EVM: Beyond SPI & CPI

September 22, 2014 Charlene Thompson, PE PMP EVP PSP

Beyond SPI & CPI

OK, so you routinely calculate and report SPI and CPI for your projects, but what other information does the EVM chart tell us? Let’s take a detailed look at the information provided by our Earned Value calculations and chart, what the chart shows (and what it doesn’t). Are you really measuring the right things? Are there elements of your project schedule or cost/spending plan that skew the data?

Baseline Schedule Early Dates, Late Dates or ? Resource Loading Cost Loading

Earned Value Measurement Requirements

PV Planned Value

EV Earned Value

AC Actual Cost

SPI Schedule Performance Index

= EV/PV CPI Cost Performance Index = EV/AC

Earnings Rules

0% or 100%

25% - 50% - 75% - 100%

Actual progress (WIP)

Earned Value Measurement

Earned Value Chart – “S” Curve

Are we measuring the right things . . . right?

Are we measuring the right things . . . right?

Are we measuring the right things . . . right?

Are we really >$1MM behind?

Are we measuring the right things . . . right?

Progress against the baseline

EVM Chart with Progress

SV = EV – PV; SPI = EV/PV SV = -$512,500; SPI = 0.89

EVM Chart with Progress

Schedule Performance

SV = EV – PV; SPI = EV/PV SV = -$512,500; SPI = 0.89

CV = EV – AC; CPI = EV/AC CV = -$75,000; CPI = 0.98

Cost Performance

Trending

Trending

0.82 0.84 0.86 0.88 0.90 0.92 0.94 0.96 0.98 1.00 1.02 1.04 1.06 1.08 1.10 1.12 1.14 1.16 1.18

1.18

1.16

1.14

1.12

1.10

1.08

1.06

1.04

1.02

1.00

0.98

0.96

0.94

0.92

0.90

0.88

0.86

0.84

0.82Behind Schedule – Over Budget

Behind Schedule – Under Budget

Ahead of Schedule – Over Budget

Ahead of Schedule – Under Budget

Schedule Performance Index

Cos

t Per

form

ance

Inde

x

EAC

1

2

3

4

Today

5

6

Date of Last Rebaseline: mo/yrNumber of Rebaselines:Date of Next Rebaseline: mo/yr

Date of Last Award Fee: mo/yrDate of Next Award Fee: mo/yr

Tota

l Spe

nt

$0M

$110M EAC

$100M TAB

$90M BAC

$50M ACWP

Total Schedule ElapsedMo/Yr

EstimatedEnd

Mo/Yr

Baseline End

Contract Award

Mo/Yr Mo/Yr

CurrentDate

TCPI = 0.76CV = $2.0MSV = $2.9M

Communicate?

0.82 0.84 0.86 0.88 0.90 0.92 0.94 0.96 0.98 1.00 1.02 1.04 1.06 1.08 1.10 1.12 1.14 1.16 1.18

1.18

1.16

1.14

1.12

1.10

1.08

1.06

1.04

1.02

1.00

0.98

0.96

0.94

0.92

0.90

0.88

0.86

0.84

0.82Behind Schedule – Over Budget

Behind Schedule – Under Budget

Ahead of Schedule – Over Budget

Ahead of Schedule – Under Budget

Schedule Performance Index

Cos

t e

oa

ce

de

EAC

1

2

3

4

Today

5

6

Date of Last Rebaseline: mo/yrNumber of Rebaselines:

Date of Last Award Fee: mo/yrDate of Next Award Fee: mo/yr

Tota

l Spe

nt

A

ota Sc edu e apsedo/

d

o/

ase e d

a d

o/ o/

Cu e tate

Forecasting

How much is it really going to cost?

CV = EV – AC; CPI = EV/AC CV = -$75,000; CPI = 0.98

EAC = AC+(BAC-EV)

$6,825,000

How much is it really going to cost?

CV = EV – AC; CPI = EV/AC CV = -$75,000; CPI = 0.98

EAC = BAC/CPI

$6,868,076

How much is it really going to cost?

CV = EV – AC; CPI = EV/AC CV = -$75,000; CPI = 0.98

EAC = AC+(BAC-EV)/(CPI*SPI)

$7,167,576

SV = EV – PV; SPI = EV/PV SV = -$512,500; SPI = 0.89

Can we recover?

TCPI = 1.03 Is that good or bad?

Be careful – if you use the EAC: TCPI = (BAC-EV)/(EAC-AC) TCPI = 1.00 You’ve changed the target!

Earned Value based on Manhours

Earned Value based on Manhours

Earned Value based on Manhours

Earned Value based on Manhours

SPI = 0.98 CPI = 0.96

?

How long is it really going to take?

?

Earned Schedule

Earned Schedule

SPI(t) = 0.88 CPI(t) = 0.91

Earned Schedule

Earned Schedule

Earned Schedule

SPI(t) = 0.82 CPI(t) = 0.88

Other Considerations

• Self-performing vs. Contracting • Type of contract

• Large expenditures

• Accrue?

• Level of Effort • Management Costs • Operation Costs

• Software

• Calculation Options

Questions?

???