bjørn Asbjørnslett from NTNU for the collaboration, advising, and getting me into Norway
• Research advisors Iris Tommelein, Glenn Ballard, and Phil Kaminsky from UC Berkeley
• Lone Ramstad and Even Holte from Marintek
23