In-house Repair of Hydro-generator Stator Winding...2017/05/17  · US Army Corps of Engineers...

Post on 05-Aug-2020

1 views 0 download

Transcript of In-house Repair of Hydro-generator Stator Winding...2017/05/17  · US Army Corps of Engineers...

US Army Corps of Engineers

BUILDING STRONG®

In-house Repair of Hydro-generator Stator Winding

May 17, 2017 by Scott Cotner, P.E. Senior Electrical Engineer Hydroelectric Design Center

BUILDING STRONG® PORTLAND DISTRICT 2

John Day Lock and Dam Multi-purpose facility on Columbia River on

Washington-Oregon border Powerhouse has sixteen 164MVA generators

BUILDING STRONG® PORTLAND DISTRICT 3

Fault and Damage

Placing Unit in-line, generator at rated speed and voltage

LL Fault occurred: ► >13kA in A and B

phase ► Tripped by multiple

elements of DMFR relay

BUILDING STRONG® PORTLAND DISTRICT 4

Repair Decisions

Contract or in-house forces? ► Contracting difficulty encountered ► In-house with technical direction

With rotor in or out? ► In – remove 2-3 poles

• shorter duration, cramped workspace

► Out – disassemble machine • much longer duration, easier access

BUILDING STRONG® PORTLAND DISTRICT 5

Materials and Tooling On-hand at project

► Spare top and bottom stator bars, insulating caps, polyester roving, spare pole collars

On-hand at nearby projects ► Slot closing wedges, fillers, polyester felt, field coil

lifting jig ► Test equipment, induction brazing equipment

To be ordered ► Mica tape, insulating, semiconducting, and weeping

epoxies, brazing filler metal, copper for pole group connections

BUILDING STRONG® PORTLAND DISTRICT 6

Lashing and Cap Removal

BUILDING STRONG® PORTLAND DISTRICT 7

Bar Removal

BUILDING STRONG® PORTLAND DISTRICT 8

Slot Prep/Bar Test

BUILDING STRONG® PORTLAND DISTRICT 9

Bar Insertion

BUILDING STRONG® PORTLAND DISTRICT 10

Slot Wedging

BUILDING STRONG® PORTLAND DISTRICT 11

Brazing Mock-ups

BUILDING STRONG® PORTLAND DISTRICT 12

Lashing Bars and Brazing

BUILDING STRONG® PORTLAND DISTRICT 13

Bottom Cap Installation

BUILDING STRONG® PORTLAND DISTRICT 14

Taping Pole Group Jumpers

BUILDING STRONG® PORTLAND DISTRICT 15

Top Cap Installation

BUILDING STRONG® PORTLAND DISTRICT 16

Testing – In-process and Final Overpotential (hipot) spare bars Slot paint resistance to ground Top bar side resistance to ground Ripple spring compression Overpotential (hipot) bars after wedging Resistance of all brazed joints Field winding pole drop Both Rotor and Stator - winding resistance,

insulation resistance/polarization index, final overpotential (ac)

BUILDING STRONG® PORTLAND DISTRICT 17

Lessons Learned

Rotor in or rotor out? ► Out: allowed more work space but much longer

outage ► In: cramped but could pull and push bars against rim

Careful Spare Bar measurements ► Checked width but not depth, spare bars were slightly

shallower than old ones resulting in lots of top filler to wedge slot tightly.

BUILDING STRONG® PORTLAND DISTRICT 18

Lessons Learned (cont’d)

Material orders ► Order early and notify team of supply problems

Technical Direction ► More emphasis on what not to do

• Collateral damage expands repair scope

► Clear descriptions of work • Sketches, photos, and mock-ups help ensure all parties have

clear understanding of work

Crew consistency and craftsmanship

BUILDING STRONG® PORTLAND DISTRICT 19

Questions?

BUILDING STRONG® PORTLAND DISTRICT 20

Cause of Fault

BUILDING STRONG® PORTLAND DISTRICT 21

Field Coil Removal

BUILDING STRONG® PORTLAND DISTRICT 22

Pole Body Insulation

BUILDING STRONG® PORTLAND DISTRICT 23

Re-assembling Coil