HOOSIER HEARTLAND HIGHWAY
Public Information Meeting – August 27, 2009
STATE ROAD 25, SEGMENT 2From 0.42 mile east of Tippecanoe/Carroll County line
to 0.20 mile east of CR400WLength of 8.46 miles with 9 Bridges
INDOT DESIGN CONSULTANT:Bernardin Lochmueller & Associates, Inc.
Jeff Whitaker, P.E.
Section 2: Central Segment
Current Design Status Road & Bridge Design - 50%
Complete R/W Engineering – 50% Complete
Section 2: Central Segment Work Schedule
Hydraulic Review & Grade Review(Completed 2007)
Context Sensitive Solution Design (Completed August 28, 2008)
Preliminary Field Check of Road & Bridge (February 23, 2009)
Public Information Meeting (August 27, 2009)
Design Approval (September 2009)
Section 2: Central Segment Right-of-Way Schedule
R/W Engineering & Acquisition (2008-2011)
90 Parcels of Property 26 Relocation R/W Appraising
(Oct/Nov 2009-April 2010) Property Information
Construction Schedule Phase 2A - (November 2010- 2012) Phase 2B – (March 2011-2013) Phase 2C – (December 2011-2013) Phase 2D – (October 2011-2013)
Section 2: Central Segment
Alignment Issues: Alignment was shifted on SR 25 and Connector
Roads to avoid Environmental Sensitive Areas Alignment shifted on SR 218 because of an at-
grade Railroad Crossing Alignment shifted on Connector Road between
the New SR 218 and Existing SR 218 Robinson Branch Bridge Added:
Because of Environmental Stream Impacts & Wetland Seeps
Upstream Bridge Creek Bridge Added: Because of hydraulics & cost savings
Section 2: Central Segment
Main Street Access Local Officials Requested – Main Street
Access Revised Improve Entrance into Delphi Signature Bridge for the Monon Trail
Section 2: Central Segment
Context Sensitive Solutions - Deer Creek Valley Rural Historic District
Committee Stakeholders Total of 4 Meetings, Last Meeting August 28, 2008 Context Sensitive Design Solutions
Texturing & Coloring of the Retaining Walls & Bridge Piers
Shape of Bridge Piers Type of Bridge Railing Type of Landscaping Type of Lighting at Main Street
Section 2: Central Segment
HOOSIER HEARTLAND HIGHWAY
Thank You For ComingQuestions Contact:
Aimee Kindred, Public Involvement DirectorOffice: (317)234-4938Mobile: (317)517-2166