01. Scope of the EMS:
“those envi aspects that the organization identifies as those it can control and over which it can be expected to have an influence” => envi aspects of the supply chain
02. EMS audit => Internal audit
ISO 14001: 1996 -> ISO 14001:2004
03. Nonconformity
-no definition in the 1996 version
-nonconformity defined in the 2004 version
04. Legal and other requirements
-new requirement: an organization must now determine how its legal requirements apply to its aspects
ISO 14001: 1996 -> ISO 14001:2004
05. Objectives, targets and programmes
-new requirement: the objectives and targets shall be measurable
06. Communication
-additional requirement: the organization shall decide and document a decision on external communication
ISO 14001: 1996 -> ISO 14001:2004
07. Documentation
-new requirement: the organization shall specify documents
08. Evaluation of compliance
-new requirement: the organization shall evaluate and record its compliance with legal and other requirements
ISO 14001: 1996 -> ISO 14001:2004
09. Internal audit-use of a contractor or another member of the staff trained in EMS
10. Management review-inputs: results of internal audits, evaluations of compliance, communications from external parties, environmental performance of the organization,
ISO 14001: 1996 -> ISO 14001:2004
(inputs cont’d) extent to which objectives and targets have been met, the status of CA and PA, follow-up actions from previous mgt reviews, changing circumstances and recommendations for improvement
ISO 14001: 1996 -> ISO 14001:2004
-Mgt review outputs: decisions and actions related to possible changes to environmental policy, objectives, targets and other elements of the EMS, consistent with the commitment to continual improvement.
ISO 14001: 1996 -> ISO 14001:2004
Nonconformity: Non-fulfillment of a requirement
Previous definition (based on other ISO standards): non-fulfillment of a requirement of the management system
Current definition: Previous definition plus non-fulfillment of performance requirements such as objectives, targets or legal permits
Definitions
Corrective action : Action to eliminate the cause of a detected
nonconformity
Preventive action: Action to eliminate the cause of a potential nonconformity
Requirements related to CA/PA
The procedure must define requirements for
a. Identifying and correcting NCs and mitigating their envi impact;
b. Investigating NCs, determining their causes and taking actions to avoid recurrence;
c. Evaluating the need for action to prevent NCs and taking action to avoid their occurrence;
Requirements related to CA/PA
d. Recording results of CA and PA
e. Reviewing the “impactiveness” of CA and PA.
Requirements related to CA/PA
NCAR Form
-Description of the Non-conformance
(activity description, issued to auditee/DC/PL, date, issued by the IEAT Leader, description/illustration of the NCAR: major, minor, obs)
-Nature of request and answer date (root cause, immediate action, CA, PA)
-Closure of the NCAR (signatures of the auditee, IEAT Leader, and EMR
Requirements related to CA/PA
Surveillance audit recommendation:
Addition of “immediate action” to Part II of the NCAR (i.e., nature of the request)