GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software TEM Power Supply

Post on 11-Jan-2016

25 views 0 download

description

Gamma-ray Large Area Space Telescope. GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software TEM Power Supply Part 1 Gunther Haller Stanford Linear Accelerator Center Manager, Electronics, DAQ & FSW LAT Chief Electronics Engineer haller@slac.stanford.edu - PowerPoint PPT Presentation

Transcript of GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software TEM Power Supply

GLAST LAT Project Tower Power Supply Review Sept 22, 2003

Gunther Haller Part 1, Version 3 1

GLAST Large Area Telescope:GLAST Large Area Telescope:

Electronics, Data Acquisition & Flight Software TEM Power SupplyPart 1

Gunther HallerStanford Linear Accelerator CenterManager, Electronics, DAQ & FSWLAT Chief Electronics Engineer

haller@slac.stanford.edu(650) 926-4257

Gamma-ray Large Gamma-ray Large Area Space Area Space TelescopeTelescope

GLAST LAT Project Tower Power Supply Review Sept 22, 2003

Gunther Haller Part 1, Version 3 2

LAT Electronics PhysicalLAT Electronics Physical

16 Tower Electronics Modules– DAQ electronics module (DAQ-EM)– Power-supplies for tower electronics

* Primary & Secondary Units shown in one chassis

ACD

spare

EPU-3

EPU-2EPU-1

spare spare

Pwr Dist. Box

GASU

spare

spare

SIU-P SIU-R

3 Event-Processor Units (2+1 spare)

– Event processing CPU– LAT Communication Board (LCB)– Storage Interface Board (SIB)Spacecraft Interface Unit

– Storage Interface Board (SIB): EEPROM

SC MIL1553 control & data

– LAT control CPU– LAT Communication

Board (LCB): LAT command and data interface

Power-Distribution Unit (PDU)*

– Spacecraft interface, power

– LAT power distribution

– LAT health monitoring

Global-Trigger/ACD-EM/Signal-Distribution (GAS) Unit*

TKR

CAL

TKR Front-End Electronics (MCM)

ACD Front-End Electronics (FREE)

CAL Front-End Electronics (AFEE)

GLAST LAT Project Tower Power Supply Review Sept 22, 2003

Gunther Haller Part 1, Version 3 3

LAT Power DistributionLAT Power Distribution

ACD

ACD

ACD

PDUBoard P

EPUP0

SC MainFeed P

0 1 11

EPUP1

EPUR

SIUR

SIUP

TEMDAQ

CAL

TKR

Power Distribution

PDUBoard R

TEMDAQ

CAL

TKR

TEMDAQ

CAL

TKR

TEMDAQ

CAL

TKR

SC SIU RFeed

PDUPrimeRedundant

SC SIU PFeed

SC MainFeed R

GASUDAQ P

GASUDAQ R

ACD PSP

ACD PSR

GASUTowerPS

TEM0

TowerPS

TowerPS

TowerPS

TEM1

TEM14

TEM15

Power Distribution

• SIU’s are powered directly by spacecraft on dedicated feeds

• Rest of LAT electronics is powered via SC main feed to PDU

– Prime and redundant SC feeds connected to prime and redundant PDU circuits

• PDU controls power to towers, to GASU, and to EPU’s

– Either PDU circuit can supply power to clients

• GASU switches power to ACD

– Prime and redundant GASU circuit can supply power to ACD

• TEM’s switch power to TKR/CAL

– No redundancy in tower power system

• Heater power circuit not shown

GLAST LAT Project Tower Power Supply Review Sept 22, 2003

Gunther Haller Part 1, Version 3 4

RequirementsRequirements

• Requirements are in LAT-SS-01281• Supply power to Calorimeter, Tracker, TEM-DAQ systems

– Main drivers are• Low output noise, down to 100 uV RMS, 1 mV p-p

– Powers input amplifiers of CAL and TKR front-end electronics

• Low output voltage, down to 1.5 V– TKR input amplifier runs of 1.5V to meet power/thermal

requirements for 850k channels

• High overall efficiency– Total LAT power limited, also thermal limits because of

radiator area

• Adjustable high-voltage supply up to 150V– Silicon strip TKR detectors (up to 150V) and CAL Si-

diodes (up to 100V) need remotely adjustable depletion voltages

GLAST LAT Project Tower Power Supply Review Sept 22, 2003

Gunther Haller Part 1, Version 3 5

Detailed RequirementsDetailed Requirements

• See LAT-SS-1281,

(display the requirement pages in that document for discussion)

GLAST LAT Project Tower Power Supply Review Sept 22, 2003

Gunther Haller Part 1, Version 3 6

Tower Power Supply ModuleTower Power Supply Module

Tracker Voltages

Ana-1.5V-A (~1A)Ana-1.5V-B (~1A)Ana-2.5V-A (~1A)Ana-2.5V-B (~1A)Dig-2.5V-A (~0.3A)Dig-2.5V-B (~0.3A)HV-150Vadj- (~1uA)

Calorimeter Voltages

Ana-3.3V (~0.4A)Dig-3.3V (~0.96A)HV-100Vadj- (~1uA)

TEM-DAQ Voltages

Dig-3.3V-del (~0.6A)Dig-2.5V (~0.4 A)

Temp, 3.3V TEM-V Sensors

461-Filter28V from PDU

To PDU

TRK-Enable

CAL-Enable

HV-I MON

HV-I MON

I-Total MON

Currents are measured values

GLAST LAT Project Tower Power Supply Review Sept 22, 2003

Gunther Haller Part 1, Version 3 7

Tracker ElectronicsTracker Electronics

• TKR sub-system electronics • Si-Strip Detectors• 24 GTFE (GLAST Tracker Front-End) ASICs (1,536 signal channels)• 2 GTRC (GLAST Tracker Readout Controller) ASICs• MCM (Multi-Chip Module) • Flex-cables

• Total of 36 (4 sides, 9 each) MCM’s per tower power supply module– Power is routed via TEM DAQ board from TEM-PS to TKR

GTFE ASIC

GTRC ASIC

GLAST LAT Project Tower Power Supply Review Sept 22, 2003

Gunther Haller Part 1, Version 3 8

Calorimeter ElectronicsCalorimeter Electronics

• CAL sub-system electronics• Diodes• 48 GCFE (GLAST Calorimeter Front-End) ASICs• 4 GCRC (GLAST Calorimeter Readout Controller) ASICs• AFEE (Analog Front-End Electronics) board

• Total of 4 (4 sides, 1 each) AFEE’s per tower power supply module– Power is routed via TEM DAQ board from TEM-PS to CAL

GCFE ASIC

GCRC ASIC

GLAST LAT Project Tower Power Supply Review Sept 22, 2003

Gunther Haller Part 1, Version 3 9

DAQ ElectronicsDAQ Electronics

• Tower Electronics Module DAQ board

• Total of 1 TEM DAQ per tower power supply module

GLAST LAT Project Tower Power Supply Review Sept 22, 2003

Gunther Haller Part 1, Version 3 10

InterfacesInterfaces

• Tower Power Supply interface via two connectors to– Power Distribution Unit

• Incoming 28V +/- 1V• Monitoring to PDU• For EGSE desire to be able to remotely adjust front-end

voltages– Tower Electronics Module

• Supply voltages to TKR, CAL, and TEM• HV currents and total current monitoring• Enable signals for CAL and TKR system• Analog set voltage for HV supplies

– LAT-SS-1281

GLAST LAT Project Tower Power Supply Review Sept 22, 2003

Gunther Haller Part 1, Version 3 11

EnclosureEnclosure

TEM – PSU StackTower Electronics Module

PSU

GLAST LAT Project Tower Power Supply Review Sept 22, 2003

Gunther Haller Part 1, Version 3 12

DevelopmentDevelopment

• When SLAC electronics group started getting involved in LAT electronics (at approval of project)– Efficiency of power supplies of tower was supposed to be about

70% overall to meet power numbers – Tried to get more power, but denied

• SC interface issue• Problem with getting rid of heat (radiator areas)

– Worked to even more optimizing CAL, TKR, DAQ power (ASIC’s and other components), • Reduced power supply efficiency required to 62% (still very

challenging, but that was it)• Standard solution with “catalog” 28V/3.3V DC/DC converter and linear

regulators were explored but not realistic– At tower load of ~25W, needed at least 40W (at 3.3V!) converter,

(no 1.5V or 2.5V converter available at that time)• At LAT load: efficiency is 65% to 70%. just for 28->3.3V part• Need to generate 2.5V and 1.5V via linear regulators from 3.3V• Results in 47-50% overall efficiency (including HV supplies)• Over allocation: between 88W and 126W

GLAST LAT Project Tower Power Supply Review Sept 22, 2003

Gunther Haller Part 1, Version 3 13

Development (Con’t)Development (Con’t)

• First solution– Pursued full-custom vendor design

• Proof-of-principle prototype was designed and built, based on synchronous rectification

• Measured 87% efficiency of 28V/1.5V supply!• Met power requirement (status at CDR)• Went out for bids (Responses came in after CDR)• Bid returned were not affordable, by a lot• Not a working solution

GLAST LAT Project Tower Power Supply Review Sept 22, 2003

Gunther Haller Part 1, Version 3 14

Development (Con’t)Development (Con’t)

• Beginning of 04 – International Rectifier proposed new Z-series converter, based on

synchronous rectification– 28V/3.3V converter with up to 82% efficiency at full load, great device

compared to others on the market– New Device (no flight heritage yet), assembly of two PC-boards and

controller hybrid

GLAST LAT Project Tower Power Supply Review Sept 22, 2003

Gunther Haller Part 1, Version 3 15

Development (Con’t)Development (Con’t)

– Needed to be optimized for LAT load (Z-series is optimized for 20A/3.3V (~82%), LAT only needs 40% of that -> efficiency drops considerably)

– Put contract in place late spring 03 (as back-up)– However still does not meet power allocation by > 30W– Prototypes to be delivered late Fall 03– On order, but cancelable (need to decide end of 9/03 with penalty of 10%)– Risk that calorimeter 3.3V analog is connected to DAQ TEM 3.3V, very hard to filter low frequency noise

from DAQ• Need to decide by end of 9/03 to avoid further penalty

GLAST LAT Project Tower Power Supply Review Sept 22, 2003

Gunther Haller Part 1, Version 3 16

Development (Con’t)Development (Con’t)

• Spring 03:• Surveyed commercial DC/DC converters and evaluated for potential

radiation performance (CMOS versus bipolar technology, IC feature sizes)

• Radiation tested several DC/DC integrated circuit devices at Legnaro and TAMU (in Summer 03)

• Selected MAX724/726 devices as base-line• Designed circuit board for low-voltage circuits using MAX726• Designed high-voltage circuit (all along needed to be full-custom

since nothing available as a catalog item)– Received also proof-of-principle HV design from vendor (at CDR)– Went out for bids– Was not affordable, by a lot– Got previous flight design from Art Ruitberg (GSFC)– Started new design at SLAC (Dieter Freytag), eliminating

transformers

GLAST LAT Project Tower Power Supply Review Sept 22, 2003

Gunther Haller Part 1, Version 3 17

Development (Con’t)Development (Con’t)

• Designed/simulated high-voltage circuit by 7/03• Laid out HV-only PC board, fabricate/loaded by 8/03• Designed/laid-out/fabricated full TEM-PS by end of August 03• Started testing 9/03• Review 9/22/03