• Aline Franqui• Bianca Farias• Gabriel Silva (PM)• Gilberto Pierozan• Julian Miyamoto• Junior Badziak• Lara Barroso

Outline Introduction

Technical approach

Tasks Responsabilities

Bid Breakdown by major components

Bid Summary

Introduction Since the past to our current age, mankind have

always tried to let a legacy behind. In construction, we can make this wish last for ages. But nothing of it would have happened if there were no planning or management skills.

In this project we could taste how the real world is, and how to be prepared to challenges to come.

Technical Approach We divided the work by lottery!

As PM I assumed that since everyone have done all the homeworks, nobody would have problem.

We’ve scheduled meetings twice a month So, as a group, we could see the progress of our

work.

After all the work was done, we revised the work from our collegues, to make sure it was correct

Task Responsabilities

Concrete

l Footing l Slab

l Footing

Footing

l Footing l Slab

Slab and Final Cost

#5 Rebars

Wood & Plastic

Dimensions of the elements used for Wood & Plastic and Thermal & Moisture

Studs

Headers

Blocking / OSB - CDX

Total price for Wood & Plastic = $7,084.90

Thermal & Moisture

Total price for Thermal & Moisture = $1,570.34

Plumbing

Plumbing

VTR – vent tub riser

LAV – lavatory

WC – water closet

TUB – tub shower

CO – cleanout adapter

KIT SK – kitchen sink

Plumbing

8’

11.5’

10.5’

11.5’5’

8’

Plumbing

Hot water line: pass through tubs, lavatories and kitchen. Cold water line: pass through tubs, lavatories, water closets and kitchen. For tubs and wc: 1” pipeFor lavatories and kitchen: ½” pipe

Roof

Roof main dimensions

Calculate the area on the plane, and then use the

following to have the inclined area:

34

54

4

(1+slope2)0.5

Roof Materials

Roof Calculation

HVAC

HVAC

Electrical

Electrical Wiring and Fixtures Take-off

Openings

Finishes

Finishes Calculation

Finishes Calculation

Bid Summary

Summary SheetDescription Material cost Equip. Cost Labor cost Total Cost

Earthwork $3,737.52 $4,439.94 $3,826.49 $12,003.95 Concrete (Foundation) $6,017.25 $14.18 $2,260.39 $8,291.82 Wood, plastics and composites $2,716.42 $446.72 $2,595.58 $5,758.72 Openings $2,016.19 $- $546.00 $2,562.19 Plumbing and fixtures $299.05 $- $1,445.78 $1,744.82 Roof (with truss package on total cost) $5,020.98 $- $3,228.39 $11,249.37 HVAC System $4,159.46 $- $851.21 $5,010.67 Electrical $6,803.22 $- $8,392.86 $15,196.08 Fire Suppression $52.00 $- $29.00 $81.00 Thermal, moistures protection $757.61 $- $812.73 $1,570.34 Finishes $11,408.05 $8,094.97 $19,503.03 Specialties $2,500.00 $2,500.00 Documentation $2,000.00

Labor Taxes (25%) $8,020.85

Sales Taxes (6%) $2,729.26 Subtotal $98,222.11 O&P (10%) $9,822.21

TOTAL COST $108,044.32