Post on 29-Mar-2015
Evaluating the Effect of Machine Runtime on Energy Consumption
Rebekah DrakeMark Hansen
Prashant Lodhia
Department of Industrial and Manufacturing Engineering
Green Manufacturing Faculty Advisors: Dr. Janet Twomey, Dr. Bayram Yildirim,
Dr. Lawrence Whitman, Dr. Jamal Sheikh-Ahmad
Supported by NSF CAREER: DMI-973347
Research ObjectiveIdentify environmental impacts of the manufacturing system so that we can: Conserve natural resources Offset adverse effects of rising fuel costs Prevent negative impacts of advances in
technology Extend useful product life
Product Life Cycle
Inputs End of LifeManufacturing
ProcessProduct Use
Reuse of Manufacturing By-Products
Environmentally Benign Materials
Component Recovery
Materials Recovery
Remanufacture
EnergyWastePollution WaterHazardous materials
Sub-cellular Machine Level Decisions
ProductionOperational Decisions
Supply Chain DecisionsEnergyWastePollution WaterHazardous materials
Process Diagram
Background Manufacturers’ objective is to decrease
production costs Current agenda focus includes:
Optimization of batch size Minimizing cycle time Optimizing production sequence Quality control
Status quo models do not consider the environment, specifically energy consumption
ThesisThe purpose of this research is to determine the energy consumption of a machine during startup, idle, runtime operations, and cutting in order to minimize the energy use of a production sequence through the development of a scheduling model.
Preliminary Study
Method Empirical study Production run of a single machined part Track power over time using National
Instruments Load Control Evaluate energy consumption of each
operation Startup Coolant Feed Movement Cutting Movement Etc.
Machined Part
Simulation Scenario Two 8-hour shifts, producing 250 parts/shift Two 15-minute breaks, one 30-minute lunch Non-bottleneck machine running at
approximately 50% capacity Best Case Scenario
All parts arrive at the beginning of the shift Parts are machined continuously without idle time Machine is shut off when all parts are complete
Worst Case Scenario Parts arrive with a random inter-arrival time Machine runs idle for any time not machining
Best Case Scenario Machining energy/part = 65,590 J/part Machining energy for 250 parts (one shift)
= 65,590 J/part * 250 parts/shift = 16,397,566 J/shift
Machining energy for 1 day= 16,397,566 J * 2 = 32,795,132 J/day
Total energy/year= 32,795,132 J/day * 250 days/year = 8,198,782,876 J/year
Worst Case Scenario Machining energy/year
= 8,198,782,876 J/year Idle energy/hour = 1,472,988 J/hour Idle energy/shift = 1,472,988 J/hour * 4 hours/shift
= 5,891,951 J/shift Idle energy/day = 5,891,951 J/shift * 2 shifts/day
=11,783,901 J/day Idle energy/year = 11,783,901 J/day * 250 days/year
= 2,945,975,351 J/year Total energy/year = 8,198,782,876 J/year +
2,945,975,351 J/year=11,144,758,227 J/year
Simulation Energy Comparison
0
2
4
6
8
10
12
En
erg
y (
Bil
lio
n J
ou
les)
Best Case Worst Case Idle
26% of Total
Energy
Future Work Other factors to consider
Consider cycle time, batch size, production sequence, etc.
More machines Different parts Different materials Monitors, lighting, air conditioning, etc.
Real-world scheduling algorithms Expand study to entire product life cycle
Thank you.