Post on 22-Mar-2021
HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL)
Registered Office : Village Phulokhari, Taluka Talwandi Saboo, Bathinda, Punjab-151301
Corporate Office : Inox Towers, Plot No. 17, Sector 16A, Noida-201301 in the State of Uttar Pradesh. Tel : 0120 – 463 4500/4610, Fax : 0120-42719 38/39/40.
Application as per Form 1 of the EIA Notification 2006: Mundra – Bathinda Pipeline Capacity Expansion Project
NOVEMBER 2015
M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 1
Application as per Form 1 of the EIA Notification 2006: Mundra – Bathinda Pipeline Capacity Expansion Project
This report is released for the use of the HPCL-Mittal Pipelines Limited, Regulators and relevant
stakeholders solely as part of the subject project’s Environmental Clearance process. Information
provided (unless attributed to referenced third parties) shall not be used for any other purpose
without the written consent of HPCL-Mittal Pipelines Limited.
QUALITY CONTROL
Name of
Publication Form 1: Mundra – Bathinda Pipeline Capacity Expansion Project
Project
Number 2015-16-01
Report
No. 1 Version 1 Released November 2015
Prepared By Prodip Kumar Biswas, AGM - Pipeline
Reviewed By Pawan Kumar Agarwal, GM - Pipeline
Released By Prodip Kumar Biswas, AGM - Pipeline
DISCLAIMER
HPCL-Mittal Pipelines Limited has taken all reasonable precautions in the preparation of this report as per its
auditable quality plan. HPCL-Mittal Pipelines Limited also believes that the facts presented in the report are
accurate as on the date it was written. However, it is impossible to dismiss absolutely, the possibility of errors or
omissions. HPCL-Mittal Pipelines Limited therefore specifically disclaims any liability resulting from the use or
application of the information contained in this report. The information is not intended to serve as legal advice
related to the individual situation.
M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 2
CONTENTS
1 SCOPING .................................................................................. 5
2 PROPOSED TERMS OF REFERENCE ............................................... 19
M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 3
LIST OF ANNEXURES
1 SCOPING .................................................................................. 5
2 PROPOSED TERMS OF REFERENCE ............................................... 19
ANNEXURE 1: PIPELINE ROUTE MAP ............................................................... 22
ANNEXURE 2: TOPOGRAPHY OF IPS-1, IPS-2, IPS-3, IPS-4 & IPS-5 LOCATIONS AND
AREAS WITHIN 10 KM RADIUS SHOWING ROADS, ADJACENT
LOCALITIES, FORESTS, WATER BODIES, PROTECTED AREAS, STATE &
NATIONAL BOUNDARIES (IF ANY) ............................................... 23
ANNEXURE 3: CGWA CATEGORIZATION OF TALUKAS . ........................................ 28
ANNEXURE 4: HAZARDOUS WASTE – TYPE, MODE AND DISPOSAL ........................ 32
M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 4
ABBREVIATIONS
API American Petroleum Institute
ASME American Society of Mechanical Engineers
DG Diesel generator
ESD Emergency Shut Down
FV Full Vacuum
HDPE High Density Polyethylene
IEC International Electro technical Commission
IJ Insulating Joint
IPS Intermediate Pigging Station
ISA International Society of Automation
MOC Material of Construction
MBPL Mundra-Bathinda Pipeline
MMTPA Million Metric ton per Annum
MSL Mean Sea Level
NBP Nominal Boiling Point
OFC Optical Fiber Cable
OISD Oil Industry Safety Directorate
PFD Process Flow Diagram
PUF Polyurethane Foam
PE Polyethylene
RCC Reinforced Cement Concrete
RJ Rajasthan
SCADA Supervisory Control And Data Acquisition
XSV Emergency Shutdown Valve
M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 5
1 SCOPING
The scoping for the project has been done based on FORM 1, as per EIA Notification, dated September 14, 2006
amended as on date. The scoping details are as follows:
I. Basic Information
S.
No. Item Details
1 Name of the Project/s Mundra – Bathinda Pipeline Capacity Expansion Project
2 S. No. in the Schedule 6(a) & 6(b)
3
Proposed capacity / area / length /
tonnage to be handled/ command
area / lease area / no. of wells to
be drilled
Capacity expansion of Mundra – Bathinda Crude Oil Pipeline from 9 MMTPA to
11.25 MMTPA by converting 2 of its existing intermediate pigging stations into
pumping stations.
4 New / Expansion / Modernization Expansion
5 Existing Capacity / Area etc. 9 MMTPA
6 Category of Project (A or B) A
7 Does it attract the general
conditions? If yes, please specify.
Yes. The general condition no. ii. specifies that “There will be no change in the
pipeline route, design, capacity without the prior approval of this Ministry. While
laying the pipeline, OISD standards with regard to distance etc. from private
buildings, industrial buildings or places or habitation etc. should be followed.”
8 Does it attract specific condition? If
yes, please specify No
9
Location
Khasra no. 141/P, Village Mundra, Taluka Mundra, District Kutch in Gujarat
to
Mastile No. 123, Kila no. 27, Village Ramsara, Taluka Talwandi Saboo, District
Bathinda, Punjab.
Plot Survey / Khasra No.
Please refer Pipeline Route Map attached as Annexure 1
Location of Intermediate Pigging
Stations out of which 1 will be
converted to pumping stations
after detailed engineering study.
Location of Intermediate
Pigging Stations out of which 1
will be converted to pumping
stations after detailed
engineering study.
Existing
Intermediate
Pumping
Station
IPS-1 IPS-2 IPS-4 IPS-5 IPS-3
Survey
Nos.
103/2-
P1&P2,
104,
105
Survey Nos. 90/1P, 91,
92P1 Survey No. 219 Survey No. 67
Survey Nos.
152, 156, 157,
172, 173
Village Dedarva Juna Raviyana Jud Shri Dungargarh Dhansa
Tehsil / Taluka / Mandal Taluka
Rapar Taluka Kankrej Tehsil Osian
Tehsil Shri
Dungargarh
Tehsil
Jaswantpura
District Kutch Banaskantha Jodhpur Bikaner Jalore
State Gujarat Gujarat Rajasthan Rajasthan Rajasthan
M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 6
S.
No. Item Details
10 Nearest railway station / airport /
along with distance in km.
IPS-1 IPS-2 IPS-4 IPS-5 IPS-3
Chitrod
Railway
Station ~1.5
km in South
direction
Airport
Kandla, ~70
km in South-
West
direction,
Bhuj, ~134
km in West
direction
Deodar
Railway
Station ~13
km in West
direction
Airport
Deesa (small
airstrip), ~36
km in North-
East direction,
Ahmedabad,
~135 km in
South-East
direction
Mathania
Railway
Station ~7.7
km in South-
West
direction
Airport
Jodhpur, ~37
km in South
direction
Shri
Dungargarh
Railway
Station ~12.5
km in South
direction
Airport
Nal (Bikaner),
~77 km in
West
direction
Modaran
Railway
Station ~12.5
km in South
direction
Airport
Noon
(Jalore),
~17.5 km in
East
direction,
Jodhpur,
~133.5 km in
North-East
direction
11
Nearest town, city, district
headquarters along with distances
in kms
IPS-1 IPS-2 IPS-4 IPS-5 IPS-3
Nearest Town
(population
>5,000)
Rapar;
distance of
~14 km in
North
direction
Nearest City
(population
>1,00,000)
Gandhidham;
distance of
~70 km in
South-West
direction
Nearest
District
Headquarters
Bhuj;
distance of
~107 km in
West-South-
West
direction
Nearest Town
(population
>5,000)
Mehsana;
distance of
~73 km in
South-East
direction
Nearest City
(population
>1,00,000)
Mehsana;
distance of
~73 km in
South-East
direction
Nearest District
Headquarters
Palanpur;
distance of
~52 km in
East direction
Nearest Town
(population
>5,000)
Jodhpur;
distance of
~37.9 km in
South
direction
Nearest City
(population
>1,00,000)
Jodhpur;
distance of
~37.9 km in
South
direction
Nearest
District
Headquarters
Jodhpur;
distance of
~37.9 km in
South
direction
Nearest Town
(population
>5,000)
Shri
Dungargarh;
distance of
~9.6 km in
South-South-
East direction
Nearest City
(population
>1,00,000)
Bikaner;
distance of
~69 km in
West-South-
West
direction
Nearest
District
Headquarters
Bikaner;
distance of
~69 km in
West-South-
West
direction
Nearest Town
(population
>5,000)
Bhinmal;
distance of
~25 km in
South-South-
West
direction
Nearest City
(population
>1,00,000)
Pali; distance
of ~114 km
in North-East
direction
Nearest
District
Headquarters
Jalore;
distance of
~28.6 km in
North-East
direction
M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 7
S.
No. Item Details
12
Village Panchayat, Zilla Parishad,
Municipal Corporation, Local Body
(complete postal address with
telephone nos. to be given)
IPS-1 IPS-2 IPS-4 IPS-5 IPS-3
Gram
Panchayat
Dedarva,
Post Chitrod
Taluka Rapar
District
Kutch,
Gujarat -
370145
Telephone
No. : N.A.
Gram
Panchayat
Raviyana,
Post Raviyana
Taluka Kankrej
District
Banaskantha,
Gujarat -
385550
Telephone No.
: N.A.
Gram
Panchayat
Newra Road,
Post Jud
Tehsil Osiyan
District
Jodhpur,
Rajasthan -
342305
Telephone No.
: N.A.
Municipality
Shri
Dungargarh,
Post Shri
Dungargarh
Tehsil Shri
Dungargarh
District
Bikaner,
Rajasthan -
331803
Telephone No.
: N.A.
Gram
Panchayat
Dhansa,
Post Dhansa
Tehsil
Jaswantpura
District Jalore,
Rajasthan -
343023
Telephone No.
: N.A.
13 Name of the applicant HPCL-Mittal Pipelines Limited,
14 Registered address Village Phulokhari, Taluka Talwandi Saboo, District Bathinda, Punjab- 151301.
15
Address for correspondence
Name Prodip Kumar Biswas
Designation AGM - Pipeline
Address INOX Towers, Plot No. 17, Sector – 16A,
Noida, Uttar Pradesh.
Pin Code 201301
E-mail prodip.biswas@hmel.in
Telephone no. +91 120 463 4610, +91 9811436258
Fax no. 0120-4271940
16
Details of alternative sites
examined, if any. Location of these
sites should be shown on the
Toposheet
Not Applicable. The pipeline is already laid and is operational. The stations IPS-2,
IPS-4, IPS-5 are operational pigging stations having adequate land for conversion
into pumping stations. IPS-1 land on the pipeline route is in the name of HPCL-Mittal
Pipelines Ltd that can be converted into pigging cum pumping station.
17 Interlinked Projects No
18
Whether separate application of
interlinked project has been
submitted?
Not applicable
19 If yes, date of submission Not Applicable
20 If no, reason Not applicable
21
Whether the proposal involves
approval / clearance under: if yes,
details of the same and their status
to be given:
The Forest (Conservation) Act, 1980
The Wildlife (Protection) Act, 1972
The C.R.Z Notification, 1991
Forest Conservation Act: No
The Wildlife (Protection) Act, 1972: No
The C.R.Z Notification, 1991 : Not Applicable
22
Whether there is any Government
order / policy, relevant / relating to
the site
No
M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 8
S.
No. Item Details
23 Forest land involved (ha.) No
24
Whether there is any litigation
pending against the project and / or
land in which the project is
proposed to be set up?
Name of the Court
Case No.
Order / directions of the Court, if
any and its relevance with the
proposed project
No
II. Activity
1. Construction, operation or decommissioning of the project involving actions, which will cause
physical changes in the locality (topography, land use, changes in water bodies, etc.)
S. No. Information/Checklist
Confirmation
Yes /
No?
Details thereof (with approximate quantities /
rates, wherever possible) with source of
information data
1.1
Permanent or temporary change in
land use, land cover or topography
including increase in intensity of
land use (with respect to local land
use plan)
Yes Additional facilities will be built within the existing
stations/land leading to increase in intensity of land use
1.2 Clearance of existing land,
vegetation and buildings? No Not Applicable
1.3 Creation of new land uses? No The pumping stations will be built on existing land owned
by M/s HPCL Mittal Pipelines Ltd.
1.4 Pre-construction investigations e.g.
bore houses, soil testing? Yes
Although preconstruction investigations will be carried out,
these will not cause physical changes in the locality.
1.5 Construction works? Yes The pumping stations will have built-up structures which
will change the physical layout of the area.
1.6 Demolition works? Yes
The existing buildings may need to be demolished for
construction of other plant buildings like control room,
substation, fire engine shed, DG shed, parking shed, pump
house/shed, fire water pump house, warehouse etc.
1.7
Temporary sites used for
construction works or housing of
construction workers?
No
These workers will be brought from the nearby
town/village and will be at site for the duration of their
shifts. Few portable and temporary cabins (functioning as
site office/ware house) are likely to be placed at the site
for the duration of the project.
1.8
Above ground buildings, structures
or earthworks including linear
structures, cut and fill or
excavations
Yes
Two licensed underground tanks of 20 m3 storage capacity
each exist at IPS-2, IPS-3, IPS-4 & IPS-5 respectively. Two
underground tanks of 20 m3 storage capacity each will be
constructed at IPS-1 in addition to other ancillary facilities
covered in the pre-feasibility report submitted along with
this Form I application.
1.9 Underground works including No Not Applicable
M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 9
S. No. Information/Checklist
Confirmation
Yes /
No?
Details thereof (with approximate quantities /
rates, wherever possible) with source of
information data
mining or tunneling?
1.10 Reclamation works? No Not Applicable
1.11 Dredging? No Not Applicable
1.13 Production and manufacturing
processes? No Not Applicable
1.14 Facilities for storage of goods or
materials? Yes As mentioned in S. No 1.7
1.15 Facilities for treatment or disposal
of solid waste or liquid effluents? No
Solid Wastes
Although solid waste will be generated, these will be only
stored temporarily and disposed to a GPCB/RSPCB
authorized TSDF
Liquid Effluents
No liquid effluents will be generated other than domestic
effluent (sewage) which will be disposed off in a soak pit/
septic tank within the site.
1.16 Facilities for long term housing of
operational workers? No Not Applicable
1.17 New road, rail or sea traffic during
construction or operation? Yes
Construction phase
During construction phase, vehicles transporting
construction equipment and workers will be used
Operation phase
Very few (one or two) vehicles transporting staff and
workers for operational phase will be used.
1.18
New road, rail, air, waterborne or
other transport infrastructure
including new or altered routes and
stations, ports, airports etc?
No
The project is for developing pumping stations for
boosting the pressure of the crude oil inside the pipeline
that is required to increase the flow in the pipeline covered
under category 6(a) of EIA notification 2006
1.19
Closure or diversion of existing
transport routes or infrastructure
leading to changes in traffic
movements?
No Not Applicable
1.20 New or diverted transmission lines
or pipelines? No Please read S. No 1.18
1.21
Impoundment, damming,
culverting, realignment or other
changes to the hydrology of
watercourses or aquifers?
No Not Applicable
1.22 Stream crossings? No Not Applicable
1.23 Abstraction or transfers of water
from ground or surface waters? Yes
~ 24.2 KLD for each station
Source: Ground Water, few users residing in nearby areas
also utilize ground water for their domestic and irrigation
M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 10
S. No. Information/Checklist
Confirmation
Yes /
No?
Details thereof (with approximate quantities /
rates, wherever possible) with source of
information data
purposes.
1.24
Changes in water bodies or the land
surface affecting drainage or run-
off?
No
1. There is no impact on surface drainage due to waste
water generation since waste water will be
discharged into a soak pit/ septic tank.
2. The area of IPS-1, IPS-2, IPS-4 & IPS-5 are flat and
do not have a pronounced slope. Rainfall is scanty
consequently no significant change in surface
drainage is envisaged.
1.25
Transport of personnel or materials
for construction, operation or
decommissioning?
Yes Please read S. No 1.17
1.26
Long-term dismantling or
decommissioning or restoration
works?
Yes
Existing Temporary IPS-1 facilities will be dismantled and
shifted to permanent IPS-1 land plot in case, this station is
chosen after detailed engineering for conversion to
pumping station.
1.27
Ongoing activity during
decommissioning which could have
an impact on the environment?
No Not Applicable
1.28 Influx of people to an area either
temporarily or permanently? No
Although some people will be present at the site during
the construction period, the no of persons cannot be called
an “influx”.
1.29 Introduction of alien species? No Not Applicable
1.30 Loss of native species or genetic
diversity? No Not Applicable
1.31 Any other actions? No None identified.
2. Use of Natural resources for construction or operation of the Project (such as land, water,
materials or energy, especially any resources which are non-renewable or in short supply):
S. No. Information/Checklist
confirmation
Yes /
No?
Details thereof (with approximate quantities / rates,
wherever possible) with source of information data
2.1 Land especially undeveloped or
agricultural land (ha) No
The IPS-1, IPS-2, IPS-3 & IPS-4, IPS-5 are already existing out of
which IPS-2, IPS-3 & IPS-4, IPS-5 are being used as part of the
Mundra – Bhatinda Pipeline. Only IPS-1 land that is in the name of
HPCL-Mittal Pipelines Limited is not under any use as of now.
2.2 Water (expected source & competing
users) unit: KLD Yes
~ 24.2 KLD for each station
Source: Ground Water, few users residing in nearby areas also
utilize ground water for their domestic and irrigation purposes.
2.3 Minerals (MT) No None other than those mentioned in S. No 2.4
2.4
Construction material stone,
aggregates, sand / soil (expected
source, MT)
Yes These will be purchased from nearby suppliers.
2.5 Forests and timber (source, MT) No Not Applicable
M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 11
S. No. Information/Checklist
confirmation
Yes /
No?
Details thereof (with approximate quantities / rates,
wherever possible) with source of information data
2.6
Energy including electricity and fuels
(source, competing users) unit: fuel
(MT), energy (MW)
Yes
Construction
Electricity from grid.
Emergency Power from DG set.
Diesel from nearby retail outlet.
Operations
Electricity from grid.
Emergency Power from DG set (320 kVA running on HSD sourced
from nearby retail outlet).
2.7 Any other natural resources (use
appropriate standard units) No Not Applicable
3. Use, storage, transport, handling or production of substances or materials, which could be
harmful to human health or the environment or raise concerns about actual or perceived risks to
human health.
S. No. Information / Checklist
confirmation
Yes /
No?
Details thereof (with approximate quantities / rates,
wherever possible) with source of information data
3.1
Use of substances or materials, which
are hazardous (as per MSIHC rules) to
human health or the environment (flora,
fauna, and water supplies)
Yes
1. HSD used for running the standby DG sets in case of
electricity outages and Fire water pumps in case of fire.
2. Crude oil, which is being transported in the pipeline is also
hazardous.
3.2
Changes in occurrence of disease or
affect disease vectors (e.g. insect or
water borne diseases)
No No correlation between project activities and occurrence of
diseases or disease vectors has been established.
3.3 Affect the welfare of people e.g. by
changing living conditions? Yes
Some additional (direct and indirect) employment will be generated
due to the project and this will add to the wellbeing of nearby
communities.
3.4
Vulnerable groups of people who could
be affected by the project e.g. hospital
patients, children, the elderly etc.,
No None identified
3.5 Any other causes No None identified
4. Production of solid wastes during construction or operation or decommissioning (MT/month)
S. No. Information/Checklist confirmation Yes/
No?
Details thereof (with approximate quantities / rates,
wherever possible) with source of information data
4.1 Soil, overburden or mine wastes No Not Applicable
4.2 Municipal waste (domestic and or
commercial wastes) Yes Minor amount (< 5 kg/day) of municipal waste will be generated.
4.3 Hazardous wastes (as per Hazardous
Waste Management Rules) Yes Please refer Annexure-4
4.4 Other industrial process wastes No Not Applicable
4.5 Surplus product No Not Applicable
4.6 Sewage sludge or other sludge from Yes ~ 2.43 KLD Sewage for each station
M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 12
S. No. Information/Checklist confirmation Yes/
No?
Details thereof (with approximate quantities / rates,
wherever possible) with source of information data
effluent treatment
4.7 Construction or demolition wastes Yes
Some construction waste will be generated and this will be sent
to recyclers/re-users/scrap dealers or in case of inert waste will
be used for land filling.
4.8 Redundant machinery or equipment No
All construction related equipment will be removed from the site
by the contractors at the end of the construction phase. During
the operation phase no redundant machinery or equipment will be
generated.
4.9 Contaminated soils or other materials No These will not be generated in the normal condition.
4.10 Agricultural wastes No Not Applicable
4.11 Other solid wastes No None identified
5. Release of pollutants or any hazardous, toxic or noxious substances to air(kg/hr)
S. No. Information/Checklist confirmation Yes/No?
Details thereof (with approximate quantities /
rates, wherever possible) with source of
information data
5.1 Emissions from combustion of fossil fuels from
stationary or mobile sources Yes
A 320 kVA stand-by DG set will be used at each station
respectively during times of power failure and will emit
PM, SO2, NOx. Three 284 KW Fire Water Engines will also
be used at each station respectively. The DG Sets as well
as the engines will run on Diesel (HSD).
5.2 Emissions from production processes No
There is no production process and in the normal course
pumping and transfer of crude oil will be done using grid
power.
5.3 Emissions from materials handling including
storage or transport No Please read S. No 5.1 & 5.2 above
5.4 Emissions from construction activities including
plant and equipment Yes
Certain emissions such as from batch mixing plant and
other diesel operated construction equipment and
vehicles will be generated.
5.5
Dust or odours from handling of materials
including construction materials, sewage and
waste
Yes Minor dust will be generated during the construction
phase of the project.
5.6 Emissions from incineration of waste No Not Applicable
5.7 Emissions from burning of waste in open air
(e.g. slash materials, construction debris) No Not Applicable
5.8 Emissions from any other sources No None identified
6. Generation of Noise and Vibration, and Emissions of Light and Heat:
S. No. Information/Checklist confirmation Yes / No? Details thereof (with approximate quantities / rates,
wherever possible) with source of information data
6.1 From operation of equipment e.g. engines,
ventilation plant, crushers
Yes Noise
Construction Phase:
Noise and vibration will occur due to different construction
M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 13
S. No. Information/Checklist confirmation Yes / No? Details thereof (with approximate quantities / rates,
wherever possible) with source of information data
materials and vehicles.
Operation Phase:
Noise from DG set for emergency power requirement during
grid power outages.
Noise from fire water pumps during firefighting only (if any)
All noise levels will be within CPCB prescribed limits.
Light
Construction Phase:
Light emissions will occur due to construction operations
during the night time and floodlighting arrangements for the
same as also from vehicles or equipment used for
construction purposes.
Operation Phase:
Light emissions will occur due to operation of the facility
during the night time and floodlighting arrangements for the
same.
6.2 From industrial or similar processes Yes Noise and vibration from pumps within plant limit
conforming to CPCB guidelines
6.3 From construction or demolition Yes As mentioned in S. No 6.1
6.4 From blasting or piling Yes Possibly from laying of pile foundations (if required).
6.5 From construction or operational traffic Yes As mentioned in S. No 6.1
6.6 From lighting or cooling systems Yes As mentioned in S. No 6.1. No cooling systems are required
as part of the operating system
6.7 From any other sources No None identified
7. Risks of contamination of land or water from releases of pollutants into the ground or into
sewers, surface waters, groundwater, coastal waters or the sea
S. No. Information/Checklist confirmation Yes/No?
Details thereof (with approximate quantities /
rates, wherever possible) with source of
information data
7.1 From handling, storage, use or spillage of
hazardous materials No Pipeline along with its pump stations is a closed system.
7.2
From discharge of sewage or other effluents
to water or the land (expected mode and
place of discharge)
Yes Domestic sewage will be disposed into soak pit within the
premises.
7.3 By deposition of pollutants emitted to air into
the land or into water No Not Applicable during normal operations
7.4 From any other sources No None identified
7.5
Is there a risk of long term buildup of
pollutants in the environment from these
sources?
No Not Applicable
M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 14
8. Risk of accidents during construction or operation of the Project, which could affect human
health or the environment
S. No. Information/Checklist confirmation Yes/No?
Details thereof (with approximate quantities /
rates, wherever possible) with source of
information data
8.1
From explosions, spillages, fires etc from
storage, handling, use or production of
hazardous substances
Yes Due to failure of plant and equipment
8.2 From any other causes No Not Applicable
8.3
Could the project be affected by natural
disasters causing environmental damage e.g.
floods, earthquakes, landslides, cloudburst
etc)?
Yes
Earthquake
The IPS-1 site lies in Seismic Zone V and IPS-2 site lies in
Seismic Zone IV. IPS-4 and IPS-5 sites lie in Seismic Zone
III & II respectively. Therefore, all construction, design
and other features of the project at these sites that can be
impacted due to earthquakes will be as per earthquake
sensitive designs and construction
Floods
The project areas are unlikely to be prone to flooding.
9. Factors which should be considered (such as consequential development) which could lead to
environmental effects or the potential for cumulative impacts with other existing or planned
activities in the locality
S. No. Information/Checklist confirmation Yes / No? Details thereof (with approximate quantities/ rates,
wherever possible) with source of information data
9.1
Lead to development of supporting facilities,
ancillary development or development
stimulated by the project which could have
impact on the environment e.g.: supporting
infrastructure (roads, power supply, waste or
waste water treatment, etc.) housing
development extractive industries supply
industries, (other)
No
The project is a closed system comprising two licensed
underground tanks of 20m3 storage capacity each at the
respective stations and a pumping system for boosting the
pressure of the crude oil inside the pipeline that is required
to increase the flow in the pipeline as mentioned above.
9.2 Lead to after-use of the site, which could have
an impact on the environment No
Not likely, further the site is likely to be used for the
existing activities well into the foreseeable future.
9.3 Set a precedent for later developments No Not Applicable
9.4
Have cumulative effects due to proximity to
other existing or planned projects with similar
effects
No
There are no related or similar structures nearby such as
pipelines or storages others than those operated by M/s
HPCL-Mittal Pipelines Ltd
III. Environmental Sensitivity
S.
No. Areas
Name /
Identity
Aerial Distance (within 10 km) of the proposed project location
boundary
1
Areas protected under
international conventions,
national or local legislation for
their ecological, landscape,
cultural or other related value
No
None identified. Please refer Annexure-2.
Our understanding of the situation is that the nearest protected area including
wildlife sanctuary is more than 10 km away from each of the IPS-1, IPS-2,
IPS-3, IPS-4 & IPS-5 locations respectively.
2 Areas which are important or No IPS-1 IPS-2 IPS-4 IPS-5 IPS-3
M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 15
S.
No. Areas
Name /
Identity
Aerial Distance (within 10 km) of the proposed project location
boundary
sensitive for ecological
reasons - Wetlands,
watercourses or other water
bodies, coastal zone,
biospheres, mountains, forests
Wetlands: No
Wetlands are
present near
the area,
Watercourses
or other water
bodies: The
water bodies
present near
the area are
given as
follows:
River:
Khari River,
~1.92 km in
South - West,
Pond:
Govindpar,
~4.3km in
South - West
direction,
Jadavas,
~13.97 km in
East
Coastal Zone:
No, not present
within 10 km of
the area
Biosphere:
No, not present
within 10 km of
the area
Mountains:
No, not present
within 10 km of
the area
Forests:
No, Reserved
Forest not
present within
10 km of the
area. However,
Social Forestry
is present in
the ROW of SH-
51
Wetlands: No
Wetlands are
present near
the area,
Watercourses
or other water
bodies: The
water bodies
present near
the area are
given as
follows:
River:
Banas River,
~13 km in East,
Pond:
Juna Raviyana,
~1km in South
direction,
Two ponds in
Village Khoda,
~1.65 km in
North and ~3
km in North-
West direction,
Raiya, ~6.6 km
in West of
North-West
direction
Deodar, ~12.37
km in West
direction,
Sanodar, ~10
km in West
direction,
Zalmor, ~3km
in West
direction.
Coastal Zone:
No, not present
within 10 km of
the area
Biosphere:
No, not present
within 10 km of
the area
Mountains:
No, not present
within 10 km of
the area
Forests:
No, Reserved
Wetlands: No
Wetlands are
present near
the area,
Watercourses
or other water
bodies: The
water bodies
present near
the area are
given as
follows:
River:
No, not present
within 10 km of
the area
Pond:
No, not present
within 10 km of
the area
Coastal Zone:
No, not present
within 10 km of
the area
Biosphere:
No, not present
within 10 km of
the area
Mountains:
No, not present
within 10 km of
the area
Forests:
No, Reserved
Forest not
present within
10 km of the
area. However,
Social Forestry
is present in
the ROW of SH-
58
Wetlands: No
Wetlands are
present near
the area,
Watercourses
or other water
bodies: The
water bodies
present near
the area are
given as
follows:
River:
No, not present
within 10 km of
the area
Pond:
One pond in
Shri
Dungargarh,
~9.26 km in
South direction
Coastal Zone:
No, not present
within 10 km of
the area
Biosphere:
No, not present
within 10 km of
the area
Mountains:
No, not present
within 10 km of
the area
Forests:
No, Reserved
Forest not
present within
10 km of the
area. However,
Social Forestry
is present in the
ROW of NH-11
Wetlands: No
Wetlands are
present near
the area,
Watercourses
or other water
bodies: The
water bodies
present near
the area are
given as
follows:
River:
Sukhri River,
~3 km in
North-North
East,
Pond:
No, not present
within 10 km of
the area
Coastal Zone:
No, not present
within 10 km of
the area
Biosphere:
No, not present
within 10 km of
the area
Mountains:
No, not present
within 10 km of
the area
Forests:
No, Reserved
Forest not
present within
10 km of the
area. However,
Social Forestry
is present in
the ROW of
SH-16
M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 16
S.
No. Areas
Name /
Identity
Aerial Distance (within 10 km) of the proposed project location
boundary
Forest not
present within
10 km of the
area. However,
Social Forestry
is present in
the ROW of SH-
72
3
Areas used by protected,
important or sensitive species
of flora or fauna for breeding,
nesting, foraging, resting,
over wintering, migration
No None identified
4 Inland, coastal, marine or
underground waters Yes
There is no costal and marine water present at these sites and within the 10 km of
the area,
Information about the water bodies is presented in Section 2 of Environmental
Sensitivity,
Groundwater is present at the site and will be used for the project after due
clearance from the CGWA
5 State, National boundaries No Not present. Please refer Annexure-2
6
Routes or facilities used by the
public for access to recreation
or other tourist, pilgrim areas
No Routes:
IPS-1 IPS-2 IPS-3 IPS-4 IPS-5
State Highway-
51 (SH-51),
1.25 km in
West direction,
National
Highway-15
(NH-15), 4.82
km in South
direction
No such route
identified.
National
Highway 15 can
be used by the
Tourists and
Pilgrims
heading
towards Mount
Abu and Ambaji
Temple. But
these areas are
typically not
accessed using
the road near
the project area
State Highway-72
(SH-72), 1.15 km
in North direction,
National Highway-
27 (NH-27), 3.85
km in East
direction
No such route
identified.
National Highway
27 can be used by
the Tourists and
Pilgrims heading
towards Mount
Abu and Ambaji
Temple. But these
areas are typically
not accessed
using the road
near the project
area
State Highway-
16 (SH-16), 9.89
km in North
direction,
State Highway-
31 (SH-31),
20.81 km in East
direction
No such route
identified. State
Highway 31 can
be used by the
Tourists and
Pilgrims heading
towards Mount
Abu and Ambaji
Temple. But
these areas are
typically not
accessed using
the road near
the project area
State
Highway-58
(SH-58),
1.15 km in
South
direction,
National
Highway-65
(NH-65),
12.1 km in
East
direction
No such
route
identified.
National
Highway 65
can be used
by the
Tourists and
Pilgrims
heading
towards
Karni Mata
Temple. But
these areas
are typically
not
accessed
using the
State Highway-
6 (SH-6), 8.91
km in South -
East direction,
National
Highway-11
(NH-11), 9.75
km in South
direction
No such route
identified.
National
Highway 11
can be used by
the Tourists
and Pilgrims
heading
towards Karni
Mata Temple.
But these areas
are typically
not accessed
using the road
near the
project area
M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 17
S.
No. Areas
Name /
Identity
Aerial Distance (within 10 km) of the proposed project location
boundary
road near
the project
area
7 Defense installations No -
8 Densely populated or built-up
area Yes
IPS-1 IPS-2 IPS-4 IPS-5 IPS-3
Rapar ~ 14 km
in north –
northwest
direction,
Bhachau, ~37
km in west -
southwest
direction
Deodar, ~12 km
in west direction,
Deesa, ~31 km in
North-East
direction
Osiyan, ~19 km
in northwest
direction,
Jodhpur, ~38
km in south
direction
Shri
Dungargarh,
~9 km in
south -
southeast
direction
Bhinmal ~ 25
km in south –
southwest
direction,
Jalore, ~27.5
km in
Northeast
direction
9
Areas occupied by sensitive
man-made land uses
(hospitals, schools, places of
worship, community facilities)
Yes
IPS-1 IPS-2 IPS-4 IPS-5 IPS-3
Such facilities
are present in
Rapar Town
Such facilities are
present in Deodar
Town
Such facilities
are present in
Jodhpur City
Such facilities
are present
in Shri
Dungargarh
Town
Such facilities
are present in
Bhinmal Town
10
Areas containing important,
high quality or scarce
resources (ground water
resources, surface resources,
forestry, agriculture, fisheries,
tourism, minerals)
Yes
IPS-1 IPS-2 IPS-4 IPS-5 IPS-3
There is no
scarcity of
ground water in
the area.
Please refer
Annexure
Ground water
resources are
scarce in the area
and therefore the
area is considered
over-exploited
from the ground
water angle.
Please refer
Annexure .
Ground water
resources are
scarce in the
area and
therefore the
area is
considered over-
exploited from
the ground
water angle.
Please refer
Annexure
Ground
water
resources
are scarce in
the area and
therefore the
area is
considered
over-
exploited
from the
ground
water angle.
Please refer
Annexure
Ground water
resources are
scarce in the
area and
therefore the
area is
considered
over-exploited
from the
ground water
angle. Please
refer
Annexure
11
Areas already subjected to
pollution or environmental
damage. (Those where
existing legal environmental
standards are exceeded)
No
IPS-1 IPS-2 IPS-4 IPS-5 IPS-3
No such areas
identified.
Distance to the
nearest
critically
polluted area
as per ENVIS is
Ahmedabad,
~200 km in
East -
Southeast
direction.
No such areas
identified.
Distance to the
nearest critically
polluted area as
per ENVIS is
Ahmedabad,
~135 km in
South-East
direction.
No such areas
identified.
Distance to the
nearest critically
polluted area as
per ENVIS is
Jodhpur, ~37
km in South
direction.
No such
areas
identified.
Distance to
the nearest
critically
polluted area
as per ENVIS
is Jodhpur,
~232 km in
South –
Southwest
direction.
No such areas
identified.
Distance to the
nearest
critically
polluted area
as per ENVIS
is Pali, ~107
km in North-
East direction.
12 Areas susceptible to natural
hazard which could cause the Yes The study areas are susceptible to earthquakes. Please read S. No. 8.3
M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 18
S.
No. Areas
Name /
Identity
Aerial Distance (within 10 km) of the proposed project location
boundary
project to present
environmental problems
(earthquakes, subsidence,
landslides, erosion, flooding or
extreme or adverse climatic
conditions)
DECLARATION:
“I hereby give an undertaking that the data and information given in the application and enclosures are true to the best
of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false
or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our
risk and cost”.
Date:18.11.2015
Place: NOIDA Signature of the applicant with full name and address
Name : Prodip Kumar Biswas
Designation : AGM - Pipeline
Address : HPCL – Mittal Pipelines Limited,
INOX Towers,
Plot No. 17, Sector – 16A,
NOIDA – 201301,
Uttar Pradesh.
M/S HPCL-MITTAL PIPELINES LTD
CAPACITY EXPANSION OF MUNDRA – BATHINDA
CRUDE OIL PIPELINE PROPOSED TERMS OF REFERENCES
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 19
2 PROPOSED TERMS OF REFERENCE
The proposed terms of reference are suggested in
Table 2-1: Terms of Reference for preparing EIA Report
S. No. Proposed Terms of Reference
1. Justification of the project
2. Promoters and their background
3. Regulatory framework
4. A map indicating location of the project and distance from severely polluted area
5. Project location and plant layout
6. Infrastructure facilities including power sources
7. Total cost of the project along with total capital cost and recurring cost/annum for environmental pollution control measures.
8. Project site location along with site map of 10 km area and site details providing
various industries, surface water bodies, forests etc, along with landuse around 5 or 10 kms of the study area
9. Location of National Park/Wild life sanctuary/Reserve Forest within 10 km radius of the project.
10. Details of the total land and break-up of the land use for green belt and other
uses.
11. List of products along with the production capacities and list of solvents and its recovery plan
12. Detailed list of raw materials required and source, mode of storage and transportation
13. Manufacturing process details along with the chemical reactions and process flow chart.
14. Action plan for the safe transportation of raw material required
15. Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall is necessary.
16. Ambient air quality monitoring at 6 locations within the study area of 5 km., aerial coverage from project site as per NAAQES notified on 16th September,
2009. Location of one AAQMS in downwind direction.
17. One season site-specific micro-meteorological data covering temperature, relative humidity, hourly wind speed and direction and rainfall.
Twice weekly AAQ data (except monsoon) for PM2.5, PM10, SO2 and NOx at five
stations. CO, VOC, HC should be collected five times during the study at these
stations.
The monitoring stations should take into account the pre-dominant wind direction,
population zone and sensitive receptors including reserved forests.
Data for surface water, groundwater and noise monitoring should also be included.
18. Air pollution control measures proposed for the effective control of gaseous emissions within permissible limits.
M/S HPCL-MITTAL PIPELINES LTD
CAPACITY EXPANSION OF MUNDRA – BATHINDA
CRUDE OIL PIPELINE PROPOSED TERMS OF REFERENCES
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 20
S. No. Proposed Terms of Reference
19. An action plan to control and monitor secondary fugitive emissions
20. Determination of atmospheric inversion level and assessment of ground level
concentration of pollutants from the stack emission based on site-specific
meteorological features. Air quality modelling for proposed expansion.
21. Ground water monitoring at 6 locations should be carried out. Geological features and Geo-hydrological status of the study area and ecological status (Terrestrial and Aquatic).
22. The details of solid and hazardous wastes generation, storage, utilization and disposal particularly related to the hazardous waste calorific value of hazardous
waste and detailed characteristic of the hazardous waste.
23. Precautions to be taken during storage and transportation of hazardous chemicals should be clearly mentioned and incorporated
24. Details of landfill alongwith design details as per CPCB guidelines. Location of
secured land fill / TSDF.
25. Authorization/Membership for the disposal of solid/hazardous waste in TSDF.
26. Risk assessment for storage, handling, transportation of crude and any other
hazardous material being handled. Action Plan for implementing the recommendations of the risk assessment.
27. An action plan to develop green belt
28. Action plan for rainwater harvesting measures at plant site should be included to harvest rainwater from the roof tops and storm water drains to recharge the
ground water.
29. Occupational health of the workers needs elaboration including evaluation of noise, heat, illumination, dust, any other chemicals, metals being suspected in
environment and going into body of workers either through inhalation, ingestion or
through skin absorption and steps taken to avoid musculo-skeletal disorders
(MSD), backache, pain in minor and major joints, fatigue etc. Occupational
hazards specific pre-placement and periodical monitoring should be carried out.
30. Socio-economic development activities, with an Action Plan for implementing
future CSR activities with schedule and budget
31. Detailed Environment management Plan (EMP) with specific reference to details of air pollution control system, water & wastewater management, monitoring
frequency, responsibility and time bound implementation plan for mitigation measure should be provided.
32. EMP should include the concept of waste-minimization, recycle / reuse / recover
techniques, Energy conservation, and natural resource conservation.
33. Any litigation pending against the project and/or any direction/order passed by
any Court of Law against the project, if so, details thereof.
M/S HPCL-MITTAL PIPELINES LTD
CAPACITY EXPANSION OF MUNDRA – BATHINDA
CRUDE OIL PIPELINE ANNEXURE
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 21
ANNEXURES
M/S HPCL-MITTAL PIPELINES LTD
CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL
PIPELINE ANNEXURE
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 22
Annexure 1: Pipeline Route Map
M/S HPCL-MITTAL PIPELINES LTD
CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL
PIPELINE ANNEXURE
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 23
Annexure 2: Topography of IPS-1, IPS-2, IPS-3, IPS-4 & IPS-5 locations and areas within 10 km radius showing Roads, Adjacent localities, Forests, Water bodies, Protected Areas, State & National Boundaries (if any)
1. IPS-1, Dedarva
10 Km
M/S HPCL-MITTAL PIPELINES LTD
CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL
PIPELINE ANNEXURE
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 24
2. IPS-2, Juna Raviyana
10 Km
M/S HPCL-MITTAL PIPELINES LTD
CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL
PIPELINE ANNEXURE
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 25
3. IPS-3, Dhansa
10 Km
M/S HPCL-MITTAL PIPELINES LTD
CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL
PIPELINE ANNEXURE
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 26
4. IPS-4, Jud
10 Km
M/S HPCL-MITTAL PIPELINES LTD
CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL
PIPELINE ANNEXURE
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 27
5. IPS-5, Shri Dungargarh
10 Km
M/S HPCL-MITTAL PIPELINES LTD
CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL
PIPELINE ANNEXURE
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 28
Annexure 3: CGWA Categorization of Talukas .
A. Gujarat
M/S HPCL-MITTAL PIPELINES LTD
CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL
PIPELINE ANNEXURE
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 29
B. Rajasthan
M/S HPCL-MITTAL PIPELINES LTD
CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL
PIPELINE ANNEXURE
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 30
M/S HPCL-MITTAL PIPELINES LTD
CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL
PIPELINE ANNEXURE
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 31
M/S HPCL-MITTAL PIPELINES LTD
CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL
PIPELINE ANNEXURE
M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 32
Annexure 4: Hazardous Waste – Type, Mode and Disposal
The hazardous waste listing is provided in the following Annexure Table 1.
Annexure Table 1: Hazardous Wastes for each pumping station, with Type, Mode and Disposal
S. No. Items
Category
as per HW
Rules
Unit Quantity
Treatment /
Disposal
Method
1 Pigging Waste 3.3 MT/ month 0.5 TSDF
2
Sludge from Tank
Cleaning, used Filter
Elements
3.3 Tons / 5 Years 2 TSDF
3 Used Lube Oil 5.1 MT/year 2 Authorised
Recyclers
4
Used Pig
Cups/Discarded
Containers/Barrels
33.3 Nos./year
16 pig cups
5 Discarded
Containers/Barrels
TSDF