Background • City was awarded a $2.225 million grant
under the HUD Sustainable Communities Challenge Grants program in 2010.
• Grant funds are available for planning and pre development assistance related to affordable housing and TOD during a three-year period
• Fregonese Associates was selected from 12 firms to carry out the planning activities related to the grant.
2
Grant Study Areas
There are five separate plans being developed:
1. Vickery Meadow
(Walnut Hill and Park Lane Stations)
2. MLK 3. Hatcher 4. Lancaster Corridor (VA
Medical and Kiest Stations)
5. Buckner
3
Project Process
Existing Conditions
and Visioning
January - May
Plan Development and Strategies
April - August
Draft and Final Plan
September - December
Implementation
1 2 3 4 1
4
First Phase (Completed) January – May 2012
• Draft the Public Engagement Plan • Create Public Involvement Toolkit • Conduct Stakeholder Interviews • Conduct Developer and Broker Interviews • Evaluate Station Area Existing Conditions • Develop Guiding Principles • Develop Library of Feasible Buildings and
Development Prototypes • Evaluate Policy Framework and Local Market
5
Second Phase May – December 2012
• Conduct a Community Visioning Workshop • Workshop Results and Major Ideas Open House
Events • Existing Conditions Analysis, Findings and
Market Feasibility Study Findings • Develop and Compare Draft Scenarios • Create 2-D and 3-D Visualizations to
Communicate the Scenarios • Redevelopment Feasibility Analysis • Develop Station Area Visions • First Five Year Implementation Strategy
6
Overview of Approach for Each Station Area
–Land Use Concept Plan –Strategic Near-Term Opportunities –Catalytic Projects
• Conceptual Site Plans • Visualizations • Development Programs and Proforma
Analysis 7
8
Draft
9
Draft
Draft
10
VA Med Center Station
Kiest Station
Adaptive Reuse Concept
Lancaster Urban Village
Opal TOD Concept
Draft
11
Catalyst Sites
Catalytic Projects in the Lancaster Corridor
1. Lancaster Opal TOD Concept
2. Adaptive Reuse Concept
12
Lancaster Opal TOD
Mixed-income apartments, housing for veterans, housing for special needs, neighborhood retail, service office and restaurants. A: 3 and 4 Story Phase One Mixed-Use Building B: 2 and 3 Story Phase Two Residential Units 13
Existing Building
Draft 14
Lancaster Opal TOD Concept
15 Draft
Adaptive Reuse Concept – Old Payless Shoe Store
Adaptive Reuse Opportunity - Before
16
Draft
Lancaster Adaptive Reuse Opportunity– After
17
Draft
18
Draft
19
Draft 20
Hatcher Station
Hatcher Square
Adaptive Reuse Concept
Draft
21
Scyenne Road
Catalyst Sites
Catalytic Projects in Hatcher
1. Hatcher Square
2. Adaptive Reuse Concept on Second Avenue
22
23 Draft
Hatcher Square Conceptual Site Plan
24 Draft
Adaptive Reuse Concept Opportunity
Hatcher 2nd Ave Catalyst Development Opportunity Site - Before
25
Hatcher 2nd Ave Catalyst Development Opportunity Site - After
26
Draft
27
Draft
28
Draft
29
MLK Station
Station Development Concept
Adaptive Reuse Concept
30
Catalyst Sites
Catalytic Projects in MLK
1. MLK Station Area Development Concept– artist lofts, apartments and small retail
2. Adaptive Reuse Concept
31
32 Draft
MLK Station Concept
33 Draft
Adaptive Reuse Concept
MLK Adaptive Reuse Concept - Before
34
Draft
35
Draft
MLK Adaptive Reuse Concept - After
36
Draft
37
Draft
38
DART Station
New Commercial Development Concept
Commercial and Residential Development Concept
39
Catalyst Sites
Catalytic Projects in Buckner
1. DART Station parking lot redevelopment concept
2. Residential and Commercial Development concept at Buckner and Elam
40
41 Draft
Residential and Commercial Development Concept
42 Draft
Buckner and Elam Mixed Use Development Concept
43 Draft
Buckner Station Retail Development Concept
DART Parking Lot Development Catalyst Development Concept – Before
44
Draft
DART Parking Lot Development Catalyst Development Opportunity – After (Phase A)
45
Draft
46
Draft
47
Draft
48
Walnut Hill Station
Site Plan Concept for old Sam’s Club Area
Adaptive Reuse Concept
Park Lane Station
49
Mixed Use Library Concept
Catalyst Sites
Catalytic Projects in Vickery Meadow
1. Mixed Use Library Development Concept
2. Site Plan concept for old Sam’s Club site and surrounding area
3. Adaptive reuse concept of liquor store building at Five Points
50
51
Conceptual Drawing for Mixed Use Library Project - draft
Draft
Mixed Use Library Concept
52
53 Draft
Site Plan Concept for old Sam’s Club site and surrounding area
54
Draft
Adaptive Reuse Concept
Next Steps • Developer roundtable in later this week to obtain Dallas
developer feedback on catalyst project feasibility • Focus groups planned for October for additional
community input • Catalyst projects will be designed to be complete
development proposals with financial and design considerations
• Present opportunity sites, transportation enhancements for better DART access and area plans to public in October meetings – Obtain additional feedback prior to presentation to
Dallas City Council in December/January • Upon completion of area plans, City will issue Call for
Projects to solicit study area projects seeking grant funding for preconstruction and land acquisition
55
October – Roll out the Projects to the Public
56
Visit the project website: www.dallastod.com
Fregonese Associates - www.frego.com 1525 SW Park Avenue, Suite 200, Portland, OR 97201
57