Post on 25-Mar-2020
1© Copyright 2011 EMC Corporation. All rights reserved.
EMC Propel
SAP on Vblock
May 2011
Tony Pagliarulo, Vice President, Service Delivery
EMC Corporation
2© Copyright 2011 EMC Corporation. All rights reserved.
EMC IT at a Glance
User Profiles 48,000 “internal” users
IT Environment400,000+ customers and partners
5 data centers, 7 PB storage
Business Applications 400+ applications and tools
Virtualization ≈6,000 OS images (worldwide)
75% of all servers virtualized
Global Support 80+ countries and 20 languages
3© Copyright 2011 EMC Corporation. All rights reserved.
The New IT Landscape
Existing Apps New Cloud Apps SaaS Apps
Existing Datacenters Public Cloud Services
Private
Cloud
4© Copyright 2011 EMC Corporation. All rights reserved.
The New IT Landscape
Existing Apps New Cloud Apps SaaS Apps
Existing Datacenters Public Cloud Services
Private
Cloud
How do you weave all this together into a cohesive, secure,Cloud infrastructure?
5© Copyright 2011 EMC Corporation. All rights reserved.
EMC IT‟s Journey to the Cloud
% V
irtu
aliz
ed
86%
100%
75%
40%
30%
15%
2004-08 2009-10 2011+
Run IT as a
business
Mission-critical
applications
Development, test, and
IT-owned applications
WE ARE HERE
IT ProductionLower Cost
Business ProductionImprove Quality of Service
IT-as-a-ServiceImprove Agility
6© Copyright 2011 EMC Corporation. All rights reserved.
PROPEL Program Design Principles
• Design Approach
– Design for the future state of the business
– Minimize customizations and stay on vendor upgrade path
• Program Approach
– Move rapidly to migrate growing system risk
– Use phased approach to realize value
• People
– Drive cultural change and transformation
– Develop new skills and competencies for the team
7© Copyright 2011 EMC Corporation. All rights reserved.
Program Roadmap
Analyze
2010 2011 2012
Q2 Q3 Q4 Q1Q2 Q3 Q4 Q1Q2 Q3 Q4 Q1
2013
Gate 2b
Gate 3b
Gate 6
Gate 4
Gate 2a
Gate 3a
Gate 5
Design
Build
Test
Deploy
Phase/Gate: Plan/Analyze
Gate 2a
Design
Gate 2b
Build
Gate 3a – 3b
Test
Gate 4
Deploy
Gate 5 &6
Duration: 5 Months 8 Months 9 Months 9 Months 5 Months
Months: May „10 – Sept „10 Oct „10 – May „11 Feb „11- Oct „11 Aug „11– April „12 May „12 – Sept „12
(July 2012 Go Live)
Key Deliverables: • High Level Process
Designs
• Requirements
• RICEFW Inventory
• Instance Strategy
• Business Process Designs
• Configuration Rationales
• Functional Design
• Tech Arch Designs
• High Level Business Change
Impact
• High Level Training Strategy
• Initial Environment Build-outs
• Technical Design
• Source Code
• Training Materials
• Test Plan
• Mock Conversions
• Common Test Data
• String Test
• Integration Test
• User Verification Test
• Performance Test
• Deployment Plan
• Training Delivery
• Production Conversions
• Business Acceptance
8© Copyright 2011 EMC Corporation. All rights reserved.
Confirmed in
scope
Potential Agile /
Future Release
Incremental capability in
scope for foundation
SAP Module Landscape
ERP Central Component (ECC)– Core of 11.0.3 replacement
Credit
Management
Organization
Mgmt.
Nota Fiscal
Commissionaire
Localization
Financial Accounting
New GL AP
Asset
Account.
Bank
Account.
Logistics
General Transport. Warehouse
Financial Control
Overhead
Costs
Profit
Analysis
Product
Costing Production
Planning (PP)
General
eKanban
Planning
Sales and
Distribution
Supply Chain Mgmt (SCM)
Advanced Planning & Optimizer (APO)
Demand Planning
Global Available to
Promise
Supply Network
Planning
Supplier Network
Collaboration
BW
BWA
BO
Data Warehouse
Product
Hub
MDM Hub
Available to
Promise
High TechSupplier Relationship Mgmt (SRM)
MDM Catalogs Self-Service
Procurement
Product Lifecycle Mgmt (PLM)
Integrated Prod
Development
Product
Compliance
Materials
Management
Environment
al Health &
Safety
(EH&S)Product
Safety
SPRC
Quality
Management
Self Service
Registration
Sourcing
(RFx/Auction)
Project Systems
Cash Management &
Liquidity Planning
Note: This is not the full SAP landscape
Business
Planning
Bus. Planning & Consolidations (BPC)
Consolidation
Vertex or
Sabrix
3rd Party App.
Financial Supply Chain Mgmt (FSCM)
AR
9© Copyright 2011 EMC Corporation. All rights reserved.
Iomega
RSA
BRS
Re-architect the Business Processes to Enable the Future Business Model
Primary scope Other processes impacted
by ERP (TBD)
Out of scopeFuture
release (TBD)
Manage customer relationships
Track and manage product pipeline
Support install baseProvide professional
servicesManage contracts
General Accounting & Consolidation
Taxes & Treasury
Fixed Assets
Corp. FP&A
Functional Finance & Mgmt Reporting
Customer master
Item master
Other master
Business Intelligenceand Reporting
Forecast salesGenerate quote and configure products
Provide environment support services
Product &
Process Design
Plan
Ship
and
Deliver
Supply
Chain
Make to
order
Collect
payment
Order
confirmation
Revenue
& Cost
Posting
Post-order
IntegrationInvoice
Plan/install products and solutions
Design & develop
hardware
Design & develop software
SourcingOrder
Management
Contract
Management
Payment &
SettlementMaster Data Reporting
Engineering
Sales and Marketing
Release product
Manage hardwar
e changes
Release product & revisions
Manage electronic licenses
Other Businesses
Product Delivery
Order to Cash
Procure to Pay
Manageleases
Manage commissions
Record to Report
Information Mgmt
Global Services
10© Copyright 2011 EMC Corporation. All rights reserved.
VBlock for Mission Critical Applications
App
App
App
App
App
App
App
App
App
App
App
App
App
App
App
App
App
App
ArchitectureTechnology Highlights
App
App
App
App
App
MS
App
App
App
App
App
Oracle
Oracle ESX Cluster
SQL Server ESX Cluster
SAP App Tier ESX Cluster
3 Separate ESX Clusters• Best Practice
• License Restrictions
SAP App Tier Cluster
• VMware HA
• Load Balanced
SQL Server Cluster
• VMware HA
Oracle Cluster
• VMware HA
• Clusterware HA
ERPIntegration
11© Copyright 2011 EMC Corporation. All rights reserved.
Scope of Propel Integration Architecture
Private
Cloud
Enterprise
Integration
B2B
12© Copyright 2011 EMC Corporation. All rights reserved.
SpringSource Technology
• Enterprise software framework
• Web, Integration, Batch, Web Services
• Higher productivity framework for web applications
• Lightweight application server
• Enterprise monitoringReduce operational costs
Improve agility of IT
delivery
Drive workforce
productivity
• Team productivity ecosystem
• Scale projects through software, not people
• Make best practices a first and easy practice
Architect for the future• Enterprise Elastic Data Grid
• Enterprise Cloud Messaging
Implement EMC
“IT Proven” solutions
13© Copyright 2011 EMC Corporation. All rights reserved.
Current Integration Challenges
• Complexity
• Developer productivity at operations team expense
• Scalability and performance
• Application lifecycle management is too coupled to the
platform
• Too many platforms
• Middleware too specialized
• Little to no reuse across platforms
• Project cost
• Difficult to pool resources due to “stove-piped” skills
• Federated management and monitoring
• Scalability
Management / Security
Development
Operations
14© Copyright 2011 EMC Corporation. All rights reserved.
CIC – Integration Bus Example
Distribute
2
Distribute 1
Distribute
3
Process
Legacy 3
Integration Middleware
SAP
Legacy 1
Legacy 2CollectInvoice
17© Copyright 2011 EMC Corporation. All rights reserved.
Vblock – Environment
VMAX Configuration
• 4 Engines
• 3 Bays
• 96 FC drives with 4 hot spares
• 64 SATA drives with 4 hot spares
• No EFD drives (future)
• Microcode 5874
• 32 total FA‟s (16 dual port adapters)
• 213 empty drive slots for expansion
• RDF enabled
UCS Configuration
• 5108 Blade Chassis*
• 2104 Fabric Extender*
• B230-M1 Blade
• B440-M1 Blade
• 6140 Fabric Interface*
18© Copyright 2011 EMC Corporation. All rights reserved.
Technology Stack• EMC
• Recoverpoint
• Networker
• Avamar
• Data Domain
• VM backups ?
• Virtualization (VMware)
• vSphere 4.1 (5.0?)
• ESXi PXE boot (stateless, separate vNIC)
• vCenter
• vMotion
• Storage vmotion
• Site Recovery Manager (SRM)
• Dynamic Resource Scheduling (DRS)
• Distributed Virtual Switch (dvSwitch)
• Virtual Desktop Infrastructure (VDI)
• VM “gold” templates
• Vsphere management: accounts, authorization
• Clone policy
• Host profiles
Vmware vSphere
Application
Services
Vmotion
Storage vMotion
HA
Fault Tollerance
Data Recovery
Availability
vShield Zones
VMSafe
Security
DRS
Hot Add
Scalability
Application
Services
ESX and ESXi
DRS and DPM
Memory
Overcommit
vCompute
VMFS
Thin
Provisioning
vStorage
Distribution
Switch
Network I/O
Control
vNetwork
19© Copyright 2011 EMC Corporation. All rights reserved.
www.emc.com/emcit
EMC IT‟s Journey to the Cloud: A Practitioner's
Guidehttp://www.emc.com/collateral/software/white-papers/h7298-it-journey-private-cloud-wp.pdf