July 2016

DES Division Of Transportation

Project Update

Wilson Boulevard Streetscape Improvements

N. Quincy Street to 10th Street N.

Wilson Boulevard Streetscape Improvements

Sector Plan Recommendations

Wilson Boulevard Streetscape Improvements

Sector Plan Recommendations

Wilson Boulevard Streetscape Improvements

Sector Plan Recommendations

• Provide new sidewalks, streetlights, bus shelters, street trees,

traffic signals and other complete street amenities.

• Provide appropriate pedestrian safety improvements.

• Coordinate the County project with new ongoing real estate

development.

• Design and construct the work in three phases - west, east and

center sections.

Wilson Boulevard Streetscape Improvements

Project Goals

DES Division Of Transportation

Wilson Boulevard Streetscape Improvements

Phase II-B

Completed spring 2012

Completed and Proposed Projects

Phase II-A

Completed summer 2010

Phase I-

Completed fall 2009

New C&G, sidewalks, traffic signal at Oakland St,

streetlights, trees and new bus shelters.

Proposed Phase III Center

Project requires ROW from three

businesses and utility undergrounding.

Expected to be completed as last phase.

Proposed Phase III West

Currently in engineering design

Proposed Phase III East

Includes the 10th and

Wilson Blvd intersection.

Currently in engineering

design. Utility

undergrounding in design.

Phase III Overview - 10th Street N. to N. Lincoln Street (All Sections)

Wilson Boulevard Streetscape Improvements

Proposed Improvements Overview Underground utilities

New upgraded traffic signals and streetlights

Extend WB 10th St. left turn lane

Remove Wilson to 10th St. free right turn

Maintain 11’ lanes

New ADA compliant sidewalks and crosswalks

New Traffic / Pedestrian Signal at Kansas Street

Phase III West - N. Lincoln Street to N. Kansas Street

Wilson Boulevard Streetscape Improvements

Existing Conditions End of Phase I work

Phase III West - N. Monroe Street to N. Lincoln Street

Wilson Boulevard Streetscape Improvements

Proposed

Phase III West - N. Lincoln Street to N. Kansas St.

Wilson Boulevard Streetscape Improvements

Proposed

Plumbing

Supply7-11 & Cleaners

Highlander Motel

Phase III East – Jackson Street

Wilson Boulevard Streetscape Improvements

Existing Conditions – Looking East

Phase III East – N.10th Street S

Wilson Boulevard Streetscape Improvements

Existing

Existing Conditions - Looking East

Phase III East – N. Ivy Street

Wilson Boulevard Streetscape Improvements

Existing Conditions – Looking East

Phase III East - Jackson,10th and N. Ivy Streets

Wilson Boulevard Streetscape Improvements –

ExistingGoodyear Tire and Auto

Pio Pio Chicken

Hess Gas StationUrgent Care

Used Cars

Used Cars

Phase III Center -

Wilson Boulevard Streetscape Improvements

Existing

Kenmore Street Intersections

Phase III Center – Kenmore Street Intersections

Wilson Boulevard Streetscape Improvements

Yellow represents proposed new alignment – No Z Burger easement.

Schedules/Next Steps:

Wilson Blvd. Phase III West

End of Presentation

Wilson Blvd. Phase III Center

Wilson Blvd. Phase III East

Construction will start at this

section and is anticipated to

begin in winter/spring 2019.

End of PresentationThank You!