NCC LIMITEDNCC LIMITED“NCC HOUSE”| Madhapur | Hyderabad – 500 081 | India
Sep - 2017
Copyright © 2017 NCC Limited
PRESENTATION OUTLINE
• HISTORICAL BACKGROUND
• INDUSTRY OUTLOOK
• SEGMENTS
• FOCUSED GROWTH STRATEGY
Copyright © 2017 NCC Limited
HISTORICAL BACK GROUND
Copyright © 2017 NCC Limited
VISIONVISION
To be a world class construction and infrastructure enterprise committed to quality, timely completion,customer satisfaction, continuous learning and enhancement of stakeholders value.
MISSIONTo build a strong future ensuring increased returns to shareholders and enhanced support toassociates.
To adopt latest technologies in the field of engineering, construction, operation & maintenance ofinfrastructure projects.
To encourage innovation, professional integrity, up gradation of knowledge & skills of employees and
To be a responsible corporate citizen committed to social cause.
To encourage innovation, professional integrity, up gradation of knowledge & skills of employees anda safe working environment.
VALUESOpenness and Trust
Integrity & Reliability
Team Work & Collaboration
Commitment
Creativity
Copyright © 2017 NCC Limited
NCC – GROWING REPUTATION
• Fastest growing Construction Company in 2006• Fastest growing Construction Company in 2006
• Twelve research reports during last two years with BUY recommendationTwelve research reports during last two years with BUY recommendation
• A return of 95% to GDR holders in the first year
• Recognition by Forbes Asia as “ Best Under a Billion”
• Invitation by “World Economic Forum” to participate in their conference
Copyright © 2017 NCC Limited
Strong financial position and excellent credit rating
• Relatively low levels of long‐term bank loans
h l l d f k l–Short term loans primarily used for working capital requirements
• Able to borrow on good terms and at favourable rates due to strong standing in construction
industry and good track recordindustry and good track record
–Committed facility for issuance of bank guarantees and letters of credit
• High net worth enables NCC to compete for bigger projects with stringent pre‐qualification criteriag p gg p j g p q
• INR 3.0 billion commercial paper borrowing programme ‐ Rated as CRISIL A1. Indicates very
strong degree of safety with respect to timely payment of interest and principal on instruments
• Loan portfolio of INR 57 billion rated as CRISIAL A1 by CRISIL(1).
• Long term debt program of INR 4.0 billion rated as CRISIL A+/Negative by CRISIL.
(1) Subsidiary of Standard & Poor in India( ) y
Copyright © 2017 NCC Limited
Experienced and Professional Management
Experienced Experienced Management and Skilled Management and Skilled workforceworkforce
• 4,733 employees including 3.072 engineers• Focus on skills improvement through training
Major Investors Major Investors • Rakesh Jhunjunwala• DSP Blackrock
Cli R i iCli R i i
• Focus on timely execution has been rewarded by clients in the form of early completion bonuses Kalina‐Vakola flyover, Mumbai
Corporate Governance Corporate Governance
Client Recognition Client Recognition Kalina Vakola flyover, Mumbai National Academy of Construction, Hyderabad Times of India Print City, Navi Mumbai
• Board comprises of 14 directors, including 5 independent directors and 3 nominee directors• Nomination & Remuneration Committee/Audit Committee/Shareholder’s Grievance Committee/ Corporate Social
Responsibility Committee headed by independent directors
Select Awards and Accolades
2006: “Fastest Growing
Forbes Asia, 2005: The only
2010: Company’s AnnualReport and Accounts for
2010: Company’sAnnual Report and
Vishwakarma Award of CIDC,2016 For
National award for
One of the Best CFOs of India by
Construction Company in India”
2007: “2nd largest construction
Indian construction company to be One of the 200 "Best Under a Billion" listed
the year 2008‐09 hasbeen awarded Certificateof Merit the “ BestPresented Accounts andCorporate GovernanceDisclosures Awards
Accounts for the yearended 31st March,2009 have been“adjudged as the 2ndbest under the categoryInfrastructure &
Industry Doyen Award‐ A R Raju,MD
Best Professionally Managed Company
B t C t ti
excellence in Cost management for the year 2015 by the Institute of
the CIMA, R S Raju, 2016
Copyright © 2017 NCC Limited
construction company in India”
companies in Asia Pacific
2009” by the South AsianFederation ofAccountants(SAFA)
Construction Sector byICAI Awards forExcellence in FinancialReporting”
Best Construction Project‐ ESIC Gulbarga
Cost Accounts of India.
Experience, Size and Know‐how
NCC achieved significant scale to bid for and win
NCC amongst most experienced firms in industry
large contracts
Consolidated Revenues (Rs. Mn)Company rebranded as NCC
Rights Issue of Rs. 6 Bn2014
2011
Equity - investment by Blackstone
QIP Issue of $ 70 Mn2009
2007
Turnover crosses Rs. 10 Bn
GDR Issue of $ 120 Mn2005
2004-05
Turnover crosses Rs. 1 Bn
ISO 9001-2000 Certified2001
1994-95
NCC set up as partnership firm
IPO1992
1978
Copyright © 2017 NCC Limited
Company Snapshot( Mn)
Total Order Book: Rs. 219,090 Mn
• One of the largest Indian construction companies in terms of revenues
• Presence across buildings & housing, transportation, water & environment, irrigation, electrical, metals, mining, power and
l (As on Sep – 2017)railways• Well diversified operations having a foothold in every segment
of construction sector• Market capitalization: US$ 881.1 Mn as on Nov 13, 2017
7%
4%
1% 0%8%
Buildings
Roads
Water & Env &
(Source: BSE)
46%
Water & Env. & Railways
Electrical
Irrigation
5%
29%Power & Metals
Mining
Internationals
Copyright © 2017 NCC Limited
Company Snapshot
(as on Sep 30, 2017)Total Turnover: Rs. 35,830 Mn
4%
1% 0%
8%Buildings
46%
7%
4%Roads
Water & Env. & Railways
29%
Electrical
Irrigation
5%
Power & Metals
Mining
Internationals
Copyright © 2017 NCC Limited
Size & Scale
• Among the top 3 construction companies in India in terms of revenues • Our size and scale help us pre‐qualify for larger projects
N b f ffi I di bl ti ti i ti i j t bid• Number of offices across India enables active participation in project bids• Backed by strong execution teams, currently executing around 200 projects at various
locations• Demonstrated ability to bid for and win large projects
Lucknow Development Authority, Lucknow: Rs. 7.18 Bn.
UP Expressways Development Authority : Rs. 16.75 Bn.
Demonstrated ability to bid for and win large projects
Bangalore Metro Rail Corp., Bangalore: Rs. 5.09 Bn.
UP Avas Vikas Parishad : Rs. 5.25 Bn.
Telangana Drinking Water Supply : Rs 14 45 Bn Telangana Drinking Water Supply : Rs. 14.45 Bn.
HMWSSB, Hyderabad : Rs. 5.33 Bn.
Palamuru‐Ranga Reddy Lift Irrigation Scheme: Rs 13.78 Bn.
S i t d t E i K l P j t R 5 66 B Superintendent Engineer Kaleswaram Project: Rs 5.66 Bn.
INDUSTRY OUTLOOK
Copyright © 2017 NCC Limited
Executing Projects Across India & Overseas
LucknowNew Delhi
Dubai
HyderabadM b i
Ahmadabad Bhopal
Bhubaneswar
Kolkata
RanchiLucknowDubai
Muscat
Visakhapatnam
Banguluru
Mumbai
ChennaiKochi
Copyright © 2017 NCC Limited
SEGMENTS
Copyright © 2017 NCC Limited
Buildings &Buildings & Water &Water &InternationalInternational
• Buildings
R d
Buildings & Buildings & HousingHousing RoadsRoads Water & Water &
EnvironmentEnvironment IrrigationIrrigation
• Housing projects• Industrial
• Highways
• Bridges flyovers
• Transmission and distribution
• Dams
• Lift irrigation
• Water supply projects
ElectricalElectrical
• Roads
• Waterbuildings
• IT Parks • Shopping malls • Sports
• Bridges, flyovers and elevated corridors
• Realignment of existing
lines and sub‐stations
• Project electrification
• Lift irrigation
• Gravity irrigation
p j
• Treatment plants
• Underground complexes
• Hotels• Hospitals
existing highways and construction of bypasses
• System improvement projects
drainages
Power MetalsOil & Gas Mining
• BOP for thermal and hydro
• Oil and gas pipeline projects
• Tied up with POSCO E&C
• Overburden removalDi
visio
ns Railways
• Track Laying
• Signaling &Projects• Tunneling for
Hydro Electric Plants
• Refinery expansion
• EPC for steel plant projects
• Coal excavationNew
• Signaling & Communication
• Railway Siding
Diversified operating base across 11 divisions helps mitigate risk against a slowdown in any one division
Copyright © 2017 NCC Limited
Buildings & Housing, Roads, Oil & Gas
$ Construction spending for Urban infrastructure expected to amount to Rs. 267 bn(US$ 5.8 bn) in Eleventh Five year plan
Key drivers include growing Indian industry & economy, increasing urbanization and household growth
Industrial buildingsBuildings , Housing & Roads ( Mn)
ivision
s
Commercial buildings
Housing projects
IT parks and shopping mallsRevenues
busin
ess d
i IT parks and shopping malls
Sports complexes
Hospitals
NCC
’s key
Roads
Share % on turnover FY‐17
Copyright © 2017 NCC Limited
Buildings & Housing
Some of the Major Projects Executed are:
Copyright © 2017 NCC Limited
Buildings & Housing
PROJECT: GOVT. HOSPITAL, CHENNAIProject: Tuberculosis Research Center, Chennai
Scope : New patient care & clinical facility at TB Hospital, Chennai
Project: Apollo Hospital, BhubaneswarProject: Army Medical College, New Delhi
Copyright © 2017 NCC Limited
Buildings & Housing
Project: ESIC Medical College ‐Gulbargha, Karnataka
Buildings & Housing
Buildings & Housing
Buildings & Housing
Project: Wipro Technologies, Cochin
Scope : Superstructure & Civil Work for Software Dvlpt., Centre
Project: IDCO, Bhubaneswar
Scope : Software Complex (Fortune Towers)p p ( )
Project: Satyam School, Hyderabad.Project: Patni Computer, Mumbai
Scope : Civil works incl. survey, excavation, and finishing works.Scope : I.T.Centre at MIDC Knowledge Park, Airoll, Navi Mumbai
Copyright © 2017 NCC Limited
Buildings & Housing
Project: Delhi Devp. Authority, Navsaad Vihar Housing socity, Delhi.
Scope : Multi Storied apartments & Site development work.
Project: Army Welfare Housing org., Panchakula, New Delhi.
Scope : Accommodation for AWHO on part ‘A’ of Plot in sector‐20
Project: SBI, Mumbai.
Scope : 186 Officer’s Flats & 12 Guest Rooms at Mumbai
Project: Singapore Class Township, Pocharam, Hyderabad
Scope : 2080 Residential Flats (4floors X50X8 and 14flooresX10X4 )Scope : 186 Officer s Flats & 12 Guest Rooms at Mumbai. Scope : 2080 Residential Flats (4floors X50X8 and 14flooresX10X4.)
Copyright © 2017 NCC Limited
Buildings & Housing
Copyright © 2017 NCC Limited
Buildings & Housing
Sahara HomesIDA Green Wood ‐ Lucknow Sahara HomesIDA Green Wood ‐ Lucknow
DGMAP VIZAG MODEL BLOCK dDG MAP‐VIZAG – MODEL BLOCK J N T U – HYDERABAD ‐ Auditorium
Copyright © 2017 NCC Limited
Buildings & Housing
Copyright © 2017 NCC Limited
Buildings & Housing
Copyright © 2017 NCC Limited
Buildings & Housing
Copyright © 2017 NCC Limited
Buildings & Housing
Project: JMD, DelhiProject: KBH‐DOC, Chamrajnagar, Karnataka
Scope: Commercial Complex at Gurgaoni.j , j g ,
Scope: Construction of District Office Complex
Project: NAC Hyderabad (Rewared received for early completionProject: Cabinet Secretariat Building, New Delhi
Project: NAC, Hyderabad (Rewared received for early completion
Scope: Building, Infrastructure & ancillary structure..
Copyright © 2017 NCC Limited
Buildings & Housing
Project: SAAP Gachibowli HyderabadProject: SAAP Gachibowli, Hyderabad
Scope: Accommodation fo9r Athletics. Project: District Office Complex ‐ Haveri
Copyright © 2017 NCC Limited
Project: NBCC – NETAJI NAGAR, NEW DELHI
Buildings & Housing
Delhi Metro Bhavan, New Delhi NIT, Warangal, AP
Project: Satyam HydrabadTimes of India ‐ Mumbai
Project: Satyam, Hydrabad
Scope: Development Centre at Bachupalli.Copyright © 2017 NCC Limited
Buildings & Housing
NIT‐Silchar – Block AEIL‐DATA CENTRE‐MANESAR
Mahindra ‐ SatyamMRF ‐ SADASIVPET
Copyright © 2017 NCC Limited
Buildings & Housing
KSRTC‐MYSORE – Sathgalli Bus Stand KSRTC‐MYSORE – Illwalai Bus Stand
KSRTC‐MYSORE – Kuvempu Bus Stand PWD‐ Bowring Hospital
Copyright © 2017 NCC Limited
Buildings & Housing
NIT A t l B H t lNIT‐Agartala – Boys Hostel
ICFAI-Agartala-Hostel –A,B,C & D BlocksNIT-SILCHAR
Copyright © 2017 NCC Limited
Buildings & Housing
Copyright © 2017 NCC Limited
SYMBOSIS INTERNATIONAL SCHOOL
Buildings & HousingNIT - AGARTALA
IISER, CPWD
Copyright © 2017 NCC Limited
Buildings & Housing
Copyright © 2017 NCC Limited
Buildings & Stadiums
Khelgovn‐Ranchi
Copyright © 2017 NCC Limited
Buildings & Stadiums
Project: GMC Balayogi Stadium, Gachibowli, Hyderabad
Scope Construction of Athletic Stadium for National Games 2002
Project: National Games Stadium, Saroornager, Hyderabad
Scope Indoor Stadium for Gymnastics & Wrestling and for basketballScope: Construction of Athletic Stadium for National Games 2002 Scope: Indoor Stadium for Gymnastics & Wrestling and for basketball
Project: National Games Stadium Yousufguda Hyderabad S i i P l t G hib li H d b dProject: National Games Stadium, Yousufguda, Hyderabad
Scope: Indoor Stadium for Basketball & volleyball
Swimming Pool at Gachibowli, Hyderabad
Copyright © 2017 NCC Limited
Buildings & Stadiums
Project: Rajeev Gandhi International Cricket Stadium, Uppal, Hyderabad
Scope: Stadium with 45,000 Seating capacity & other facilities
Copyright © 2017 NCC Limited
Buildings & Stadiums
Project: Raipur Cricket Stadium
Scope: Stadium with 60,000 Seating capacity & other facilitiesCopyright © 2017 NCC Limited
Buildings & Stadiums
DELHI UNIVERSITY STADIUMS –COMMONWEALTH GAMES - DELHI 2010
Copyright © 2017 NCC Limited
Buildings & Stadiums
Copyright © 2017 NCC Limited
Buildings & Housing
Project: Shilpakalavedika, HyderabadScope: Multistoried Build‐Award received as outstanding
Project: Indira Gandhi International Airport – New DelhiScope: Design and Reconstruction of Terminal IAScope: Multistoried Build Award received as outstanding
structure ‐ 2002Scope: Design and Reconstruction of Terminal IA
P j t ISTA H t l H d b dProject: ISTA Hotel, Hyderabad
Scope: 5 Star Hotel & Swimming PoolProject: Volkaswagen ‐ Pune
Copyright © 2017 NCC Limited
Buildings & Housing
The Oberoi and Trident HyderabadThe Oberoi and Trident, Hyderabad
Copyright © 2017 NCC LimitedADANI SHANTIGRAM, AHMEDABAD
Industrial Buildings Structures
Zuari Cements Limited, Yerraguntla, Cuddapah, A.PHDPE Unit For Petro Chemicals Expansion Project, Pata, Auraiya
Cement Plant at Kurnool , Andhra Pradesh Gautami Power Plant at Peddhapuram, East Godavari Dist, APCopyright © 2017 NCC Limited
Industrial Buildings StructuresPosco-Pune
Copyright © 2017 NCC Limited
Industrial Buildings Structures
Copyright © 2017 NCC Limited
Industrial Buildings Structures
Copyright © 2017 NCC Limited
Buildings Structures ‐ Runways
Copyright © 2017 NCC Limited
Buildings & HousingEMBASSY of India Complex ‐ Constn.of the Embassy of Indian complex at Kathmandu 1,391.22EMBASSY of India Complex Constn.of the Embassy of Indian complex at Kathmandu 1,391.22 NBCC‐ ESIC medical college comprising of hospitals Medical and Nursing college hostels, Residential complex 6,944.50 AIIMS ‐ Patna ‐ Pkg. I ‐Constn.of Medical college and hostel complex at AIIMS Patna 1,574.96 AIIMS ‐ Bhopal ‐ Pkg. I‐Constn.of Medical college and hostel complex at AIIMS Bhopal 1,479.00 BRPNNL‐Constn. Of Vardhaman Institute of Medical Science at Pawapuri, Dist. Nalanda ‐ Bihar 5,270.74 M lti i lit h it l bld i bl k d A bl k Sikki (C l h it l) 1 212 60Mmultispeciality hospital bldg.mainblock and Annex block ‐ Sikkim(Ceepl hospital) 1,212.60 Design, construction of Sarayu apartments at Gomatinagar ‐ Lucknow (LDA‐Sarayu) 1,206.20 Delhi Urban Shelter improvement Board,EWS‐Constn of 4000 (G+4) EWS houses under JNNURM scheme 1,845.00 Karnataka Housing Board ‐ (Kengeri) ‐Constn.of highrise apartments UGD, water supply, roads drains & Compound wall at Valagerahally in Kengeri 2,446.70
CIDCO ‐ Belapur ‐ Mumbai ‐Design & Constn.of Elevated Viaduct between chainage to chainage Belapur sector 1,821.00 Allahabad Vikas Pradhikaran ,Allahabad‐Construction of 1200 nos. of Flats at Yamuna Vihar , Allahabad 2,844.10
Nalanda University, Rajgir, Bihar ‐ Construction of non resident building of Nalanda University campus, Academic & Admn buildings Phase I 4,350.80
Shillong International Centre‐Construction of Shillong International centre for Arts and culture at Shillong, Meghalaya. 1,263.30 g g g, g y , 63 30IIT Jodhpur‐Development of Permanent Campus for IIT Jodhpur(Phase I) at Karwar,NH‐65,Jodhpur 3,457.60 Engineering projects (India) Ltd., New Delhi ‐Construction of National Institute of Pharmaceutical education and Research campus (NIPER) at Guwahati, Assam. 1,475.00
Tamilnadu Housing Board,Annasalai,Chennai‐Construction of multistoried residential flats and office complex for ONGC,Chennai 1,949.40
Govt of Karnataka,P.W.P Dept‐Completion of balance works at Gulbarga Airport in Karnataka 854.62
CPWD ‐New Delhi,( IIT Delhi)‐Construction of Engg Block, IIT Delhi including water supply,sanitary,electrical works etc., 2,251.60
Hindustan Steel works, ESI Para medical ‐ Constn.of para medical&allied health science institute. 2,590.00 A l C l b it M d L k G h i "C l b it d & di di 1 000 00Ansal Celebrity Meadows ‐ Lucknow‐Group housing "Celebrity meadows & paradise diamong 1,000.00 OIIDC‐ Bhubaneswar ‐Construction of "Shakti Bhavan" complex at Bhubaneswar, Odhisha 819.30 LDA‐LUCKNOW‐ Construction of affordable group housing complex , EWS & LIG ‐Lucknow 7,184.80 UPRNNL (UPMP‐SAIFAI)‐Execution of Urban development master plan, Saifai 2,171.80 Construction of interstate bus Terminals, including external services at ISBT,Delhi 759.80
Copyright © 2017 NCC Limited
Buildings & HousingTNHB‐Construction of 1026 LIG Flats in Ambattur village(Stilt+19floors) 1,606.30 g ( ) ,TNHB‐Development of works such as roads, drains, culverts, bridge, sumps, pumproom and water supply and sewarage arrangements inTiruvallur district. 1,141.90
LDA‐Construction of "SHAN‐E‐AWADH" Commercial complex at Gomatati nagar Extension,Sector 7,Lucknow 4,789.50 Govt of India,Dept of Space, SVAB SHAR‐Sriharikota‐Civil,Structural,Architectural,Electrical,Airconditioning,and associated works of Shar 3,277.91 CPWD,Dhanbad ‐ISM DHANBAD‐construction of 120 qtrs (Stilt+15 storied) at ISM,Dhanbad,Jharkhand state. 1,226.80 U. P .Rajakiya Nirman Nigam Limited, ICS‐SAIFAI‐Constructionof International Cricket Stadium at Saifai,Etawah,U.P 2,816.90 UP Avas Vikas Parishad ‐ Lucknow (samajwadi awas yojana,)‐Construction of 2620 nos of Multistoried residential Flats at Sarayu Enclave,Lucknow 5,252.90
IIM,Raipur‐Development of Phase I Campus including buildings for IIM Raipur at Nayaraipur. 2,463.00 p p p g g p y pSikkim University, Gangtok, Sikkim‐Construction of Sikkim University campus Phase I‐Yangang, South Sikkim 1,064.50 CPWD, Tripura‐Up gradation of Agartala Govt Medical College, Tripura with super speciality facilities . 775.00 NBCC LODHI ROAD,Kidwainagar Pkg IV) ‐ Redevelopment of Kidwainagar (East) New Delhi, 5,629.90 Ansal Properties and infra ltd.,Paradise Diamond‐Design and constn.of group housing "Paradise Diamond"Lucknow 2,588.00 BDA‐Bangalore (Puttanna Kanagi Theatre)‐Constn of new Puttanna Kanagi Theatre at Jaya nagar Bangalore 2 522 70BDA Bangalore (Puttanna Kanagi Theatre) Constn of new Puttanna Kanagi Theatre at Jaya nagar,Bangalore 2,522.70 NIT‐Construction of 1500 capacity boys hostel at NIT,Agartala 1,524.30 Ministry of Defence‐Infrastructure Development Works at six locations in Arunachal Pradesh 1,876.60 Ministry of Defence‐Infrastructure Development Works at six locations in Arunachal Pradesh 773.10 Ministry of Defence‐Infrastructure Development Works at six locations in Arunachal Pradesh 1,580.30 Ministry of Defence Infrastructure Development Works at six locations in Arunachal Pradesh 1 332 40Ministry of Defence‐Infrastructure Development Works at six locations in Arunachal Pradesh 1,332.40 Ministry of Defence‐Infrastructure Development Works at six locations in Arunachal Pradesh 1,585.50 UP Hsg & Devt. Board (Mandola Vihar Ghajiabad) ‐Construction of multistoried (G+14 & G+16) 2 BHK, 2BHK + Study and 3 BHK residential flats,boundry wall,swimming pool,community centre etc., in mandola vihar yojana,Ghaziabad. 5,465.30
Ministry of Defence‐Improvement of Infrastructure for ALG Tawang in Arunachal pradesh 1,292.60 Ekana Sportz City Private Limited (I.C.S. Lucknow)‐Construction and Development of the International Cricket Stadium and Multi Purpose sports Complex in Lucknow 1,987.80
IGISCS‐Haldwani ‐Proposed International Sports Complex along with ancillary buildings, external development and all engineering services at Golapar,Haldwani, Naintal, Uttarakhand 1,727.90
Construction of 1000 Capacity Boys Hostal no 9 and new library Bldg at Nit‐Silchar 1,084.60
Copyright © 2017 NCC Limited
Chikmagalur Urban Development Authority‐Development of A.B.Vajpayee Residential Layout at Chickmagulur city 1,913.10 TG&D Corpn Ltd‐Execution of distribution strengthening works under APDRP scheme in 12 towns in Tirunelveli region. 746.30 TG&D Corpn Ltd‐Execution of distribution strengthening works under APDRP scheme in 14 towns in Trichy region. 1,090.92
Buildings & HousingTG&D Corpn Ltd‐Execution of distribution strengthening works in 7 towns of Erode region. 2,522.17 p g g g ,NBCC‐Redevelopment of kidwainagar(East) New Delhi, Construction of social structures, Type VI & Type VII quarters 4,900.00
Engineers India Ltd ,New Delhi ‐Composite works for setting of Rajiv Gandhi Institute of Petroleum Technology at Jais (UP) 2,933.36
UPHB‐LUCKNOW‐Construction of multi stored Residential flats in Bhagirathi Enclave, Lucknow 8,437.32 Central University of Jammu‐Construction of residential buildings for faculty, Directorate of distance education bldg for Central university of 729 72Jammu at Bangla(J&K) 729.72
HLL Life care Limited‐Construction of 300 bedded teaching hospital and medical colledge at Konni,Pathanamthitta District, Kerala 1,432.00
OPGC‐New construction and Renovation of existing township at IB Thermal Power station 1,302.30 KHSD & RP,Bangalore (GIMS ‐GULBARG)‐Construction of Gulbarga Institute of medical sceinces at Gulbarga 1,823.87 KHSD & RP, Bangalore (KIMS‐MADIKER)‐Construction of Kodagu Institute of medical sceinces at Madikeri 1,616.50 Public works,Ports and inland water Tpt. dept, Bangalore (BIMS‐BIDAR)‐Construction for upgradation of 300 to 750 beds teaching hospital to Bidar Institute of Medical Science at Bidar 959.50
Rashtriya Madhyamika Shiksha ‐Bagalkota‐A1‐Construction of Adarsha Vidyalas & Girls hostels at 4 locations in Karnataka Region 587.33
LDA C i f J l j ki S j l k 2 442 52LDA‐Construction of Janeswar enclave at janakipuram,Sector ‐ j, lucknow 2,442.52
Copyright © 2017 NCC Limited
Transportation
Some of the Major Projects Executed are:
Copyright © 2017 NCC Limited
Metro Rail
Copyright © 2017 NCC Limited
Railways
Metro Rail ‐ Bangalore
Project: Delhi Metro Rail Corporation Limited ‐ Delhi
Scope: Plinth casting with installation of rails in position for RC3Metro Rail ‐ Bangalore Scope: Plinth casting with installation of rails in position for RC3
Copyright © 2017 NCC Limited
Metro‐Rail
NMRCL‐Construction of NHAI Flyover ‐ orignating from Ujjawal Nagar on the North ‐South corridor of Nagapur Metro Rail Project toManish Nagar( NCC and C&C JV‐70%+30% of Rs 918.32 Million) 642.80
CMRL‐Construction of piles and pile caps for Elevated Viaduct & associated works for a stretch of about 3 KM at Tollgate at WIMCOnagar 944.20
BMRCL‐Construction of elevated structures,viaduct and 5 nos of Elevated Metro stations of Bangalore Metro Rail project, Phase 2. 5,088.60
NMRCL‐Design & Const.of Super structure of NH Road bridge of Metro rail project,Nagpur 2,375.60 MMDA‐MUMBAI‐Metro stations,elevated structures via duct works at Mumbai 2,498.59 CMRL‐CHENNAI‐ CMRL Project Phase‐I, Sidco, Alandur,Guindy 1,531.10
f b d ll b d ll d h k d h h d fNMRCL‐Construction of bridges, retaining walls, boundary walls and earth work in depot on North South Corridor of Nagpur Metro rail project 4,631.80
Copyright © 2017 NCC Limited
Roads
Project: Kalina‐Vakila Flyover rcd Bonus for early completion
Scope: Flyover on Maharastra Mumbai Highway (1427 mtrs in length)
Project: Britania Flyover at Ring Road, Lawrence Road, Delhi
Scope: Flyover and subway intersection at Britania ChowkScope: Flyover on Maharastra – Mumbai Highway (1427 mtrs in length) Scope: Flyover and subway intersection at Britania Chowk
Project: Bangalore Elevated Flyover
Scope: Elevated corridor for 28.78 km at B’lore & Maddur State Highway
Project: Lathur Flyover
Scope: Underpass cum Flyover at Sivaji Chouck, Lathur
Copyright © 2017 NCC Limited
Roads
Bangalore Elevated Tollway LimitedProject: Kovilpatti Flyover, Chennai
S C t f ROB b t K il tti & N lli t KM 94/2 & 91/4Scope: Const. of ROB between Kovilapatti & Nalli at KM 94/2 & 91/4
Bangalore Elevated Tollway Limited, Bangalore
Project: Bridge on River Sone (Longest bridge of GQ)
Scope: 4 Laning & strengthening between 110 & 140 KM (Sona Bridge)
Copyright © 2017 NCC Limited
Roads
Project: National Express Way No.1(Phase‐II of Ahmedabad‐Vadodra)
Scope: SI: Lane access controlled expressway (50km)
Project: Nagpur Flyover
Scope: Const. of ROB along with approaches at Km 1040/5 to 7
P j t 4 L i f B l M R d (SH 17) P j t ORR HYDERABADProject: 4 Laning of Bangalore – Mysore Road (SH‐17)
Scope: Bridge Culverts Road Over Bridge and Underpasses
Copyright © 2017 NCC Limited
Project: ORR ‐ HYDERABAD
Roads
Project: NHAI‐Six Laning of NH‐1 for 15 Kms. of Delhi Border to Samalkha section in Haryana state.
Project: Necklace Road under Buddha Purnima Project for Hyderabad Urban Development Authority, Hyderabad
Project: Construction of carriageway of ring road along with cross drainage works in Bangalore city
Project: AP‐Package between Vishakapatnam and Champavati river of NH‐5 for NHAI JV with Unitech Ltd., New Delhi
Copyright © 2017 NCC Limited
Roads
HGCL ‐ Kesara to Ghatkesar ‐ ORR ‐ II‐Constn.of access controlled expressway as outer ring road 3,937.46 Muncipal Corpn.‐Bhopal‐Habibganj ‐Constn.of four lane flyover at GAD square, two lane flyover at moti maszid and six lane ROB atHabibganj 1,029.31
RVNL ‐ Bhubaneswar (Package II)‐Road BED, 4 major bridges, Minor bridges, track linking 1,827.90 h b ( k ) d b d b d k l kRVNL ‐ Bhubaneswar (Package III)‐Road BED, 4 major bridges, Minor bridges, track linking 1,327.60
CCD & MC, Vijayawada‐4 Lane Access road in AP State Capital 2,155.50 ADC ‐ 8 Road construction (Package I of Phase I) works in Amaravati sustainable capital city Development project. 2,722.00 UP Expressway‐Development of Etawah to Kannauj (KM 115.500 to KM 172.500)Access Controlled Expressway (Green Field) project in the state of Uttar Pradesh. 15,836.00
MSRDCL "SWARGATE FLYOVER"‐Construction of Flyover, Vehicular underpass and pedestrian underpasses at swargate junction 1,084.30 Govt of Tripura‐Improvement of Urban North and South corridor for Agartala City in the State of Tripura under package I & Package II containing 2 lane flyover and long 2 lane stretch steel arch bridge across river. 2,499.50
HGCL ‐ Ghatkesar to Pedda Amberpet‐ORR‐III‐Constn.of access controlled expressway as outer ring road 3,554.18 The Muncipal Corporation of the City of Thane‐Design and construction of Flyovers at Meenatai Thakara Chowk,Almedia Chown and Sant Namdev Chowk in Thane (NCC‐J.Kumar‐SMC JV) NCC Share 40% of 2213.80 Million 885.60
Copyright © 2017 NCC Limited
Oil & Gas
Copyright © 2017 NCC Limited
Water & Environment and Railways
Water supply and sanitation projects expected to account for over Rs500bn(US$12.5 bn), in Eleventh Five Year plan
Increasing private sector participation and use of BOOT contracts to lead growth for private players
• Water supply projectsWater & Environment , Railways ( Mn)
Water supply projects
• Water treatment plants
• Underground drainage works
ivision
s Revenues
• Sewage treatment projects
• Railways
busin
ess d
iNCC
’s key
Share % on turnover FY‐17
Copyright © 2017 NCC Limited
Water & Environment
Some of the Major Projects Executed are:
Copyright © 2017 NCC Limited
Water & Environment
India Biggest water treatment plant Amberpet Hyderabad
Project: CMWSSB, Chennai
Scope: M S Pipe line of 2000mm dia & 1500mm dia Raw Water &India Biggest water treatment plant, Amberpet, Hyderabad Scope: M.S.Pipe line of 2000mm dia & 1500mm dia Raw Water & Clear water transmission pipe for 530 MLD Water treatment plant
Project: Krishna Drinking Water Supply Project Phase IMaharashtra Jeevan Pradhikaran Water Supply Scheme, Amaravathi.Project: Sanand.
Project: Krishna Drinking Water Supply Project‐Phase I
Scope: Manufac. Laying jointing testing and commiss. 2200 mm dia pipe
Copyright © 2017 NCC Limited
Water & Environment
Project: UGD Scheme, Bellary ‐ Karnataka
Scope: 15 MLD & 30 MLD sewage treatment plant, SWG/RCC pipelines.
Project: Kokarada, Amaravathi Dist ‐ Maharastra
Scope: Rural water supply for 156 villages in Daryapur, Anjangaon p g p p p
Project: V ValleyWater Supply Scheme, Dhanabad, Jatkhand
Project: V‐Valley
Scope: Civil works for 60 MLD waste water treatment plant
Copyright © 2017 NCC Limited
Water & Environment
FACCULATATIVE AERATED LAGOONS–339MLD STP AMBERPET HYDERABAD CLARIFLOCCULATOR AJMER KEKRIFACCULATATIVE AERATED LAGOONS 339MLD STP AMBERPET, HYDERABAD CLARIFLOCCULATOR ‐ AJMER‐KEKRI
STP BIO GAS GENERATORS –339MLD STP AMBERPET FLOATING BARGE – NADIA, WEST BENGAL
Copyright © 2017 NCC Limited
Water & Environment
RCC PIPE MANUFACTURING UNIT‐ INDORE JACK WELL CUM PUMP HOUSE ‐ MIHAN
MS PIPE LINE ‐ COIMBATOREJACK WELL CUM PUMP HOUSE ‐ MIHAN
Copyright © 2017 NCC Limited
Water & Environment
P j t IFFCO P j t N diProject: IFFCO Project: Nadiya
Project: Kosaram Pumping Project: Maharastra Jeevan Pradhikaran Surji ‐ Maharastra
Copyright © 2017 NCC Limited
Water & Environment
Copyright © 2017 NCC Limited
Water & Environment
Copyright © 2017 NCC Limited
Water & EnvironmentPHED,Bikaner‐Design, construction,operation & maintenance of Water supply project Bungi Rajgarh 1,514.70 PHE, Narampur, Khatra water supply scheme, W.B‐Surveying,Planning, Designing, Delivery,Erection, construction,Commissioning andcompletion of piped water supply scheme in Kahtra,Hirbandh,Ranibandh block of Bankura District. 1,699.07
CMWSSB‐Tambaram WSP‐Waterpipe lineworks from Ponamallee Bypass road to Tambaram 759.01
PHED, Ajmer‐ Chambal Bhilwar,P3‐Chmbal Bhilwara Water supply project Phase I with operation and maintenance for 10 years 675.70
Goa Water supply and sewarage Project,Jica (UGD margoa) ‐ Construction of sewer network in Margoa 520.10 PHED,Jodhpur‐Narmada canal based transmission drinking water supply project Sanchor town (116 & 138 villages) 1,358.50
PHED,Jodhpur ‐Narmada based Transmission & Cluster Water supply project of 205 villages of Ramsor &Sheo, Tehsil of District Barmer 6,395.00
Aditional Chief Engineer PHED, Bikaner‐Water supply project, at Taranagar‐ Jhunjhunu‐Sikar‐Khetri ( Turnkey project) 5,883.30 Chief Engineer,PHED,Ajmer(chambal phase‐II)‐Work of Cluster scheme of 188 villages of Mandal Tehsil along with augumentation of mandal Head works under "Chambal water supply project Phase‐II" 2,351.20
TDWSP‐Warangal‐Providing Drinking water supply in HMWSSB segment in Warangal district. 7,495.80
Utt kh d b t d l t G t f Utt kh d D h d ) ROORKEE W t S l di t ib ti t f R k t 436 11Uttarakhand urban sector development, Govt of Uttarkhand , Dehradun). ROORKEE‐Water Supply distribution system of Roorkee town 436.11
JICA Assisted Agra water supply project‐Supply and construction of 2100 mm diameter steel gravity mains conduit pipes from Parla to Bhurekha under package 5 A under JV L&T & NCC 55&45 % of contract value Rs 74555.10 million 3,354.70
Copyright © 2017 NCC Limited
Water & Environment
HC WSS‐Surface water based piped water supply scheme at Nadia Dist. 2,383.00 The Supdt Engineer,PRLIS Cirlce no 1,Nagarkarnool‐Formation of Venkatadri Reservoir bund from KM 0.00 to KM 6.900 at Vattem village,Mahaboobnagar district.. 13,783.40
Sardar Sarovar Narmada Nigam Ltd‐Design, Constn.,Testing, Commissioning & O & M of Kutcch Branch Canal Pkg. I 4,481.18 Govt of Telangana TDWSP RANGAREDDY Design supply erection testingand commissioning of electro mechanical works for variousGovt of Telangana,TDWSP., RANGAREDDY‐Design, supply,erection,testingand commissioning of electro mechanical works for various pumping stations at Khammam,Warangal and Rangareddy district. 1,396.50
Water Resources & supply , Rajkot ‐(sauni‐PKG‐2)‐EPC Contract of MS Pipeline water project at Khatadi village (Pkg‐2) 8,310.05 Water Resources & supply, Rajkot‐(Sauni‐pkg‐1)‐EPC Contract of MS Pipeline water project at Khatadi village (Pkg‐1) 4,548.20 Govt of Telangana,TDWSP., RANGAREDDY‐Providing drinking water supply to Chevella,Vikarabad,Pargi,Tandur,and Maheswaram,
i i f S i il i 14,447.60constituencies from Srisailam Reservoir. 14,447.60
HMWSSB ‐HYDERABAD (QUITHUBULLAPUR)‐Water supply distribution net work project‐GHMC Package II,part of Hyderabad city. 5,329.60
Govt of Telangana,TDWSP‐KHAMMAM‐Drinking water supply project construction of intake well in palair Reservoir for 17 Mandals of Warangal Dist and 3 Mandals of Khammam Dist. 2,393.90
Chief Engineer PHED Jaipur Regional water supply scheme of 210 villages of Thasil Bassi in Jaipur district 2 848 10Chief Engineer,PHED,Jaipur‐Regional water supply scheme of 210 villages of Thasil Bassi in Jaipur district 2,848.10 PHED‐Ajmer (Chambal‐Bhilwara Package 2)‐Chambal Bhilwara Water supply project Package 2 2,899.00 PHED‐Ajmer (Chambal‐Bhilwara Package 1)‐Chambal Bhilwara water supply project Package I 2,872.50 PHED‐Bikaner,Rajasthan‐Ratangarh water supply project 2,497.50
PHE, Dte, Narampur‐Bankura W.B. ‐Piped Water supply scheme allied works in Bankura Muncipality I & II, near Durgapur Barrage. 2,487.30 p p pp y p y g p g
Guntur Muncipal Corporation‐Water supply system in Guntur 2,770.20 Supdt Engineer,Western Circle,PHE Dte,Paschim Medinipur,WB. (Panskura WSP II)‐Surveying,planning,designing,delivery,erection,construction,commissioning and completion of all related works for piped water supply scheme in Pansukura‐II
1,709.00
Copyright © 2017 NCC Limited
Railways
Copyright © 2017 NCC Limited
Railways
RVNL‐S'BAD‐Railway electrification & Line doubling with all related works of Gudivada‐Bhimavaram section 2,090.00
Copyright © 2017 NCC Limited
Electrical Indian power supply needs to grow at approximately 12% annually to keep pace with GDP growth rate of 8% Indian power supply needs to grow at approximately 12% annually to keep pace with GDP growth rate of 8%
per annum Central Government has introduced schemes which include “Accelerated Power Development and Reform
Programme” (APDRP) for improving transmission and distribution network across states
• Design, engineering, erecting, testing and commissioning of transmission lines and 18 400
( Mn)
transmission lines and substations
• Project electrification
ivision
s
18,400
Revenues
• System improvement projects
busin
ess d
i
5 170
8,280
4 820Share % on turnover FY‐17
NCC
’s key 4,430
2,770 2,550
5,170 4,820
2,610 7%
Share % on turnover FY 17
FY‐12 FY‐13 FY‐14 FY1‐15 FY‐16 FY‐17 H1 FY‐18 ORDER BOOK
93%
Copyright © 2017 NCC Limited
Electrical
Some of the Major Projects Executed are:
Copyright © 2017 NCC Limited
Electrical
ELECTRICAL DIVISIONELECTRICAL DIVISION
DESIGN, ENGINEERING, ERECTION, TESTING & COMMISSIONING OFDESIGN, ENGINEERING, ERECTION, TESTING & COMMISSIONING OF
•• 400 KV TRANSMISSION LINE400 KV TRANSMISSION LINE•• 220 KV TRANSMISSION LINE220 KV TRANSMISSION LINE•• 33/11 KV SUB STATION33/11 KV SUB STATION
33 KV OVER HEAD LINE33 KV OVER HEAD LINE•• 33 KV OVER HEAD LINE33 KV OVER HEAD LINE•• 11 KV OVER HEAD LINE11 KV OVER HEAD LINE•• PROJECT ELECTRIFICATIONPROJECT ELECTRIFICATION•• SYSTEM IMPROVEMENT PROJECTSSYSTEM IMPROVEMENT PROJECTS•• SYSTEM IMPROVEMENT PROJECTSSYSTEM IMPROVEMENT PROJECTS
Copyright © 2017 NCC Limited
Electrical
Project: AP TRANSCO, Mahaboobnagar, AP
Scope: Aug of 33/11 KV power trans VCBs Bay Extns DFID 85/98
Project: APDRP – Nagpur ‐ Maharastra
Scope: 33 KV OH/UG Lines Substations allied work on turnkey basisScope: Aug of 33/11 KV power trans. VCBs. Bay Extns‐DFID‐85/98 Scope: 33 KV OH/UG Lines, Substations, allied work on turnkey basis
Project: APGRP, Mangaldoi, Assam.
Scope: Strength & Imporve of sub‐trans. & Distribute – Turnkey basis
Project: Tata, Madanapally, AP
Scope: 400 KV Double Circuit Transmission‐110 km Khammam to Madanapally
Copyright © 2017 NCC Limited
Electrical
Project: Southern Power District Co of AP, Tirupati, AP.
S T k b i P j 28Scope: Turnkey basis Project ‐ 28
UPPALWADI, NAGPUR APTRANCO‐KhammamUPPALWADI, NAGPUR APTRANCO‐Khammam
Copyright © 2017 NCC Limited
Electrical
Copyright © 2017 NCC Limited
Electrical
Copyright © 2017 NCC Limited
Electrical
Copyright © 2017 NCC Limited
ElectricalP V N L Varanasi (RGGY PHASE II Basti) Rural Electrification work on turnkey basis in Basti of UP 1 714 80P V N L, Varanasi (RGGY PHASE ‐II Basti)‐Rural Electrification work on turnkey basis in Basti of UP 1,714.80 P V N L , Varanasi (RGGY PHASE‐II Maharajganj)‐Rural Electrification work on turnkey basis in Maharajganj ‐ UP 1,893.80 Rural Electrification work on turnkey basis in Deoria Dist ‐ UP 917.60 Dakshinanchal Vidyut Vitran Nigam Limited, Agra, (DDUGY‐ Auraiya)‐Rural electrification works in Auraiya district of UP 1,485.78
Dakshinanchal Vidyut Vitran Nigam Limited Agra (DDUGY Chitrakoot) Rural electrification works in Chitrakoot district of UP 907 56Dakshinanchal Vidyut Vitran Nigam Limited, Agra, (DDUGY‐Chitrakoot)‐Rural electrification works in Chitrakoot district of UP 907.56
Madhyanchal Vidyut Vitran Nigam Limited, Lucknow, (DDUGY ‐Bahraich)‐Rural electrification works in Bahraich district of UP 1,372.28
Madhyanchal Vidyut Vitran Nigam Limited, Lucknow (DDUGY ‐Hardoi‐II)‐Rural electrification works in Hardoi district of UP 1,528.16 M V V N L , Lucknow (RGGY ‐HARDOI)‐Rural electrification works under RGGVY scheme‐Hardoi 1,067.60 M V V N L ,Lucknow (RGGY ‐AMETHI)‐Rural electrification works under RGGVY scheme‐Amethi 860.20 M V V N L,Lucknow (RGGY‐AMBEDKARNAGAR)‐Rural electrification works under RGGVY scheme‐ Ambedkarnagar 661.20 W.B.S.E.D.C.L ,West Bengal‐Rural Electricity Infrastructure Development in Burdwan district of West Bengal . 1,554.70 Jharkhand Bijli Vitran Nigam Limited‐Rural Electricity Infrastructure Development in Dumka & Jamtara District. 2,999.60 Madhyanchal Vidyut Vitran Nigam Limited Lucknow Construction of Feeder Separation works in Badaun district in Uttarpradesh 672 85Madhyanchal Vidyut Vitran Nigam Limited, Lucknow‐Construction of Feeder Separation works in Badaun district in Uttarpradesh 672.85 Purvanchal Vidyut Vitaran Nigam Limited, Varanasi‐Constructionof 33/11 kv substation & associated 33/11 kv line works of Gorakhpur & Basti under intergrated power development scheme. 862.00
P V N L , Varanasi (RGGY‐Varanasi.)‐Execution of works for rural electrification under RGGVY in Varanasi of UP 816.60 Purvanchal vidyut Vitran Nigam Limited , Agra (IPDS ‐ALLAHABAD)‐Construction of Sub stations and Kv line works of Allahabad zone 1,560.10 y g , g ( ) ,
Purvanchal vidyut Vitran Nigam Limited , Agra (FSP AZAMGARH)‐Rural electrification works in Ballia , MAU, AZAMGARH Dist.of UP 755.00
P V N L., (RGGY Phase II‐Azamgarh)‐Rural electrification works under Rajiv Gandhi Grameen Vidutikarana Yojana Phase III ‐ Azamgarh 1,926.00
P V N L, (RGGY Phase II‐Fatehpur)‐Rural electrification works under Rajiv Gandhi Grameen Vidutikarana Yojana Phase III ‐ Fatehpur 1,351.70 PVNL ‐Varanasi (RGGY ‐ Phase II Allahabad)Rural electrification works under RGGY Phase II in Allahabad District 1,650.46 PVNL‐Varanasi ( RGGY ‐Phase II Ballia)‐Rural electrification works under RGGY Phase II in Ballia District 1,363.91 Kerala State Electricity Board, (RAPDRP‐KOCHI)‐Execution of works for augmentation of distribution system in Kochi under RADRP scheme. 2,015.60
Copyright © 2017 NCC Limited
Irrigation Construction investment in irrigation sector expected to be Rs. 1033bn (US$25.9 bn) during 11th Five YearConstruction investment in irrigation sector expected to be Rs. 1033bn (US$25.9 bn) during 11th Five Year
plan Construction investment in Hydropower sector expected to be around US$18.5 billion during 11th Five Year
plan being 57% of total investment in power sector Increasing importance being given to hydro‐power
• New business division started i A il 2004 M t j t
Construction intensive nature of hydro power projects
( Mn)
in April 2004: Most projects in JV
–Dam projects
Lif i i i jivision
s 26,500
–Lift irrigation projects–Gravity irrigation projects–Hydroelectric power bu
siness d
i
Revenues
projects
NCC
’s key
3,470 3,970 3,480 2,400 3,050 1,310
4%
Share % on turnover FY‐17
FY‐13 FY‐14 FY‐15 FY‐16 FY‐17 h1 fy‐18 ORDER BOOK
96%
Copyright © 2017 NCC Limited
96%
Some of the Major Projects Executed are:
Copyright © 2017 NCC Limited
Irrigation
Project: Gundalkamma Reservoir Project, Ongole Scope: Water supply of 80,000 acres, Dam, bund, Right & Left canals
Project: Devadula, APScope: Devadula Lift Irrigation Project ‐ AP
G dik t R i G dik t APProject Tadipudi AP Gandikota Reservoir – Gandikota‐APProject: Tadipudi , APScope: Tadipudi Ettipotala Project
Copyright © 2017 NCC Limited
Irrigation
Copyright © 2017 NCC Limited
Irrigation
Govt.of AP ‐ CAD Irrigation (Thotapally)‐Construction of Thotapally Barrage 1,954.15 Govt.of AP ‐ CAD (Gundalakamma)‐Construction of Gundalakamma Reservoir 1,372.40 J.Chokkarao Devadula Phase III, Pkg. IV‐Devadula Phase II 4,815.30 GANDAK CANAL Project ‐ Bihar‐Execution of restoration of Eastern Gandak canal system 5,414.46 I di S P j t (P l P j t) I i ti k I di S P j t 1 064 70Indira Sagar Project (Polavaram Project) ‐Irrigation works ‐ Indira Sagar Project 1,064.70 Irrigation works ‐ SRBC Main canal work‐Irrigation works ‐ SRBC Main Canal work 2,818.38 GNSS Flood flow canal work,Gorakallu‐P29‐Irrigation works ‐ GNSS Flood Flow Canal 858.15 Kailasagiri canal‐P 10‐Irrigation works ‐ Kailasagiri Canal 425.60 Supdt Engineer,Kaleswaram Project,Karimnagar‐Lift Irrigation project ‐ Medigadda Barrange to Annavaram Barrage, Sripada Yellampally 5 652 22project. 5,652.22
Exc. & Lining of Irr.Tunnel‐GNSS Works (OWK‐P30)‐Excavation & Lining of Irrigation Tunnel ‐ GNSS works 2,228.47 Pranahitha‐Chevella Lift Irrigation‐Bellampally‐Pkg.No.2, Pranahitha‐Chevella Lift Irrigation Scheme 744.80 Saradhi Barrage ‐ Chattisgarh‐Constn.of Saradhi barrage with verticle lift gates 3,990.30
Copyright © 2017 NCC Limited
Power& Metals The performance of the power sector directly impacts the overall economy of the country, as it is the most
i t t tit t f i f t timportant constituent of infrastructure. The Indian Govt.’s current economic plan, with its emphasis on greater industrialization and infrastructure
development, has created tremendous demand on the generation and supply of power. Metal Industry is the mainstay of an economy as it meets the requirements of a wide range of industries such as
• The Company is concentrating on Balance ofPlant(BOP) works pertaining to various thermal andhydro‐power projects in various parts of the
Metal Industry is the mainstay of an economy as it meets the requirements of a wide range of industries such asinfrastructure, engineering, automobile, electrical and electronics.
( Mn)
hydro power projects in various parts of thecountry.
• The division will also take‐up tunneling work forhydro‐electric power projects.
• NCC has signed a MoU with POSCO E&C of SouthKorea the fourth largest steel producer in the worldiv
ision
s 32,780
Korea, the fourth largest steel producer in the world
• The Company intends to leverage the provencapabilities of POSCO E&C to bid for EPC contractsof various steel plant expansion projects andgrassroot steel plants that are coming up in thecountry.bu
siness d
i
15,050
NCC
’s key
8,510 11,290
2,620 190 730
Share % on turnover FY‐17
190 730
FY‐13 FY‐14 FY‐15 FY‐16 FY‐17 1HY FY‐18 ORDER BOOK
Copyright © 2017 NCC Limited
99%
Power
Hydro Power - Manali
Project: Gowtami Powr Project, PeddapuramProject: Gowtami Powr Project, Peddapuram
S 460 bi d l l t t K ki d
Project: Duhagan Hydro Electric Project
S U t H d R T l T l i id iScope: 460 mw combined cycle power plant at KakinadaScope: 460 mw combined cycle power plant at Kakinada Scope: Upstream Head Race Tunnel – Tunnel inside view
Copyright © 2017 NCC Limited
Power
Coal Bunker #10(14 MTR LVL) & COAL BUNKER #10 (35 MTR LVL) Name of client: BHEL; Work: Site at Angul OrissaCoal Bunker #10(14 MTR LVL) & COAL BUNKER #10 (35 MTR LVL) Name of client: BHEL; Work: Site at Angul, Orissa
Copyright © 2017 NCC Limited
Power
Name of Client: Adhunik PowerWork: Power House – Size 38M X 167M
Copyright © 2017 NCC Limited
Power
Copyright © 2017 NCC Limited
Power
Copyright © 2017 NCC Limited
Metals
SAIL‐IISCO STEEL PLANT, Blast Furnace Project, Burnpur – West BangalCopyright © 2017 NCC Limited
Metals
Copyright © 2017 NCC Limited
Metals
NTPC‐BARH‐BIHAR
Copyright © 2017 NCC Limited
Metals
SCCL ‐ Opencast Project ,Kothagudem‐Blast hole drilling, controlled blasting with shock tubeintiation, excavation, loading, Transportation and dumping 3,037.87
NTPC LTD., NOIDA‐Civil works Package for BARH Super Thermal Power project 1,095.90 NCC Power Projects Limited‐Power project at Nellore 60,753.62
Copyright © 2017 NCC Limited
Mining A number of opportunities exist in this space in view of the government planning to open private sector A number of opportunities exist in this space in view of the government planning to open private sector
participation in mining. Untapped potential for Indian players in global market
Established in 2008, this division caters to the coal needs of the Group company’s power
( Mn)
p p y pgenerating assets as well as rising demand.
It also seeks to enter the ferrousivision
s
16,330
It also seeks to enter the ferrous and non‐ferrous metal segments
Bid for overburden removal busin
ess d
i
projects
NCC
’s key
860 640 800 330 ‐ 60
FY‐13 FY‐14 FY‐15 FY‐16 FY‐17 H1 FY‐18 ORDER BOOK
Copyright © 2017 NCC Limited
MiningHEMM at Medapalli Open Cast Project, Ramagundam‐ AP
Copyright © 2017 NCC Limited
Mining
Copyright © 2017 NCC Limited
International India has miniscule Rs22bn (US$0 5bn) share of Rs176tn(US$4trillion) global construction business India has miniscule Rs22bn (US$0.5bn) share of Rs176tn(US$4trillion) global construction business. Construction business internationally offers excellent opportunity for project exports Untapped potential for Indian construction players in global market
• NCC has opened regional offices in Dubai(UAE) and
( Mn)
Muscat(Sultanate of Oman) for participation in various roads, Water supply projects and
ivision
s
8 8909,930 9,620
building projects, where NCC has proven expertise.
busin
ess d
i
8,170 8,890
7,330 8,150
Share % on turnover H1‐FY‐17
NCC
’s key
2,870
FY‐13 FY‐14 FY‐15 FY‐16 FY‐17 H1 FY‐18 ORDER BOOK
Copyright © 2017 NCC Limited
International
I t ti l P ( Mn)International Presence• NCC has presence in Oman and UAE through subsidiaries
– NCCL International LLC in MuscatHighlights of Our International Business
– Nagarjuna Contracting Co. LLC in Dubai• Key focus areas internationally are also built around expertise
gained in the domestic market– Transportation( Roads & Bridges)
Contracts won so far Rs. 9,620 Mn
FY17 Revenues Rs. 9,930 Mn
– Water & Sanitation– Buildings
• NCC is opportunistically trying to build its international presence in Saudi Arabia, GCC and some other North African Nations
Outstanding order book
(As on March, 2017)
Rs. 9,620 Mn
5% of total order book
• International projects are typically higher ROCE projects
MuscatSohar Water pipeline, Sohar City: Rs. 773 Mn Abu Dhabi
DubaiDEWA water pipeline, Dubai: Rs. 7,054 Mn
• Batinah Expressway Road Project: Rs. 22,876 Mn• Al Batinah Coastal Road : Rs. 18,065 Mn• Al Amerat Quriyat Road (70 km): Rs. 6,781 Mn
(completed)
MuscatQuriyat
588 villas at Al Ain, Abu Dhabi: Rs. 6,828 Mn(completed)
Copyright © 2017 NCC Limited
718 villas at Quriyat City: Rs. 8,944 Mn
(completed)• Wadi Adai Amerat Road (7.5 km): Rs. 6,495 Mn
(completed)
International
Dualization of Al Amerat Quriyat Road at Muscat
Copyright © 2017 NCC Limited
International
S l th H i P j tSalamath Housing Project:
DEWA Pipe Line Project, Dubai, Package‐ 512ASohar Water Network Phase – I at Sohar, MuscatCopyright © 2017 NCC Limited
International
Quriyat Housing Project:
Copyright © 2017 NCC Limited
International
Copyright © 2017 NCC Limited
Subsidiaries ‐ Business Plans
Focus onFocus onLong Term Infra ProjectsLong Term Infra Projects
Focus On Focus On Real Estate ProjectsReal Estate Projects
TransportationTransportationPowerPower
ResidentialResidential CommercialCommercial
VilasVilas IT ParksIT Parks
ApartmentsApartments
TownshipsTownshipsSEZSSEZS
HotelsHotels
Shopping Shopping MallsMalls
Commercial Commercial ComplexesComplexes
Copyright © 2017 NCC Limited
Current BOT Portfolio
NCC Ltd.NCC Ltd.
NCC InfraNCC Infra
55%
Roads
OB Infra Limited (~63 km)64%
Pondicherry – Tindivanam Tollway Limited (~36 km)
64%
48%48%
Copyright © 2017 NCC Limited
Execution on TrackNCC INFRA HOLDINGSNCC INFRA HOLDINGS
P jRevenue
PProject
C (R
Exposure of NCC(1)
COD C S (2)ProjectsModel
Partners Cost (Rs. Mn)
NCC( )
(Rs. Mn)
COD Current Status (2)
Roads
OB Infra Annuity KMC 5,896 1245.50 June 2009
COD achieved w.e.f 30.06.2009Annuities being received regularly
Securitisation of future cash flows achieved.2009 Annuities being received regularly o s ac e ed
Pondicherry – IL&FS Dec Toll collection is Rs 3 0 Lacs per The Loans have been Pondicherry –Tindivanam Toll E&C ,
Terra3,621 767.70 Dec
2011Toll collection is Rs. 3.0 Lacs per day restructured by lending
consortium.
TOTAL ( Roads) 9,517 2013.20
Copyright © 2017 NCC Limited
Real Estate Projects
NCC Ltd.NCC Ltd. PromotersPromoters
• Real estate development spearheaded by NCC Urban Infrastructure Ltd
• 17 projects planned in the Group
NCC UrbanNCC Urban
80% 20%• 17 projects planned in the Group
– 8 projects are ongoing currently• Presence across 6 cities in India and Dubai• Acreage ~ 245 acres
JHLP
Acreage 245 acres• No fresh investments from parent company in
real estate• NCC Harmony, Dubai
Real Estate SPVsTellapur Technocity
NCC Vizag Urban
– Construction of twin towers for 1.5 Mn sftof mixed development at Dubai Biotech & Research ParkE i d j R 18 92 B
Held directly by NCC Ltd.– Estimated project cost Rs. 18.92 Bn.
• NCC Urban (Consolidated)• Turnover for FY 2016‐17 – Rs. 828.78 Mn• Turnover for H1 FY‐18 – Rs. 673.80 Mn.
Copyright © 2017 NCC Limited
Real Estate Portfolio
Projects City Percentage holding
Type of Development Acreage Built up Area
(Mn Sqft.) Current Status
NCC Urban
R id G hib li H d b d 100% R id ti l 9 5 1 16 C l t dResidency, Gachibowli Hyderabad 100% Residential 9.5 1.16 Completed
NGHC Ranchi 88% Residential 56.44 2.55 Phase 1 Completed and Phase 2 in progress
Meadows Bangalore 100% Residential 8.00 0.65 Completed
Meadows II Bangalore 100% Residential 5.83 0.79 Completed
Serene Bangalore 100% Residential 1.75 0.10 Completed
Aster Park Bangalore 100% Residential 3.20 0.31 Completed
Maple Heights II Bangalore 100% Residential 2 13 0 17 CompletedMaple Heights II Bangalore 100% Residential 2.13 0.17 Completed
Green Valley Cochin 100% Residential 0.89 0.18 Completed
Laurel Cochin 100% Residential 1.24 0.16 Completed
Green Province Bangalore 75% Residential 22.61 0.41 Ongoing
Pallavaram Project Chennai 100% Residential 8.00 0.90 Yet to commence
NCC Urban Mist Woods Bangalore 50% Residential 12.00 0.25 Ongoing
Park Square Guntur 64% Residential 2.00 0.23 Completed
Gardenia Hyderabad 55% Residential 4.00 0.63 Ongoing
MunneKollal Bangalore 50% Commercial 2.00 0.22 Yet to commence
Temple Trees Chennai 56% Residential 2.03 0.14 Ongoing
Ivory Heights Bangalore 58% Residential 3 30 0 47 Completed
Copyright © 2017 NCC Limited
Ivory Heights Bangalore 58% Residential 3.30 0.47 Completed
Real Estate Portfolio
Projects City Percentage holding Type of Development Acreage Built up Area
(Mn Sqft.) Current Status
NCC Ltd.
Development AgreementJHLP Hyderabad 25% Residential 6.00 0.80
Development Agreement with Mantri Developers
of Bangalore
Tellapur Technocity Hyderabad 26% Residential & Commercial 100.00 7.5 Yet to commence
NCC Vi U b Vi kh t 95% R id ti l & C i l 98 00 4 9 Y t tNCC Vizag Urban Visakhapatnam 95% Residential & Commercial 98.00 4.9 Yet to commence
Some of the Major Projects Executed are:
Copyright © 2017 NCC Limited
NAGARJUNA GREEN RIDGE NAGARJUNA GREEN WOODS
NAGARJUNA ENCLAVE Nagarjuna Green Valley
Copyright © 2017 NCC Limited
Copyright © 2017 NCC Limited
Nagarjuna Premier ‐ Bangalore Nagarjuna Aster Park ‐ Bangalore
Nagarjuna Suites, Bangalore
Copyright © 2017 NCC Limited
Construction of National Housing Complex (NGHC) Project at Ranchi. No. of flats : 2000 Copyright © 2017 NCC Limited
Copyright © 2017 NCC LimitedNagarjuna Residency, Gachibowli ‐ Hyderabad
Nagarjuna Maple Heights I & II BangaloreNagarjuna Maple Heights I & II Bangalore
Copyright © 2017 NCC Limited
NCC Urban Gardenia Gachibowli ‐ Hyderabad
No of Units: 184
Copyright © 2017 NCC Limited
No of Units: 184Build up Area: 8.6 Lacs sft.
Urban One – Narsingi - Hyderabad
No of Units: 1529
Copyright © 2017 NCC Limited
Build up Area: 36.56 Lacs sft.
Copyright © 2017 NCC Limited
Park Square ‐ Guntur Nagarjuna Meadows‐ II‐Banguluru
NCC URBAN –FACADE NCC Urban Facade windows and doors combine high quality
FACADEg q y
materials with perfect operation and provide a highlight oftrendsetting designs and advantages. The beauty of thisallows you to find ideal solutions for your windows, doors andsun protection which will match your life style and way ofliving perfectly.
The three design styles studio, home and ambiente arereflected through their individuality, diversity and comfort – inproper clear styleUPVC/aluminium
The material combination UPVC/aluminium unites a highdegree of functionality best heat and sound insulation and
proper clear style.
degree of functionality, best heat and sound insulation, anda wealth of possibilities for individual design with a highlyweather‐resistant aluminium clad and an easy to maintainsurface.
We have infrastructure and machineries to execute 1,20,000 sqm UPVC Works and 1,00,000 sqm of Façade Works
We have core team with experience from reputedorganizations like Shapoorji Pallaonji Fabricators, Alufit (I)organizations like Shapoorji Pallaonji Fabricators, Alufit (I)Pvt Ltd and Global Façade Solutions etc. With this coreteam we are developing infrastructure which will be one ofmajor player in Façade Solutions Field and in the processwe have already bagged two orders from Brigade
Copyright © 2017 NCC Limited
Entreprises Limited one of reputed and Major Developersin Southern INDIA
FOCUSED GROWTH STRATEGY
Copyright © 2017 NCC Limited
Focused growth strategy
Increased focus on BOT and BOOT projects in Transportation and Power
O f f i k l i BOT d BOOT j One of few companies to make early entry into BOT and BOOT projects
Expand in international markets that fit within broad strategic vision
Currently focusing on Transportation Water and Buildings projects in Middle EastCurrently focusing on Transportation, Water and Buildings projects in Middle East
Establish Oil & gas division, Metal Division and Power Division
substantial business opportunity.
Established engineering division called EDTD (Engineering Design & Technology Development).
Copyright © 2017 NCC Limited
Numerous accolades testify to NCC’s excellent reputation
Award from Forbes Asia: Only construction company in India to be One of the 200 "Best Under a Billion" listed companies in Asia Pacific in 2005
Select Awards & Accolades
• Possesses one the best records for quality
On‐time performance
2005
Award as the “Fastest Growing Construction Company in India” as per Construction World ‐ NICMAR study in 2006.
Awarded the coveted position of being the “2nd largest construction i I di ” C t ti W ld NICMAR St d i 2007
and timely completion of large projects among Indian players
• Early completion bonuses from clients:
– INR 10 million for early completion ofcompany in India” as per Construction World‐NICMAR Study in 2007.
Award for Excellent Aesthetics Matching with Environment for project comprising a flyover, bridge, pedestrian subway and allied structures at Latur, Maharashtra in the year 2004
Award for Outstanding Concrete Structure of Year in 2003 for Main
INR 10 million for early completion of Kalina‐Vakola flyover, Mumbai from Maharashtra State Road Development Corporation
– INR 10 million for early completion of
Indian Institute of Bridge Engineers
Award for Outstanding Concrete Structure of Year in 2003 for Main Athletic Stadium, at Gachibowli, Hyderabad and 2002 for Shilpakalavedika, state of the art auditorium at Hyderabad respectively
National Aluminum Company, awarded Safety Certificate for maintaining highest standards of safety while constructing factory at
y pbuilding project from National Academy of Construction, Hyderabad
• One of few Indian companies to be awarded
Quality control
Damanjodi, Orissa in 1999
2010: Company’s Annual Report and Accounts for the year ended 31st March, 2009 have been “adjudged as the 2nd best under the category Infrastructure & Construction Sector by ICAI Awards for Excellence in Financial Reporting”
• One of few Indian companies to be awarded ISO 9001‐2000 certification from American Quality Assessors for quality management systems
Financial Reporting
2010: Company’s Annual Report and Accounts for the year 2008‐09has been awarded Certificate of Merit the “ Best Presented Accountsand Corporate Governance Disclosures Awards 2009” by the SouthAsian Federation of Accountants(SAFA)
Copyright © 2017 NCC Limited
Asian Federation of Accountants(SAFA)
Client List
Copyright © 2017 NCC Limited
CONSTRUCTION MACHINERY & EQUIPMENT
NCC has acquired modern, sophisticated and state‐of‐the‐art construction plant, equipment andmachinery imported as well as indigenous viz., Hot Mix Plant (Mobile and Stationery), ElectronicPavers, Pneumatic Tyred Rollers, Vibratory Tandem Rollers, Vibratory Earth Compactors, Cone & Jaw, y , y , y p ,crushers, Concrete Batching Plants, Transit Mixers, Concrete Pumps, Tower Cranes, Excavators,Hydras, Dozers, Plaster Sprayers etc.
At NCC technological up gradation and advancement in keeping with contemporary times is aAt NCC, technological up gradation and advancement, in keeping with contemporary times, is acontinuous process.
Copyright © 2017 NCC Limited
Thank You
Copyright © 2017 NCC Limited