1

DMAIC

A FIVE STEP METHODOLOGY TO PROBLEM SOLVING

2

DEFINE

D M A I C

3

PROJECT CHARTER

Project Title Project Type

YB/GB/BB

Business CaseProblem Statement

Goal Statement

In scope Out Scope

Unit of Measurement

Nature of Saving Hard/Soft

Revenue Enhancement

Expense Reduction

Loss Avoidance

Project Y

PROJECT TIME LINE

Define

Measure

Analyse

Improve

Control

Champion

Leader

Project Members

PROJECT ID

4

SIPOCSUPPLIER CUSTOMERPUTPUTPROCESSINPUT

5

PROCESS MAP

xxxx

xxxx

xxxx

xxxx

xxx

xxxx

6

CTQ TREE

xxxx

xxxx

xxxx

xxxx

xxxx

xxxx

7

DEFINE TOLLGATE

Date of Review

Participants

Sign off date

Signing off authority Process owner/champion/BB

8

MEASURE

D M A I C

9

MEASUREMENT PLANProject Y

Operational Definition

Continuous Data

Target

USL

LSL

Discrete Data

Unit

Defect

Number of Opportunities

List of Opportunities for defect

10

MEASUREMENT PLANMeasure of Performance

Data source and location

Sample Size Who will collect data

Closure Date Data Period

11

BASELINE CALCULATION FOR DESCRETE DATA

Total number of units

Total number of defects

Opportunity per unit

Defects per unit

Defect per opportunity

DPMO

Sigma level

12

BASELINE CALCULATION FOR CONTINEOUS DATA

Process Capability

Sigma level

DPMO

Yield

13

MEASUREMENT SYSTEM ANALYSIS

14

MEASURE TOLLGATE

Date of Review

Participants

Sign off date

Signing off authority Process owner/champion/BB

15

ANALYSE

D M A I C

16

ROOT CAUSE ANALYSIS

17

HYPOTHESIS TESTING SUMMARY

X’s Identified Data Normal? Hypothesis test performed

P- Value Is X significant?

18

HYPOTHESIS TESTING

Continuous

Discrete

Discrete Continuous

1 Sample t

2 Sample t

ANOVA

Correlation & Regression

Chi-Square Log-Regression

Y

X

19

ANALYSE TOLLGATE

Date of Review

Participants

Sign off date

Signing off authority Process owner/champion/BB

20

IMPROVE

D M A I C

21

IMPROVEMENT IDEASS.N Identified

root causeSolutions Perceived Benefits Cost / Risk

1.

2.

3.

22

IMPROVEMENT ACTION PLANImprovement actions

Responsibility Action plan Timeline

23

BASELINE CALCULATION POST IMPROVEMENT FOR DISCRETE DATA

Total number of units

Total number of defects

Opportunity per unit

Defects per unit

Defect per opportunity

DPMO

Sigma level

24

BASELINE CALCULATION POST IMPROVEMENT FOR CONTINUOUS DATA

Process Capability

Sigma level

DPMO

Yield

25

IMPROVE TOLLGATE

Date of Review

Participants

Sign off date

Signing off authority Process owner/champion/BB

26

CONTROL

D M A I C

27

CONTROLLING XS

Standard operating procedures changed

Visual controls

Mistake proofing

28

PROCESS CONTROL PLAN

29

CONTROL CHART

30

FMEA

31

CONTROL TOLLGATE

Date of Review

Participants

Sign off date

Signing off authority Process owner/champion/BB

32

PROJECT CLOSUREPROJECT CLOSURE

Champion

Leader

Project Members

PROJECT ID

Project highlights

Project CTQ Unit of Measurement

Before Project

After Project Target set

Statistically proven improvement ?

Yes/ No

Benefits – Hard or Soft ; $ / Year

Participants

Presented byFinancial Validation completed ?