Edward Downer Elementary School Playfield Renovation Status Update 06/10/14.

Post on 15-Dec-2015

214 views 0 download

Tags:

Transcript of Edward Downer Elementary School Playfield Renovation Status Update 06/10/14.

WCCUSD Bond ProgramConstruction Update

Edward Downer Elementary School Playfield RenovationStatus Update

06/10/14

Construction Manager: Gabriel Fortich (SGI)

Project Engineer: Shawn Fitzgibbons (SGI)

Inspector of Record: Man Wah Cheng

Architect of Record: Rod Sepulvida (BCA Architects)

General Contractor: Maggiora & Ghilotti, Inc.

Edward Downer Elementary SchoolPlayfield Renovation

Project

Project Team

DEMOLITION OF EXISTING ASPHALT PAVING AND

MISCELLANEOUS ITEMS TO BUILD A NEW GRASS

FIELD INCLUDING ROUGH AND FINISH SITE GRADING,

IRRIGATION, PLANTING, AND FIELD DRAINAGE.

ELECTRICAL SCOPE CONSISTING OF POWER AND

DATA CONNECTION TO NEW IRRIGATION CONTROLLER

AND PROVISION OF CONDUIT AND FULL BOXES FOR

FUTURE LOW VOLTAGE SYSTEMS.

Edward Downer Elementary SchoolPlayfield Renovation

PROJECT SUMMARY

Edward Downer Elementary SchoolPlayfield Renovation

Project

Project Summary

Project Duration: 180 (Calendar

Days)

Notice To Proceed Date: May 19, 2014

Completion Date: Nov 15, 2014

Percent Complete: 18%

Base Contract Amount: $563,226.00

Edward Downer Elementary SchoolPlayfield Renovation

Project

General Information

Edward Downer Elementary SchoolPlayfield Renovation

Project

Site Demolition

Edward Downer Elementary SchoolPlayfield Renovation

Project

Clear and Grubbing

Edward Downer Elementary SchoolPlayfield Renovation

Project

Utility Trenching

Edward Downer Elementary SchoolPlayfield Renovation

Project

Electrical and Signal Conduit

Edward Downer Elementary SchoolPlayfield Renovation

Project

Sub-Grade Preparation