Post on 24-Aug-2018
IH TfU,/ HUb/ nf} I{'&lld/I> '; - df {2f :r/13~,ABHIJE="'r
-\Four Laning of Barhi Haza-:ibagh Section NH-33~-----------------------------
RL - Abhijeet Hazaribagh Toll Road Ltd.
~ect Title -:
FOUR L NING OF BARHI HAZARIBAGH SECTIONFROM KM 0.00 to km 40.500 OF NH-33 IN THE STATEOF JHARKHAND ON DESIGN, BUILT, FINANCE,OPERATE AND TRANSFER (DBFOT) TOLL BASISPHASE III PROJECT UNDER NHDP
R-Monthly Progress Rwort [June -20131"
v'"
r-.
""r-...
'"
--,r>.
r--,
r>r">.
r> .-/
r--.
r>.
f'
,.-..
~
r>.
r>.
r=;
r<;
.,..,.--..-r>». J
r>.
0
r=;
, r--.
r>
r>.
r>.
"1'\
r>.
"
Monthly Progress ReportJune-2013
Table of Content
S.No. Description Page No.
1.0 Introduction 1
1.1 Contract Data 1
1.2 Project Details 2
1.2.1 Details of contract provision 2
1.2.2 Scope of work 3
1.3 Organization structure 3~.
2.0 Programme and progress 4
2.1 Milestone 4
2.2 Construction programme 4
2.3 Progress summary 4
2.3.1 Physical and financial progress 4
2.3.2 Rc;::~wcrks 5
2.3.3 Structure works 6
2.4 Mobilization status of concessionaire, EPCcontractor; 7
I
2.5 Plants and equipments at site 7
2.6 Quantity control 7
2.7 Land acquisition status 8
2.8 Pre construction activities 9
2.9 Utility shifting 9
2.10 Others hindrance 9
2.11 Survey works 9
2.12 Construction method statement 10I2.13 I Job mix formula / Mix design 10
2.14 Quality assurance manual and plan 10
2.15 Safety, Health and Environment Manual 10
3.0 Design 10..AbhlJeet Hazanbagh Toll Road Ltd.
I r
r=;r> ./
r=.
"r>:
"""""
,.-.,
"r--
'"
r-.
r-.
---..
Monthly Progress ReportJune-Z013
S.No. Description Page No.
3.1 Design Review 10
3.2 Design change 10
3.3 Change of scope 10
3.4 Details of Non conforming report 11
4.0 Maintenance 12
5.0 Health, Safety, Security, Environment and Accident 12
5.1 Health 12~,
5.2 Safety 12
5.3 Security 12
5.4 Accident 12
6.0 Constraint 12
Annexure
1 Organizatlcn chart of concessionaire lA
2 Organization chart of EPC 1B
3 Strip chart of road works,
2A"
4 Strip chart of structure works 2B &2C
5 List of plant and equipment 3
6 Quality control test 4
7 Weather Report 5
8 Accident Report 6
9 Site Photograph 7
Abhijeet Hazaribagh Toll Road Ltd.
~--------------------------------------~------------------------------------~/
v~
"r--
'\
r>.
'-"
r>
,......"
f'
r>.
r>r=.
,--.,
r--.
r--.
,~
r>.
.-.,
r--.
r<:
r>
'"~
'"r--.
r-.
,,---,
r>.
"'""'
r>:
r-.,
r>.
,......"
'"
r--.,......"
r>.
Monthly Progress ReportJune- 2013
1.0 Introduction
National Highway 33 (NH 33) starts from the junction of NH 2 and NH 31 at Barhi and ends in thejunction of NH 6 at Baharagora in EastSinghbhum district in Jharkhand. The total length of NH 33 is352 km.
The Ranchi- Hazaribagh is key road connecting the coal belt areas of Jharkhand to the NationalHighway No.2 which is a major part of the Golden Quadrilateral linking the metro cities of Delhi andCalcutta
National Highway No.33 is being built on Design, Built, Finance, Operate and Transfer (DBFOT)Tollbasis under NHDP Phase III Project. The present project corridor Barhi- Hazaribagh Section, is a partof NH-33.
The project mainly consists of converting the existing road in to a four lane highway by constructingand maintaining of Barhi- Hazaribagh Section of NH-33. Total length of the road is 41.314. The workincludes
~,,1) Construction of RoadWorks in rigid as well as flexible pavements,
2) Construction of Major bridges, Minor bridges, culverts and all other cross drainage works.
3) Construction of Toll Plaza.
4) Maintenance of existing road until completion of construction.
5) Maintenance of the road for the entire concession period of 24 years.
6) Handing over of the project to NHAI at the end of Concessionperiod.
1.1 Contract Data:
1.1.1 The Authority National Highway Authority of India
Name of Project Director
Address
Mr. Awadhesh Kumar
Project Implementation Unit,National Highways Authority of h'ldiaC-76,Harmu Housing Colony,Near Swami SahajanandChowk, Harmu,Ranchi834012 (Jharkhand)
1.1.2 The Concessionaire M/s Abhijeet Hazaribagh Toll Road Ltd
Address Behind Laxmi Petrol Pump,Nawabganj - Hazaribag - 825301
General Manager (Project) Mr. U.S.P.Singh
Project Cost INR425.66 Cr.
Date of Signing of Concession Agreement si"August -2010
Financial closure due on 27.02.2011/21.04.2011
u" Feb 2012Appointment Date
Construction Period 24 Months from the Appointment date
Concession & Maintenance Period 24 Yearsfrom the Appointment date
1.1.3 EPCContractor Mis Abhijeet Projects Ltd. Nagpur.
1.1.4 Design Consultant of Concessionaire Mis Gifford India Pvt. Ltd., New Delhi
Page 1- 1 Abhijeet Hazaribagh Toll Road Ltd.
~ r=.I
'"
'"
~
-'"'"
'"r>.
""f'
f"
r-r\
rr-.
r-.
~
~
'".~
r>.
f',
~
r--,
~r-.
(\
0
r>.
'"
~
f'
r=.
r<;
,,---..,
"..,
(\
/"'-",
f'
1.1.5 Independent EngineerAddress
Monthly Progress ReportJune- 2013
1.2 Project Details
Project Name
Length of the Project Road
Major Towns En route
Rivers En route
1.2.1 Details of Contract Provision
Widening & Strengthening Length
Bye-pass Length
Carriageway Width
ROW
Major Intersection
Minor Junctions
Service Road Length (Total)
Toll Plaza
RCCRetaining Wall
RETWall Structures
Major Bridge
Minor Bridge
Pipe Culverts
Box/Slab Culverts
Project Facilities
SAI Consulting Engineers Pvt. LtdKashturi Niwas, Devangana ChowkShiv Mandir Road, Korra,Hazaribagh - 825 301 Jharkhand
Four Laning of Barhi Hazaribagh Section from km0.00 to km 40.500 of NH-33 in the State ofJharkhand on Design, Built, Finance, Operate andTransfer (DBFOT) Toll basis under NHDP Phase IIIProject
"4i.314 Km
Barhi, Surajpura, Ithkori More, Ichak more, Bariyath,Bonga,lChak, Nagawa
t·Barhi @ Km 1.035, Kewta @ Km 12.829,Kosma Ghat @ Km 15.409, Shiwaney @ Km 28.993Kunar@ Km 40.700.
30.900Km
10AOOKm
17.50 M
60 M/45 M
5 Nos.
10 Nos.
4.875 Kms Each side
1 Nos.
Nil
Nil
3 Nos
2 Nos
9 Nos
60 Nos
• Toll plazas• Roadside furniture• Street lighting• Pedestrian facilities• Landscaping and tree plantation;
". Rest areas;• Truck lay-bys• Bus-bays and bus shelters• Cattle crossings• Development of site for wayside amenities;• Traffic aid posts;• Medical aid posts;• Vehicle rescue posts;• Telecom system;• Highway traffic management system
Page 1- 2 Abhijeet Hazaribagh TollRoad Ltd.
,..--...
.'-"
r=.
r--
r--.
r>
r---
r>
r'"\r>.
r>.
,-..,
r-..
r-..
-----
rr-:
r>.
,--...,
, r-..
r=-.r-,
r-.,
r>:
r>.
~
r--
r>.
r>.
'"
", r>
r-,
r-..
----.
Monthly Progress ReportJune- 2013
1.2.2 Scope of Work
Sr•., I
Ho•.Description Unit Estimated Total Quantity
1 Clearing & Grubbing Hect. 250
2 Earthwork in Excavation Cum 801000
3 Earthwork in Embankment Cum 1328000
4 Sub-grade with borrow earth Cum 524000
5 GSB layer Cum 287000
6 WMM Cum 214000
7 Kerb Casting Mt. 83000
8 Prime Coat over sub - base Sq.m. 852000
9 Tack Coat Sq.m. 1610000
10 DBM Cum 121000
11 BM (Grading 2) Profile corrective course Cum~.
10000 J
12 Median Filling Cum 70000
13 BC Cum 43000
14 DlC Cum 3000
15 PQC Cum 5000
1.3 Organization Structures:• Concessionaire organization Structures attached as Annexure 1A• EPCContractor Organization Structures attached as Annexure-1B
;
Page 1- 3 Abhijeet Hazaribagh Toll Road Ltd.
Monthly Progress ReportJune- 2013
2.0 Programme and Progress
2.1 Milestones
2.1.1 Project Milestone-IProject Milestone-I shall occur on the date falling on the 202nd (Two Hundred and Second) day Dated30 th August 2012 from the Appointed Date (the "Project Milestone-I").
Achieved notification awaited.
Prior to the occurrence of Project Milestone-I, the Concessionaireshall have commenced constructionof the Project Highway and expended not less than 10% (ten per cent) of the total capital cost setforth in the Financial Package.
2.1.2 Project Milestone-IIProject Milestone-II shall occur on the date falling on the 410th (Four hundred and tenth) day Datedzs" March 2013 from the Appointed Date (the "Project Milestone-II"). t
Achieved notification awaited
Prior to the occurrence of Project Milestone-II, the Concessionaire shall have commencedconstruction of all bridges and expended not less than 35% (thirty five per cent) of the total capitalcost set forth in the Financial Package.
2.1.3 Project Milestone-III
Project Milestone-III shall occur on the date falling on the 618th (Six hundred and eighteenth) dayDated zo" October 2013 from the Appointed Date (the "Project Milestone-III").
Prior to the occurrence of Project Milestone-III, the Concessionaire shall have commencedconstruction of all Project Facilities and expended not less than 70% (Seventy per cent) of the totalcapital cost set forth in the Financial Package.
2.2 Construction Programme
Concessionaire has submitted the construction programme.
ProgressSummary
Physical & Financial Progress
2.3
2.3.1
Cum.Achieved by end of During the month of Cum.Achieved by endDescription April-20l3 May-20l3 ofMay-20l3
Achieved Planned Achieved Planned Achieved Planned
Physical Progress % 35.73 % - 0.00% - 35.73 % -
Financial Progress % 56.77% - 0.00% - 56.77% -
Page 1- 4 Abhijeet Hazaribagh Toll Road Ltd.
-Mile Total Phvsical Procress ueto June -13
stone Description Unit Quantity Cost For The Item Weightage % AchievedAmount WeiahtauE %
A 04 LANE NH33 BH HAZA - SUPPLY
A.l Supply Workdone
1 OWNER ROYALTY FOR BOULDER Km 41.314 8.67 2.04% 5.3 1.24%
2 COST OF CEMENT Km 41.314 18.92 4.44% 4.6 1.08%
3 COST OF REINFORCEMENT Km 41.314 13.65 3.21% 8.2 1.93%
4 COST OF BITUMEN Km 41.314 74.47 17.50% 8.1 1.90%
5 COST OF EMULSION Km 41.314 2.68 0.63% 0.8 0.18%
6 COST OF SAND Km 41.314 1.55 0.36% 0.3 0.08%
7 COST OF SOIL Km 41.314 11.28 2.65% 5.1 1.21%
8 ROAD FURNITURE Km 41.314 5.75 1.35% - 0.00%
9 ATM AND EXTRA Km 41.314 2.55 0.60% • - 0.00%
/ B 04 LANE NH33 BH HAZA - SERVICE-B.l Service Workdone
1 BASE Camp Km 41.314 /'0.6 0.15% 0.6 0.15%.-- ,
2 LAB EQUIPMENT Km 41.314 0.3 0.06% 0.3 0.06%
3 OFFICE SET-UP Km 41.314 6.5 1.53% 4.1 0.97%
4 EQUIPMENT DEPRESSION Km 41.314 2.5 0.59% 2.5 0.59%
5 SUPERVISION C~s'i\l
Km 41.314 0.8 0.18% 0.4 0.10%....'" .•. , -
6 DESIGN & DRAWING Km 41.314 28.6 6.72% 28.2 6.63%
7 BASE Camp OPERATION Km 41.314 .!4.8 22.28% 62.5 14.69%
8· SITE CLEARENCE Km 41.314 6.4 1.51% 3.9 0.92%
9· . -I=ARTHWORK Km 41.314 48.0 11.28% 29.0 6.82%I--'-~"'- .... '_ .... _-
10 GSB & WMM Km 41.314 19.3 4.53% 5.4 1.28%
11 BITUMINOUS WORK Km 41.314 16.0 3.77% 1.8 0.41%
-~ 12 CROSS DRAINAGE WORK Km 41.314 6.7 1.58% 2.7 0.63%
13 BRIDGE/FLYOVER ETC Km 41.314 6.2 1.45% 3.9 0.91%
14 DRAIN/RETAINING WALL Km 41.314 19.3 4.54% 0.3 0.08%
15 TOLL PLAZA Km 41.314 4.5 1.05% - 0.00%
16 ROAD MAINTENENCE Km 41.314 8.1 1.91% 8.1 1.89%
17 CONST. OF FOUNDATION Km 41.314 13.0 3.05% 13.0 3.05%
18 HORTICULTURE Km 41.314 1.9 0.44% - 0.00%
19 MISCLLEANOUS WORK Km 41.314 0.9 0.21% 0.1 0.02%
20 MAINTENENCE OF EQUIP Km 41.314 1.6 0.37% 0.3 0.08%
Total 425.66 100.00% 199.65 46.90%
B Advance Paid To EPC 42.00 9.87%
Grand Total 241.65 56.77%
PHYSICAL PROGRESS UP TO June 13
/"'0, Monthly Progress Report-June-2013
r>.Page 64
!J!IIIII""'"'- ) ) ) ) ) ) ) ') ') .) ') ) ') ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) )
I J )Monthly Progress Report
June-2013
2.3.2 PhysicalProgressof RoadWorks
2.3.2.1 Main Carriageway)
LHS RHS
%0/ %0/Total Progres.; %0/ Progress %0/
Project Length Upto During- Upto (As per Progress(As Upto During Upto (Asper Progress(AsLength Available May June June Project per length May June June Project per length
Sr. No. Description (Km) (Km) 2013 2013 2013 Length) available) 2013 2013 2013 Length) available) Remarks
1 C&G 41.314 22.69 20.2 0 20.2 48.89% 89.03% 20.3 0 20.3 49.14% 89.47%
2 Excavation 41.314 ?~.69 20.2 0 20.2 48.89% 89.03% 20.3 0 20.3 49.14% 89.47%~!tcJ
2 Embankment 41.314 22.69 20.2 0.1 20.2 48.89% 89.03% 20.3 0.0 20.3 49.14% 89.47%
3 Sub-grade 41.314 22.69 20.6 0.0 20.6 49.86% 90.79% 20.7 0.0 20.7 50.10% 91.23%
4 G5B 41.314 I 22.69 17.7 0.0 17.7 42.84% 78.01% 20.3 0.0 20.3 49.14% 89.47%
5 WMM 40.614 \ 22.69 15.7 0.0 15.7 38.66% 69.19% 16.31 0.0 16.31 40.16% 71.88%
6 Prime Coat 40.614 22.69 13.6 0 13.6 33.49% 59.94% 14.4 0 14.4 35.46% 63.46%
7 Tack Coat 40.614 22.69 13.6 0 13.6 33.49% 59.94% 14.4 0 14.4 . 35.46% 63.46%
8 DBM 40.614 22.69 13.6 0 13.6 33.49% 59.94% 14.4 0 14.4 35.46% 63.46%
:g Tack Coat 40.614 22.69 - - - - - 0.085 0 0.085 0.21% 0.37%
10 BC 40.614 22.69 - - - - - 0.085 0 0.085 0.21% 0.37%
11 PQC 0.7 - - - - - - - - - - -
~
~'"
Page 1- 5 Abhijeet Hazaribagh Toll Road Ltd.
•
"I ,---II
r=»;
r=-;
,',
r>.
r---"
,..-...,.
rr-;
r>.
1'-,
I'"
r<.
I'
r>;»<;
r>.
,.,
r>.
I'
r=-;
,"'-"'"
"r>.
r--,
r>.0"
/>
r=-.
"
Monthly Progress ReportJune- 2013
2.3.2.2 Service Road Details (Linear progress):-.Sr. Description Total LHS RH5 RemarksNo. Length Length Length %of Length Length %of
(Km) '(;ompleted Completer. Proqress Completed Completed ProqressUpto Upto Up to Up to
Previous June-13 Previous June-13Month Month
1 C&G 4.875
2 Embankment! 4.875Excavation
3 Sub-grade 4.875
4 GSB 4.875 Work Not Started5 WMM 4.875
6 Prime Coat 4.875 ~.
4.875)
7 BM
8 BC 4.875
Strip Chart of Road works is attached as Annexure - 2 A
2.3.3 Physical Progress of Structure Works:
No. of No. ofNo. of
Sr.Type of Structure Side
Total No. ofStructures Structures
Structures inNo. Structures Progress/
Tackled CompletedBalance
LHS 3 Nos. 3 Nos. 2 No. 1 Nos/ Nil
1 Major Bridges,
I
RHS 3 Nos. 1 No. 1 No. Nil / 2 Nos.
LHS 2 Nos. 2 Nos. 1 No. 1 Nos/ Nil
2 Minor Bridges
RHS 2 Nos. 1 No. Nil 1 No. /1 No.
LHS 60 Nos. 45 Nos. 42 Nos.3 Nos/ 16
Slab and BoxNo's
3Culverts
RHS 60 Nos. 37 Nos. 34 Nos.3 Nos./23Nos.
LHS 9 Nos. 9 Nos. 9 Nos. Nil/Nil
4 Pipe Culverts
RHS 9 Nos. 2 Nos. 1 Nos. 1 No / 7 Nos
Strip Chart of Structure works is attached as Annexure - 2 B & 2 C
Page 1-6 Abhijeet Hazaribagh Toll Road Ltd.
. --
Monthly Progress ReportJune- 2013
2.4 Mobilization Status of Concessionaire, EPCContractor.
A- CONCESSIONAIRE'S ORGANIZATION STRUCTURE- Annexure -1A
B- Man power gf EPCContractor
Sn. Descriptions Nos.l. Engineers 152. Technicians 253. Supervisors 354. Operators 3005 Labour (Skilled) - 606. Labour (Semi skilled) 1507. Labour (Unskilled) 200
j-,,2.4.1 Main Office @ Hazaribagh town.
2.4.2 Base Camp - @ Km 16+000 (Itkhori)
HM Plant, Crushing Plant, WMM Plant, Concrete Batching plant and Main Laboratory have beensetup.
2.5 Plant & Equipments at Site
List of plant & Equipments is attached as Annexure - 3
2.6 Quality Control
2.6.1 Quality Control Tests
"All required tests as per the frequencies and requirements of IRC code provisions are being carriedout in the laboratory and in the fieid, Details as per Annexure - 4
2.6.2 Summary of NCR
Sr. No. Description of NCR Toto/Issued Closed Balance Remarks
1 Structure 2 1 12 Road Works 8 5 3
Total 10 6 4
Page 1-7 Abhijeet Hazaribagh Toll Road Ltd.
i(\
Monthly Progress ReportJune- 2013
2.7 Land Acquisition Status
LA TEST STATUS OF I,ANDACQUISTTION
CHAINAGESn. VILLAGE (APPROX.) PRESENT STATUS AS ON 30.04.2013 OF L.A REMARKSNAME FROM TOI BARHI 0 1 CHEQUE DISTRIBUTION IS IN PROGRESS
2 KARSO 1 4 CHEQUE DISTRIBUTION IS IN PROGRESS
3 KHODAHAR 4 8.3 CHEQUE DISTRIBUTION COMPLETED
4 KADWA 8.3 10.8CHEQUE DISTRIBUTION COMPLETED5 KARMATAR 10.8 12.8
6 ROMI 12.8 13.57 PARTAN 13.5 14.1 CHEQUE DISTRIBUTION COMPLETED RHS
8 SURAJPURA 13.5 14.1 t· LHS
9 TILIDIH 14.1 15.5 CHEQUE DISTRIBUTION COMPLETED
10 ARAR 15.5 16.3 GM LAND (MATTER PENDING WITH AC HAZARIBAGH)
II JIHU 16.3 17.9 CHEQUE DISTRIBUTION COMPLETED
12 POKHARIA 17.9 19.9 FORESTLAND
SIJHUA19.9 20.9 FORESTLAND WILDLIFE1321.9 25 FORESTLAND
14 DANGI 20.9 21.9 FORESTLAND
15 GOBARBANDA 25 26.1 CHEQUE DISTRIBUTION IS IN PROCESS.
16 BARIAT 26.1 26.6 CHEQUE DISTRIBUTION IS IN PROCESS.
17 SIRSI 26.6 28 CHEQUE DISTRIBUTION ALMOST COMPLETED
18 BONGA 28 29 CHEQUE DISTRIBUTION IS IN PROCESS
19 NAGAON 29 31.3 CHEQUE DISTRIBUTION IS IN PROCESS
20 SINDUR 31.3 32.5 CHEQUE DISTRIBUTION COMPLETED BY PASS
21 KORRA 32.5 34.2 VALU ATION OF STRUCTURE NOT YET DONE.;
BY PASS
22 ZABRA 34.2 35.8 CHEQUE DISTRIBUTION COMPLETED BY PASS
23 SINGHANI 35.8 3724 ORIYA 37 37.6
CHEQUE DISTRIBUTION ALMOST COMPLETED .. BY PASS
25 LAKHE 37.6 38.1 CHEQUE DISTRIBUTION YET TO BE STA TRED BYPASS
26 CHANO 38.1 40 CHEQUE DISTRIBUTED COMPLETED BY PASS
27 HURHURU 40 40.7MASHIPIDHI
CHEQUE DISTRIBUTION COMPLETED BY PASS28 40.7 41.2
,"Abstract of Land Handed Over (Encumbrance free)Sr.No Chainage Length (KM)1 V Ch: 0.250 to 1.100 '7 0.852 Ch: 3.140 to 15.500 = 12.36 .3 Ch: 27:700 to 29.300 = 1.604 Ch: 30.000 to 30.450 = 0.4505 Ch: 31.010 to 32.650= 1.6406 Ch: 35.380 to 36.250= 0.8707 Ch: 36.250 to 38.750= 2.5008 Ch: 38.780 to 41.200= 2.42
Total Length available 22.69 (Km)55% Land handed over for four lanning.
PROGRESS OF· WORK, NOT GOOD DUE TO NON AVAILABILITY OFSUFFECIENT ENCUMBRANCE FREELAND.
Page 1-8 Abhijeet Hazaribagh Toll Road Ltd.
,--.
'"',-.,
r>.
~
I~
~
r>.
r>.
~
r>
r>.
r-.r=;
,""
r>.
r=.
r>.
r>.
.r'\
r>
~
~
~
"r>.
r>.
r=.
r>.
r>.
r>.
r'\
f'..
r>.
r>.
r=-:
r>.
rr>;
rr<.,
Monthly Progress ReportJune- 2013
2.8 Pre Construction Activities
2.8.1 Tree Cutting Status:
2.9 Utilities Shifting:
2.9.1 Water Supply Pipe Line:,-
Estimationunderr---+-------------r-----~------~--------._------_.--------~approvalwith NHAI
1
12 Water Pipe LineShifting
2.9.2 Electrical LineShifting:
Electricpolespurchasedand erection started. 1226Nos.of poleserected.
2.10 Others Hindrances:-
2.11 Surveyworks:
2.11.1 Traversing Details
2.11.2 TBM CheckingStatus
Work Completed
2.11.3 Alignment checkingstatus
Page 1-9 Abhijeet Hazaribagh Toll Road Ltd.
,..-.,
-"""
r-...
r--
r--
r--.
f""'.
r=;
,,-...
r>:
r>:
r<:
f'
,,--...,r--
,,-.,
,......."
f'
r-r--;
f'
f'
r».
r<;
,.-...
r-'
f'
f'
r>.
r-.
""'
r-.
r>
r--
r>
/"'
,.-..
r>.
, r-.
Monthly Progress ReportJune- 2013
2.12 ConstructionMethod Statement:
The Method Statement for GSB: WMM and DBM submitted to IE vidp. our letter no..AHTRL/NJB/2010/43 dated 31.08.2011. IE reviewed the same and approved vide letter no: SAI/IC-HAZARIBAG/AHTRL/007/2011 dated 10.09.2011, SAI/IC-HAZARIBAG/AHTRL/027/2011 Dated za"Oct'l1, SAI/IC-HAZARIBAG/AHTRL/029/2011 Dated 24th Oct'l1, SAI/IC-HAZARIBAG/AHTRL/030/2011Dated 24thOct'l1.
The Method Statement for concreting works for Bridges & Culvert submitted to IEvide our letter no:AHTRL/HZB/2010/63 dated 28.10.11 and Method Statement for Embankment & Sub-grade vide ourletter no: AHTRL/HZB/2010/64 dated 28.10.11. IE approved the method statements vide letter nos:SAI/IC-HAZARIBAGH/AHTRL/038/2011 & SAI/IC-H~Z~RIBAGH/AHTRL/037/2011 dated 08.11.2011.
The Method Statement for reconstruction & Strengthening of Existing Road submitted to IEvide ourletter no: AHTRL/HZB/2010/115 dated 23.02.2012.
~.,2.13 JobMix Formula/Mix Design:
Job mix formula for GSB, WMM, DBM and Concrete mix design for various grade of concretesubmitted to IEfor their approval and the same has been approved by IE.
Mix design for BCsubmitted to IEfor their review and approval vide letter No. AHTRL/HZB/2010/440dated 12.07.2012.
2.14 Quality AssuranceManualandPlan:
Quality Assurance Manual and Plan has been submitted for approval vide letter No.AHTr.:",'HZE:/2010/43dated 13.09.2011 & the same has been approved ~.y.IE.
2.15 Safety,Healthand EnvironmentManual:
The safety, Health and Environment Manual has been submitted to IEfor approval arfd the same hasb~Gil approved by IE.
3.0 Design
3.1 DesignReview
a. Culverts vide letter AHTRL/HZB/2010/46 dated 07.09.2011.b. Bridgesvide letter AHTRL/HZB/2010/46 dated 07.09.2011.c. Plan & Profile vide letter AHTRL/HZB/2010/69 dated 7.11.2011.
3.2 DesignChanges
3.3 Changeof Scope
Yet to be submitted
Page 1-10 Abhijeet Hazaribagh Toll Road Ltd.
) ) ) ) ) ) ) ) ) ) ) ))
)) ) ) ) ) ) )) ) ') ))
) ) ) ) ) ) ) ) ))
Monthly Progress ReportJune- 2013
3.4 Details of Non-Conforming Report
Date~ I -~ , \'7;'s,:>::r~ ."".'< , I·f;' -:., ~:& ••
E/W in embankment at Ch-1 I SAI/IC-Hazaribagh/AHTRL/06Z/Z01Z 1 13.01.Z01Z 1 Highway 1 40+750 I AHTRL/HZB/ZOI0/136A I 24.03.2012
to Ch·40+950 R/SWMtll Top layer from Ch-35+750
Z I SAI/IC-Hazaribagh/AHTRL/064/Z01Z 1 14.01.Z01Z 1 Highway 1 to 35+950 B/S, Ch-35+940 to I AHTRL/HZB/ZOI0/136A I 24.03.201236+050back filling behind Box culvert @
3 I SAI/IC-Hazaribagh/AHTRL/11B/Z01Z 1 05.05.Z01Z 1 Structure I Ch -11+B15, Ch-11+BBO & Ch-1Z+054
4 I SAI/IC-Hazaribagh/ AHTRL/1ZZ/Z01Z OB.05.Z01Z HighwayWMM Top layer from
AHTRL/HZB/ZOI0/165 I 15.05.2012Ch 6+BZO to 6+9BO LHS
5 I SAI/IC-Hazaribagh/ AHTRL/13Z/Z01Z ZO.06.Z01Z Highway DBMMix AHTRL/HZB/SAI/ZOI0/438 I 24.04.2013
6 I SAI/IC-Hazaribagh/ AHTRL/13Z/Z01Z ZO.06.Z012 Highway GSB Material AHTRL/HZB/SAI/ZOI0/438 I 24.04.2013D8M Top Layers from Ch 10+300
7 I SAI/IC-Hazaribagh/AHTRL/153/Z01Z I Z3.07.Z01Z I Highway I to 13+360 LHS, Ch 11+705, Ch9+605 to 9+645WMM Top layer from Ch 39+630
8 I SAI/IC-Hazaribagh/AHTRL/153/Z01Z I Z3.07.Z01Z I Highway I to 39+940 8/5, Ch 31+BOO to I AHTRL/HZ8/SAI/ZOI0/438 I 24.04.201331+900LHS
9 I SAI/IC-Hazaribagh/ AHTRL/153/Z01Z Z3.07.Z01Z StructureFilter medial back filling behindabutment wall at Ch 40+700
10 I SAI/IC-Hazaribagh/ AHTRL/153/Z01Z Z3.07.Z01Z Highway GS8 Material
.•~"
lJ Abhijeef Hazaribagh Toll Road Ltd.Page 1- 11
•
)
,......,
r--
r>;
r'-
r+>;
7'
r=.
7'
r>
r"">;
r·
r>.
r>r=>;
~
f'
r>.
....---,
r>.
r-.
rr-.
»<;
f'
,.-..,I'"
r>.
r>.
r>.
r>.
~,
r-,
r>.
f'
Monthly Progress ReportJune- 2013
4.0 Maintenance
4.1 Existing Two lane Road:
Repair of Potholes had been undertaken at Nos of location throughout the project corridor.
4.2 Existing Bridges:
NIL
5.0 Health, Safety, Security, Environment and Accident
5.1 Health
No matters arising
5.2 Safety -: ~-j
Two nos. of Safety Officers along with support staffs are deployed at Site to take care of safetyaspects and Traffic Management. In addition, one more Safety Officer has been specially appointed atShiwaney Bridge to look after the safety issuesduring the constructions.
5.2.1 Safety during construction stage.
Road Signs & Delineators, on Project corridor have been installed. Hazard Marker Sign at BridgeEntrance has been installed.
5.3 Security
The project road comes under areas affected by extremist (Naxallte) activity; We have deployedarmed police persons at camp site as per direction of local administration through NHAI.
5.4 Accident Report
Accident report attached as Annexure - 6
6.0 Constraint
• Land acquisition should be done fast by NHAI.• Environment Clearanceto be expedited by NHAI.• Forest Clearance is still the biggest bottleneck.
Page 1- 12 Abhijeet Hazaribagh Toll Road Ltd.