Post on 10-May-2017
No
None
Required
None
Required
Type of Employee No. Rate/hr Total Cost
€17.21 €0.00
€16.69 €0.00
€15.66 €0.00
€15.14 €0.00
€13.77 €0.00
€5.73 €0.00
€8.61 €0.00
€12.91 €0.00
€15.49 €0.00
€0.00
Name No.
Cost per
Unit (Exl.
VAT) % Adj. Total Cost
€0.00
Name No.
Cost per
Unit (Exl.
VAT) % Adj. Total Cost
€0.00
€0.00
No
No
No
Contractor
Contractor's Personell
Ommission in Contract
Is the delay event the fault of:
Please Provide a Brief Desciption of the claim
Adjustment to Contract Sum Required
None Required
1
Enter the Information in the Indicated Field, Do not Proceed
with this Section
Given that no Similar Works Exist in the BOQ, this Delay will
Require a Complete Recalculation of Cost. Please enter the
Information required below for Labour, Material, Plant and
Design Costs as Shown.
All other values are automatically calculated as per the
current Construction Industry Registered Employment
Please select a value for the hourly rate of the
Craftsmen on this project.
(Craftsmen rate automatically set to min. of €17.21)
None Required
Re-Caluculated Cost of Activity
Please enter the required details in relation to materials
required for pallned works. All figures to be entered
exlcuding VAT. Percentage adj. as stated to in Schedule Part
2D must not be greater than 100%.
Please enter the required details in relation to plant required
for pallned works. All figures to be entered exlcuding VAT.
Percentage adj. as stated to in Schedule Part 2D must not be
greater than 100%.
Enter the Information in the Indicated Field,
Do not Proceed with this Section
Please Enter the ID Number from the BOQ
for the Activity to Replicate Here:
Please Enter the Proprtional Amount of These
Wokrs required in comparasion to the Amount
Already Listed in the BOQ. E.g. If the Delay
Requires 10 Days of an Activity which is Listed
as Taking 20 then enter 0.5 below (20/10 =
0.5).
Please Enter the Proprtional Amount of
These Wokrs required in comparasion to the
Amount Already Listed in the BOQ. E.g. If the
Delay Requires 10 Days of an Activity which
is Listed as Taking 20 then enter 0.5 below
(20/10 = 0.5).
Please Enter the Corelation Factor Between
these Works and Those Required. E.g. if the
Works required Here will cost 50% more
than that Listed in the BOQ the Enter 1.5
Below (If Left Blank = 1).
1
Re-Caluculated Cost of Activity
Adjustment to Contract Sum Required
Do the Additional Works Required Currently Exist within the Original BOQ?
Please Continue the Documentation of this Delay Event as indicated Below:
Cost of Labour
Craftsmen
Total Recalculated Cost of Section of Works
Total Adjustment to Contract Sum Required
Cost of Materials
Cost of Plant
None
Required
Technical Operative
Skilled Operative
Semi-Skilled Operative
Basic Operative
1st Year Apprentice
2nd Year Apprentice
3rd Year Apprentice
4th Year Apprentice
Total Cost of Plant
Cost of Design Works
Total Cost of Materials
Total Cost of Labour
Has an event occurred within this section of the project which
requires a delay/extension of time to be allowed for?
Delay Event 1
0
0
-3
Adustment to Period Allowed
Adjsutments to the Contract Sum
There are Three Accpetable to Calculate the Adjustment to Contract Sum Required for this Delay. Please Select One of these from the Dropdown Below.
Rule 1
Rule 2
Rule 3
D ≤ T1
T1 < D
D > (T1 + 2T2)
E=0
E=(D-T1)/2
E=D-T1-T2
0
0
3
Current Time for Completion:
Calculation of Adjustments Required to Schedule
No Need to Proceed With Documentation
Programme Contingency Calculations
Delay
Extension
First Threshold (T1 )
Second Threshold (T2)
No Further Action Required
Please Enter the ID Number from the BOQ for
the Activity to Replicate Here:
Enter the Information in the Indicated Field,
Do not Proceed with this Section
Name of Event in Question: Please Enter Item's Code Above
Extension of Time Required:
Adjustment to Contarct Sum Required:
Please Enter the Unque Code for the Item in Question:
Current Cost for Completion:
Please Enter Item's Code Above
Please Enter Item's Code Above
Adjusted Time for Completion:
Adjsuted Cost for Completion:
Please Enter Item's Code Above
Please Enter Item's Code Above
No
None
Required
None
Required
Type of Employee No. Rate/hr Total Cost
€17.21 €0.00
€16.69 €0.00
€15.66 €0.00
€15.14 €0.00
€13.77 €0.00
€5.73 €0.00
€8.61 €0.00
€12.91 €0.00
€15.49 €0.00
€0.00
Name No.
Cost per
Unit (Exl.
VAT) % Adj. Total Cost
€0.00
Name No.
Cost per
Unit (Exl.
VAT) % Adj. Total Cost
€0.00
€0.00
Please enter Item's Code Above
Adjusted Time for Completion: Please enter Item's Code Above
Adjsuted Cost for Completion: Please enter Item's Code Above
Is the delay event the fault of:
Contractor No
Contractor's Personell No
Ommission in Contract No
No Further Action Required
No Need to Proceed With Documentation
Please Provide a Brief Desciption of the claim
Calculation of Adjustments Required to Schedule
Adustment to Period Allowed
Programme Contingency Calculations
Delay
Please Enter the Unque Code for the Item in Question:
Name of Event in Question: Please enter Item's Code Above
Extension of Time Required:
Adjustment to Contarct Sum Required:
Current Time for Completion: Please enter Item's Code Above
Current Cost for Completion:
Extension 0
First Threshold (T1 )
Second Threshold (T2)
Rule 1 D ≤ T1 E=0 0
Adjsutments to the Contract Sum
There are Three Accpetable to Calculate the Adjustment to Contract Sum Required for this Delay. Please Select One of these from the Dropdown
Below.
Do the Additional Works Required Currently Exist within the Original BOQ?
Please Continue the Documentation of this Delay Event as indicated Below:
Enter the Information in the Indicated Field,
Do not Proceed with this Section
Enter the Information in the Indicated Field,
Do not Proceed with this Section
Enter the Information in the Indicated Field, Do not
Proceed with this Section
Rule 2 T1 < D E=(D-T1)/2 0
Rule 3 D > (T1 + 2T2) E=D-T1-T2 0
1 1
Re-Caluculated Cost of Activity
Please Enter the Corelation Factor Between
these Works and Those Required. E.g. if the
Works required Here will cost 50% more
than that Listed in the BOQ the Enter 1.5
Below (If Left Blank = 1).
Craftsmen
Technical Operative
Adjustment to Contract Sum Required Skilled Operative
None RequiredSemi-Skilled
Operative
Basic Operative
1st Year Apprentice
Given that no Similar Works Exist in the BOQ, this Delay
will Require a Complete Recalculation of Cost. Please
enter the Information required below for Labour,
Material, Plant and Design Costs as Shown.
Please Enter the ID Number from the BOQ
for the Activity to Replicate Here:
Please Enter the ID Number from the BOQ
for the Activity to Replicate Here:
Please Enter the Proprtional Amount of
These Wokrs required in comparasion to the
Amount Already Listed in the BOQ. E.g. If the
Delay Requires 10 Days of an Activity which
is Listed as Taking 20 then enter 0.5 below
(20/10 = 0.5).
Please Enter the Proprtional Amount of
These Wokrs required in comparasion to the
Amount Already Listed in the BOQ. E.g. If the
Delay Requires 10 Days of an Activity which
is Listed as Taking 20 then enter 0.5 below
(20/10 = 0.5).
Cost of Labour
Please select a value for the hourly rate of
the Craftsmen on this project.
All other values are automatically calculated as per the
current Construction Industry Registered Employment
(Craftsmen rate automatically set to min. of €17.21)
Cost of Materials
Total Cost of Materials
Please enter the required details in relation to plant
required for pallned works. All figures to be entered
exlcuding VAT. Percentage adj. as stated to in Schedule
Part 2D must not be greater than 100%.
Cost of Plant
Total Cost of Plant
Cost of Design Works
Total Recalculated Cost of Section of Works
Total Adjustment to Contract Sum Required
None
Required
1 2nd Year Apprentice
Re-Caluculated Cost of Activity 3rd Year Apprentice
4th Year Apprentice
Adjustment to Contract Sum Required Total Cost of Labour
None RequiredPlease enter the required details in relation to materials
required for pallned works. All figures to be entered
exlcuding VAT. Percentage adj. as stated to in Schedule
Part 2D must not be greater than 100%.
Has an event occurred within this section of the project which
requires a delay/extension of time to be allowed for?
Delay Event 2
No
None
Required
None
Required
Type of Employee No. Rate/hr Total Cost
€17.21 €0.00
€16.69 €0.00
€15.66 €0.00
€15.14 €0.00
€13.77 €0.00
€5.73 €0.00
€8.61 €0.00
€12.91 €0.00
€15.49 €0.00
€0.00
Name No.
Cost per
Unit (Exl.
VAT) % Adj. Total Cost
€0.00
Name No.
Cost per
Unit (Exl.
VAT) % Adj. Total Cost
€0.00
€0.00
No Further Action Required
No Need to Proceed With Documentation
Please Provide a Brief Desciption of the claim
Calculation of Adjustments Required to Schedule
Adustment to Period Allowed
Please Enter the Unque Code for the Item in Question:
Name of Event in Question: Please enter Item's Code Above
Extension of Time Required:
Adjustment to Contarct Sum Required:
Current Time for Completion: Please enter Item's Code Above
Current Cost for Completion: Please enter Item's Code Above
Adjusted Time for Completion: Please enter Item's Code Above
Adjsuted Cost for Completion: Please enter Item's Code Above
Is the delay event the fault of:
Contractor No
Contractor's Personell No
Ommission in Contract No
0
Adjsutments to the Contract Sum
There are Three Accpetable to Calculate the Adjustment to Contract Sum Required for this Delay. Please Select One of these from the Dropdown
Below.
Do the Additional Works Required Currently Exist within the Original BOQ?
Rule 1 D ≤ T1 E=0 0
Rule 2 T1 < D E=(D-T1)/2 0
Programme Contingency Calculations
Delay
Extension 0
First Threshold (T1 )
Second Threshold (T2)
Please Enter the Proprtional Amount of
These Wokrs required in comparasion to the
Amount Already Listed in the BOQ. E.g. If the
Delay Requires 10 Days of an Activity which
is Listed as Taking 20 then enter 0.5 below
(20/10 = 0.5).
Please Enter the Proprtional Amount of
These Wokrs required in comparasion to the
Amount Already Listed in the BOQ. E.g. If the
Delay Requires 10 Days of an Activity which
is Listed as Taking 20 then enter 0.5 below
(20/10 = 0.5).
Cost of Labour
Please select a value for the hourly rate of
the Craftsmen on this project.
All other values are automatically calculated as per the
current Construction Industry Registered Employment
(Craftsmen rate automatically set to min. of €17.21)
1 1
Re-Caluculated Cost of Activity
Please Enter the Corelation Factor Between
these Works and Those Required. E.g. if the
Works required Here will cost 50% more
than that Listed in the BOQ the Enter 1.5
Below (If Left Blank = 1).
Craftsmen
Technical Operative
Adjustment to Contract Sum Required Skilled Operative
None RequiredSemi-Skilled
Operative
Basic Operative
1st Year Apprentice
Total Cost of Materials
Please enter the required details in relation to plant
required for pallned works. All figures to be entered
exlcuding VAT. Percentage adj. as stated to in Schedule
Part 2D must not be greater than 100%.
Cost of Plant
Total Cost of Plant
Cost of Design Works
Total Recalculated Cost of Section of Works
Total Adjustment to Contract Sum Required
None
Required
1 2nd Year Apprentice
Re-Caluculated Cost of Activity 3rd Year Apprentice
4th Year Apprentice
Adjustment to Contract Sum Required Total Cost of Labour
None RequiredPlease enter the required details in relation to materials
required for pallned works. All figures to be entered
exlcuding VAT. Percentage adj. as stated to in Schedule
Part 2D must not be greater than 100%.
Cost of Materials
Please Continue the Documentation of this Delay Event as indicated Below:
Enter the Information in the Indicated Field,
Do not Proceed with this Section
Enter the Information in the Indicated Field,
Do not Proceed with this Section
Enter the Information in the Indicated Field, Do not
Proceed with this Section
Given that no Similar Works Exist in the BOQ, this Delay
will Require a Complete Recalculation of Cost. Please
enter the Information required below for Labour,
Material, Plant and Design Costs as Shown.
Please Enter the ID Number from the BOQ
for the Activity to Replicate Here:
Please Enter the ID Number from the BOQ
for the Activity to Replicate Here:
Rule 3 D > (T1 + 2T2) E=D-T1-T2
Has an event occurred within this section of the project which
requires a delay/extension of time to be allowed for?
Delay Event 3
No
None
Required
None
Required
Type of Employee No. Rate/hr Total Cost
€17.21 €0.00
€16.69 €0.00
€15.66 €0.00
€15.14 €0.00
€13.77 €0.00
€5.73 €0.00
€8.61 €0.00
€12.91 €0.00
€15.49 €0.00
€0.00
Name No.
Cost per
Unit (Exl.
VAT) % Adj. Total Cost
€0.00
Name No.
Cost per
Unit (Exl.
VAT) % Adj. Total Cost
€0.00
€0.00
Current Time for Completion: Please enter Item's Code Above
Current Cost for Completion: Please enter Item's Code Above
Adjusted Time for Completion: Please enter Item's Code Above
Adjsuted Cost for Completion: Please enter Item's Code Above
Is the delay event the fault of:
Contractor No
Contractor's Personell No
Ommission in Contract No
Please Enter the Unque Code for the Item in Question:
Name of Event in Question: Please enter Item's Code Above
Extension of Time Required:
Adjustment to Contarct Sum Required:
Programme Contingency Calculations
Delay
Extension 0
First Threshold (T1 )
Second Threshold (T2)
No Further Action Required
No Need to Proceed With Documentation
Please Provide a Brief Desciption of the claim
Calculation of Adjustments Required to Schedule
Adustment to Period Allowed
Rule 3 D > (T1 + 2T2) E=D-T1-T2 0
Adjsutments to the Contract Sum
There are Three Accpetable to Calculate the Adjustment to Contract Sum Required for this Delay. Please Select One of these from the Dropdown
Below.
Do the Additional Works Required Currently Exist within the Original BOQ?
Rule 1 D ≤ T1 E=0 0
Rule 2 T1 < D E=(D-T1)/2 0
All other values are automatically calculated as per the
current Construction Industry Registered Employment
(Craftsmen rate automatically set to min. of €17.21)
1 1
Re-Caluculated Cost of Activity
Please Enter the Corelation Factor Between
these Works and Those Required. E.g. if the
Works required Here will cost 50% more
than that Listed in the BOQ the Enter 1.5
Below (If Left Blank = 1).
Craftsmen
Technical Operative
Adjustment to Contract Sum Required Skilled Operative
None RequiredSemi-Skilled
Operative
Basic Operative
1st Year Apprentice
Please Continue the Documentation of this Delay Event as indicated Below:
Enter the Information in the Indicated Field,
Do not Proceed with this Section
Enter the Information in the Indicated Field,
Do not Proceed with this Section
Enter the Information in the Indicated Field, Do not
Proceed with this Section
Given that no Similar Works Exist in the BOQ, this Delay
will Require a Complete Recalculation of Cost. Please
enter the Information required below for Labour,
Material, Plant and Design Costs as Shown.
Please Enter the ID Number from the BOQ
for the Activity to Replicate Here:
Please Enter the ID Number from the BOQ
for the Activity to Replicate Here:
Has an event occurred within this section of the project which
requires a delay/extension of time to be allowed for?
Cost of Materials
Total Cost of Materials
Please enter the required details in relation to plant
required for pallned works. All figures to be entered
exlcuding VAT. Percentage adj. as stated to in Schedule
Part 2D must not be greater than 100%.
Cost of Plant
Total Cost of Plant
Cost of Design Works
Total Recalculated Cost of Section of Works
Total Adjustment to Contract Sum Required
None
Required
1 2nd Year Apprentice
Re-Caluculated Cost of Activity 3rd Year Apprentice
4th Year Apprentice
Adjustment to Contract Sum Required Total Cost of Labour
None RequiredPlease enter the required details in relation to materials
required for pallned works. All figures to be entered
exlcuding VAT. Percentage adj. as stated to in Schedule
Part 2D must not be greater than 100%.
Please Enter the Proprtional Amount of
These Wokrs required in comparasion to the
Amount Already Listed in the BOQ. E.g. If the
Delay Requires 10 Days of an Activity which
is Listed as Taking 20 then enter 0.5 below
(20/10 = 0.5).
Please Enter the Proprtional Amount of
These Wokrs required in comparasion to the
Amount Already Listed in the BOQ. E.g. If the
Delay Requires 10 Days of an Activity which
is Listed as Taking 20 then enter 0.5 below
(20/10 = 0.5).
Cost of Labour
Please select a value for the hourly rate of
the Craftsmen on this project.
Delay Event 4
No
None
Required
None
Required
Type of Employee No. Rate/hr Total Cost
€17.21 €0.00
€16.69 €0.00
€15.66 €0.00
€15.14 €0.00
€13.77 €0.00
€5.73 €0.00
€8.61 €0.00
€12.91 €0.00
€15.49 €0.00
€0.00
Name No.
Cost per
Unit (Exl.
VAT) % Adj. Total Cost
€0.00
Name No.
Cost per
Unit (Exl.
VAT) % Adj. Total Cost
€0.00
€0.00
No
Current Time for Completion: Please enter Item's Code Above
Current Cost for Completion: Please enter Item's Code Above
Adjusted Time for Completion: Please enter Item's Code Above
Adjsuted Cost for Completion: Please enter Item's Code Above
Is the delay event the fault of:
Has an event occurred within this section of the project which
requires a delay/extension of time to be allowed for?
Please Enter the Unque Code for the Item in Question:
Name of Event in Question: Please enter Item's Code Above
No Further Action Required
No Need to Proceed With Documentation
Please Provide a Brief Desciption of the claim
Calculation of Adjustments Required to Schedule
Adustment to Period Allowed
Extension of Time Required:
Adjustment to Contarct Sum Required:
Rule 1 D ≤ T1 E=0 0
Rule 2 T1 < D E=(D-T1)/2 0
Programme Contingency Calculations
Delay
Extension 0
First Threshold (T1 )
Second Threshold (T2)
Contractor No
Contractor's Personell No
Ommission in Contract
Please Continue the Documentation of this Delay Event as indicated Below:
Enter the Information in the Indicated Field,
Do not Proceed with this Section
Enter the Information in the Indicated Field,
Do not Proceed with this Section
Enter the Information in the Indicated Field, Do not
Proceed with this Section
Given that no Similar Works Exist in the BOQ, this Delay
will Require a Complete Recalculation of Cost. Please
enter the Information required below for Labour,
Material, Plant and Design Costs as Shown.
Please Enter the ID Number from the BOQ
for the Activity to Replicate Here:
Please Enter the ID Number from the BOQ
for the Activity to Replicate Here:
Rule 3 D > (T1 + 2T2) E=D-T1-T2 0
Adjsutments to the Contract Sum
There are Three Accpetable to Calculate the Adjustment to Contract Sum Required for this Delay. Please Select One of these from the Dropdown
Below.
Do the Additional Works Required Currently Exist within the Original BOQ?
Please Enter the Proprtional Amount of
These Wokrs required in comparasion to the
Amount Already Listed in the BOQ. E.g. If the
Delay Requires 10 Days of an Activity which
is Listed as Taking 20 then enter 0.5 below
(20/10 = 0.5).
Please Enter the Proprtional Amount of
These Wokrs required in comparasion to the
Amount Already Listed in the BOQ. E.g. If the
Delay Requires 10 Days of an Activity which
is Listed as Taking 20 then enter 0.5 below
(20/10 = 0.5).
Cost of Labour
Please select a value for the hourly rate of
the Craftsmen on this project.
All other values are automatically calculated as per the
current Construction Industry Registered Employment
(Craftsmen rate automatically set to min. of €17.21)
1 1
Re-Caluculated Cost of Activity
Please Enter the Corelation Factor Between
these Works and Those Required. E.g. if the
Works required Here will cost 50% more
than that Listed in the BOQ the Enter 1.5
Below (If Left Blank = 1).
Craftsmen
Technical Operative
Adjustment to Contract Sum Required Skilled Operative
None RequiredSemi-Skilled
Operative
Basic Operative
1st Year Apprentice
Cost of Materials
Total Cost of Materials
Please enter the required details in relation to plant
required for pallned works. All figures to be entered
exlcuding VAT. Percentage adj. as stated to in Schedule
Part 2D must not be greater than 100%.
Cost of Plant
Total Cost of Plant
Cost of Design Works
Total Recalculated Cost of Section of Works
Total Adjustment to Contract Sum Required
None
Required
1 2nd Year Apprentice
Re-Caluculated Cost of Activity 3rd Year Apprentice
4th Year Apprentice
Adjustment to Contract Sum Required Total Cost of Labour
None RequiredPlease enter the required details in relation to materials
required for pallned works. All figures to be entered
exlcuding VAT. Percentage adj. as stated to in Schedule
Part 2D must not be greater than 100%.
Delay Event 5
No
None
Required
None
Required
Type of Employee No. Rate/hr Total Cost
€17.21 €0.00
€16.69 €0.00
€15.66 €0.00
€15.14 €0.00
€13.77 €0.00
€5.73 €0.00
€8.61 €0.00
€12.91 €0.00
€15.49 €0.00
€0.00
Name No.
Cost per
Unit (Exl.
VAT) % Adj. Total Cost
€0.00
Name No.
Cost per
Unit (Exl.
VAT) % Adj. Total Cost
€0.00
€0.00
No
Has an event occurred within this section of the project which
requires a delay/extension of time to be allowed for?
Please Enter the Unque Code for the Item in Question:
Name of Event in Question: Please enter Item's Code Above
Extension of Time Required:
Adjustment to Contarct Sum Required:
Current Time for Completion: Please enter Item's Code Above
Current Cost for Completion: Please enter Item's Code Above
Adjusted Time for Completion: Please enter Item's Code Above
Adjsuted Cost for Completion: Please enter Item's Code Above
Is the delay event the fault of:
Contractor No
Contractor's Personell No
Ommission in Contract
Delay
Extension 0
First Threshold (T1 )
Second Threshold (T2)
No Further Action Required
No Need to Proceed With Documentation
Please Provide a Brief Desciption of the claim
Calculation of Adjustments Required to Schedule
Adustment to Period Allowed
Programme Contingency Calculations
Adjsutments to the Contract Sum
There are Three Accpetable to Calculate the Adjustment to Contract Sum Required for this Delay. Please Select One of these from the Dropdown
Below.
Do the Additional Works Required Currently Exist within the Original BOQ?
Please Continue the Documentation of this Delay Event as indicated Below:
Enter the Information in the Indicated Field,
Do not Proceed with this Section
Enter the Information in the Indicated Field,
Do not Proceed with this Section
Enter the Information in the Indicated Field, Do not
Proceed with this Section
Rule 1 D ≤ T1 E=0 0
Rule 2 T1 < D E=(D-T1)/2 0
Rule 3 D > (T1 + 2T2) E=D-T1-T2 0
1 1
Re-Caluculated Cost of Activity
Please Enter the Corelation Factor Between
these Works and Those Required. E.g. if the
Works required Here will cost 50% more
than that Listed in the BOQ the Enter 1.5
Below (If Left Blank = 1).
Craftsmen
Technical Operative
Adjustment to Contract Sum Required Skilled Operative
None RequiredSemi-Skilled
Operative
Basic Operative
1st Year Apprentice
Given that no Similar Works Exist in the BOQ, this Delay
will Require a Complete Recalculation of Cost. Please
enter the Information required below for Labour,
Material, Plant and Design Costs as Shown.
Please Enter the ID Number from the BOQ
for the Activity to Replicate Here:
Please Enter the ID Number from the BOQ
for the Activity to Replicate Here:
Please Enter the Proprtional Amount of
These Wokrs required in comparasion to the
Amount Already Listed in the BOQ. E.g. If the
Delay Requires 10 Days of an Activity which
is Listed as Taking 20 then enter 0.5 below
(20/10 = 0.5).
Please Enter the Proprtional Amount of
These Wokrs required in comparasion to the
Amount Already Listed in the BOQ. E.g. If the
Delay Requires 10 Days of an Activity which
is Listed as Taking 20 then enter 0.5 below
(20/10 = 0.5).
Cost of Labour
Please select a value for the hourly rate of
the Craftsmen on this project.
All other values are automatically calculated as per the
current Construction Industry Registered Employment
(Craftsmen rate automatically set to min. of €17.21)
Cost of Materials
Total Cost of Materials
Please enter the required details in relation to plant
required for pallned works. All figures to be entered
exlcuding VAT. Percentage adj. as stated to in Schedule
Part 2D must not be greater than 100%.
Cost of Plant
Total Cost of Plant
Cost of Design Works
Total Recalculated Cost of Section of Works
Total Adjustment to Contract Sum Required
None
Required
1 2nd Year Apprentice
Re-Caluculated Cost of Activity 3rd Year Apprentice
4th Year Apprentice
Adjustment to Contract Sum Required Total Cost of Labour
None RequiredPlease enter the required details in relation to materials
required for pallned works. All figures to be entered
exlcuding VAT. Percentage adj. as stated to in Schedule
Part 2D must not be greater than 100%.
Delay Event 6
No
None
Required
None
Required
Type of Employee No. Rate/hr Total Cost
€17.21 €0.00
€16.69 €0.00
€15.66 €0.00
€15.14 €0.00
€13.77 €0.00
€5.73 €0.00
€8.61 €0.00
€12.91 €0.00
€15.49 €0.00
€0.00
Name No.
Cost per
Unit (Exl.
VAT) % Adj. Total Cost
€0.00
Name No.
Cost per
Unit (Exl.
VAT) % Adj. Total Cost
€0.00
€0.00
Current Time for Completion: Please enter Item's Code Above
Current Cost for Completion: Please enter Item's Code Above
Adjusted Time for Completion: Please enter Item's Code Above
Adjsuted Cost for Completion: Please enter Item's Code Above
Is the delay event the fault of:
Contractor No
Contractor's Personell No
Ommission in Contract
Has an event occurred within this section of the project which
requires a delay/extension of time to be allowed for?
Please Enter the Unque Code for the Item in Question:
Name of Event in Question: Please enter Item's Code Above
Extension of Time Required:
Adjustment to Contarct Sum Required:
Delay
Extension 0
First Threshold (T1 )
Second Threshold (T2)
No Further Action Required
No Need to Proceed With Documentation
Please Provide a Brief Desciption of the claim
Calculation of Adjustments Required to Schedule
Adustment to Period Allowed
Programme Contingency Calculations
No
Adjsutments to the Contract Sum
There are Three Accpetable to Calculate the Adjustment to Contract Sum Required for this Delay. Please Select One of these from the Dropdown
Below.
Do the Additional Works Required Currently Exist within the Original BOQ?
Please Continue the Documentation of this Delay Event as indicated Below:
Enter the Information in the Indicated Field,
Do not Proceed with this Section
Enter the Information in the Indicated Field,
Do not Proceed with this Section
Enter the Information in the Indicated Field, Do not
Proceed with this Section
Rule 1 D ≤ T1 E=0 0
Rule 2 T1 < D E=(D-T1)/2 0
Rule 3 D > (T1 + 2T2) E=D-T1-T2 0
1 1
Re-Caluculated Cost of Activity
Please Enter the Corelation Factor Between
these Works and Those Required. E.g. if the
Works required Here will cost 50% more
than that Listed in the BOQ the Enter 1.5
Below (If Left Blank = 1).
Craftsmen
Technical Operative
Adjustment to Contract Sum Required Skilled Operative
None RequiredSemi-Skilled
Operative
Basic Operative
1st Year Apprentice
Given that no Similar Works Exist in the BOQ, this Delay
will Require a Complete Recalculation of Cost. Please
enter the Information required below for Labour,
Material, Plant and Design Costs as Shown.
Please Enter the ID Number from the BOQ
for the Activity to Replicate Here:
Please Enter the ID Number from the BOQ
for the Activity to Replicate Here:
Please Enter the Proprtional Amount of
These Wokrs required in comparasion to the
Amount Already Listed in the BOQ. E.g. If the
Delay Requires 10 Days of an Activity which
is Listed as Taking 20 then enter 0.5 below
(20/10 = 0.5).
Please Enter the Proprtional Amount of
These Wokrs required in comparasion to the
Amount Already Listed in the BOQ. E.g. If the
Delay Requires 10 Days of an Activity which
is Listed as Taking 20 then enter 0.5 below
(20/10 = 0.5).
Cost of Labour
Please select a value for the hourly rate of
the Craftsmen on this project.
All other values are automatically calculated as per the
current Construction Industry Registered Employment
(Craftsmen rate automatically set to min. of €17.21)
Cost of Materials
Total Cost of Materials
Please enter the required details in relation to plant
required for pallned works. All figures to be entered
exlcuding VAT. Percentage adj. as stated to in Schedule
Part 2D must not be greater than 100%.
Cost of Plant
Total Cost of Plant
Cost of Design Works
Total Recalculated Cost of Section of Works
Total Adjustment to Contract Sum Required
None
Required
1 2nd Year Apprentice
Re-Caluculated Cost of Activity 3rd Year Apprentice
4th Year Apprentice
Adjustment to Contract Sum Required Total Cost of Labour
None RequiredPlease enter the required details in relation to materials
required for pallned works. All figures to be entered
exlcuding VAT. Percentage adj. as stated to in Schedule
Part 2D must not be greater than 100%.
Delay Event 7
No
None
Required
None
Required
Type of Employee No. Rate/hr Total Cost
€17.21 €0.00
€16.69 €0.00
€15.66 €0.00
€15.14 €0.00
€13.77 €0.00
€5.73 €0.00
€8.61 €0.00
€12.91 €0.00
€15.49 €0.00
€0.00
Name No.
Cost per
Unit (Exl.
VAT) % Adj. Total Cost
€0.00
Name No.
Cost per
Unit (Exl.
VAT) % Adj. Total Cost
€0.00
€0.00
Current Time for Completion:
Current Cost for Completion:
Adjusted Time for Completion:
Adjsuted Cost for Completion:
Is the delay event the fault of:
Contractor
Contractor's Personell
Ommission in Contract
Has an event occurred within this section of the project which
requires a delay/extension of time to be allowed for?
Please Enter the Unque Code for the Item in Question:
Name of Event in Question: Please enter Item's Code Above
Extension of Time Required:
Adjustment to Contarct Sum Required:
Please enter Item's Code Above
Please enter Item's Code Above
Please enter Item's Code Above
Please enter Item's Code Above
No
No
No
Delay
Extension 0
First Threshold (T1 )
Second Threshold (T2)
No Further Action Required
No Need to Proceed With Documentation
Please Provide a Brief Desciption of the claim
Calculation of Adjustments Required to Schedule
Adustment to Period Allowed
Programme Contingency Calculations
Adjsutments to the Contract Sum
There are Three Accpetable to Calculate the Adjustment to Contract Sum Required for this Delay. Please Select One of these from the Dropdown
Below.
Do the Additional Works Required Currently Exist within the Original BOQ?
Please Continue the Documentation of this Delay Event as indicated Below:
Enter the Information in the Indicated Field,
Do not Proceed with this Section
Enter the Information in the Indicated Field,
Do not Proceed with this Section
Enter the Information in the Indicated Field, Do not
Proceed with this Section
Rule 1 D ≤ T1 E=0 0
Rule 2 T1 < D E=(D-T1)/2 0
Rule 3 D > (T1 + 2T2) E=D-T1-T2 0
1 1
Re-Caluculated Cost of Activity
Please Enter the Corelation Factor Between
these Works and Those Required. E.g. if the
Works required Here will cost 50% more
than that Listed in the BOQ the Enter 1.5
Below (If Left Blank = 1).
Craftsmen
Technical Operative
Adjustment to Contract Sum Required Skilled Operative
None RequiredSemi-Skilled
Operative
Basic Operative
1st Year Apprentice
Given that no Similar Works Exist in the BOQ, this Delay
will Require a Complete Recalculation of Cost. Please
enter the Information required below for Labour,
Material, Plant and Design Costs as Shown.
Please Enter the ID Number from the BOQ
for the Activity to Replicate Here:
Please Enter the ID Number from the BOQ
for the Activity to Replicate Here:
Please Enter the Proprtional Amount of
These Wokrs required in comparasion to the
Amount Already Listed in the BOQ. E.g. If the
Delay Requires 10 Days of an Activity which
is Listed as Taking 20 then enter 0.5 below
(20/10 = 0.5).
Please Enter the Proprtional Amount of
These Wokrs required in comparasion to the
Amount Already Listed in the BOQ. E.g. If the
Delay Requires 10 Days of an Activity which
is Listed as Taking 20 then enter 0.5 below
(20/10 = 0.5).
Cost of Labour
Please select a value for the hourly rate of
the Craftsmen on this project.
All other values are automatically calculated as per the
current Construction Industry Registered Employment
(Craftsmen rate automatically set to min. of €17.21)
Cost of Materials
Total Cost of Materials
Please enter the required details in relation to plant
required for pallned works. All figures to be entered
exlcuding VAT. Percentage adj. as stated to in Schedule
Part 2D must not be greater than 100%.
Cost of Plant
Total Cost of Plant
Cost of Design Works
Total Recalculated Cost of Section of Works
Total Adjustment to Contract Sum Required
None
Required
1 2nd Year Apprentice
Re-Caluculated Cost of Activity 3rd Year Apprentice
4th Year Apprentice
Adjustment to Contract Sum Required Total Cost of Labour
None RequiredPlease enter the required details in relation to materials
required for pallned works. All figures to be entered
exlcuding VAT. Percentage adj. as stated to in Schedule
Part 2D must not be greater than 100%.
Delay Event 8
No
None
Required
None
Required
Type of Employee No. Rate/hr Total Cost
€17.21 €0.00
€16.69 €0.00
€15.66 €0.00
€15.14 €0.00
€13.77 €0.00
€5.73 €0.00
€8.61 €0.00
€12.91 €0.00
€15.49 €0.00
€0.00
Name No.
Cost per
Unit (Exl.
VAT) % Adj. Total Cost
€0.00
Name No.
Cost per
Unit (Exl.
VAT) % Adj. Total Cost
€0.00
€0.00
No
Has an event occurred within this section of the project which
requires a delay/extension of time to be allowed for?
Please Enter the Unque Code for the Item in Question:
Name of Event in Question: Please enter Item's Code Above
Extension of Time Required:
Adjustment to Contarct Sum Required:
Current Time for Completion: Please enter Item's Code Above
Current Cost for Completion: Please enter Item's Code Above
Adjusted Time for Completion: Please enter Item's Code Above
Adjsuted Cost for Completion: Please enter Item's Code Above
Is the delay event the fault of:
Contractor No
Contractor's Personell No
Ommission in Contract
Delay
Extension 0
First Threshold (T1 )
Second Threshold (T2)
No Further Action Required
No Need to Proceed With Documentation
Please Provide a Brief Desciption of the claim
Calculation of Adjustments Required to Schedule
Adustment to Period Allowed
Programme Contingency Calculations
Adjsutments to the Contract Sum
There are Three Accpetable to Calculate the Adjustment to Contract Sum Required for this Delay. Please Select One of these from the Dropdown
Below.
Do the Additional Works Required Currently Exist within the Original BOQ?
Please Continue the Documentation of this Delay Event as indicated Below:
Enter the Information in the Indicated Field,
Do not Proceed with this Section
Enter the Information in the Indicated Field,
Do not Proceed with this Section
Enter the Information in the Indicated Field, Do not
Proceed with this Section
Rule 1 D ≤ T1 E=0 0
Rule 2 T1 < D E=(D-T1)/2 0
Rule 3 D > (T1 + 2T2) E=D-T1-T2 0
1 1
Re-Caluculated Cost of Activity
Please Enter the Corelation Factor Between
these Works and Those Required. E.g. if the
Works required Here will cost 50% more
than that Listed in the BOQ the Enter 1.5
Below (If Left Blank = 1).
Craftsmen
Technical Operative
Adjustment to Contract Sum Required Skilled Operative
None RequiredSemi-Skilled
Operative
Basic Operative
1st Year Apprentice
Given that no Similar Works Exist in the BOQ, this Delay
will Require a Complete Recalculation of Cost. Please
enter the Information required below for Labour,
Material, Plant and Design Costs as Shown.
Please Enter the ID Number from the BOQ
for the Activity to Replicate Here:
Please Enter the ID Number from the BOQ
for the Activity to Replicate Here:
Please Enter the Proprtional Amount of
These Wokrs required in comparasion to the
Amount Already Listed in the BOQ. E.g. If the
Delay Requires 10 Days of an Activity which
is Listed as Taking 20 then enter 0.5 below
(20/10 = 0.5).
Please Enter the Proprtional Amount of
These Wokrs required in comparasion to the
Amount Already Listed in the BOQ. E.g. If the
Delay Requires 10 Days of an Activity which
is Listed as Taking 20 then enter 0.5 below
(20/10 = 0.5).
Cost of Labour
Please select a value for the hourly rate of
the Craftsmen on this project.
All other values are automatically calculated as per the
current Construction Industry Registered Employment
(Craftsmen rate automatically set to min. of €17.21)
Cost of Materials
Total Cost of Materials
Please enter the required details in relation to plant
required for pallned works. All figures to be entered
exlcuding VAT. Percentage adj. as stated to in Schedule
Part 2D must not be greater than 100%.
Cost of Plant
Total Cost of Plant
Cost of Design Works
Total Recalculated Cost of Section of Works
Total Adjustment to Contract Sum Required
None
Required
1 2nd Year Apprentice
Re-Caluculated Cost of Activity 3rd Year Apprentice
4th Year Apprentice
Adjustment to Contract Sum Required Total Cost of Labour
None RequiredPlease enter the required details in relation to materials
required for pallned works. All figures to be entered
exlcuding VAT. Percentage adj. as stated to in Schedule
Part 2D must not be greater than 100%.
Delay Event 9
No
None
Required
None
Required
Type of Employee No. Rate/hr Total Cost
€17.21 €0.00
€16.69 €0.00
€15.66 €0.00
€15.14 €0.00
€13.77 €0.00
€5.73 €0.00
€8.61 €0.00
€12.91 €0.00
€15.49 €0.00
€0.00
Name No.
Cost per
Unit (Exl.
VAT) % Adj. Total Cost
€0.00
Name No.
Cost per
Unit (Exl.
VAT) % Adj. Total Cost
€0.00
€0.00
Current Time for Completion: Please enter Item's Code Above
Current Cost for Completion: Please enter Item's Code Above
Adjusted Time for Completion: Please enter Item's Code Above
Adjsuted Cost for Completion: Please enter Item's Code Above
Is the delay event the fault of:
Contractor No
Contractor's Personell No
Ommission in Contract No
Has an event occurred within this section of the project which
requires a delay/extension of time to be allowed for?
Please Enter the Unque Code for the Item in Question:
Name of Event in Question: Please enter Item's Code Above
Extension of Time Required:
Adjustment to Contarct Sum Required:
Delay
Extension 0
First Threshold (T1 )
Second Threshold (T2)
No Further Action Required
No Need to Proceed With Documentation
Please Provide a Brief Desciption of the claim
Calculation of Adjustments Required to Schedule
Adustment to Period Allowed
Programme Contingency Calculations
Adjsutments to the Contract Sum
There are Three Accpetable to Calculate the Adjustment to Contract Sum Required for this Delay. Please Select One of these from the Dropdown
Below.
Do the Additional Works Required Currently Exist within the Original BOQ?
Please Continue the Documentation of this Delay Event as indicated Below:
Enter the Information in the Indicated Field,
Do not Proceed with this Section
Enter the Information in the Indicated Field,
Do not Proceed with this Section
Enter the Information in the Indicated Field, Do not
Proceed with this Section
Rule 1 D ≤ T1 E=0 0
Rule 2 T1 < D E=(D-T1)/2 0
Rule 3 D > (T1 + 2T2) E=D-T1-T2 0
Re-Caluculated Cost of Activity
Please Enter the Corelation Factor Between
these Works and Those Required. E.g. if the
Works required Here will cost 50% more
than that Listed in the BOQ the Enter 1.5
Below (If Left Blank = 1).
Craftsmen
Technical Operative
Adjustment to Contract Sum Required Skilled Operative
None RequiredSemi-Skilled
Operative
Basic Operative
1st Year Apprentice
Given that no Similar Works Exist in the BOQ, this Delay
will Require a Complete Recalculation of Cost. Please
enter the Information required below for Labour,
Material, Plant and Design Costs as Shown.
Please Enter the ID Number from the BOQ
for the Activity to Replicate Here:
Please Enter the ID Number from the BOQ
for the Activity to Replicate Here:
Please Enter the Proprtional Amount of
These Wokrs required in comparasion to the
Amount Already Listed in the BOQ. E.g. If the
Delay Requires 10 Days of an Activity which
is Listed as Taking 20 then enter 0.5 below
(20/10 = 0.5).
Please Enter the Proprtional Amount of
These Wokrs required in comparasion to the
Amount Already Listed in the BOQ. E.g. If the
Delay Requires 10 Days of an Activity which
is Listed as Taking 20 then enter 0.5 below
(20/10 = 0.5).
Cost of Labour
Please select a value for the hourly rate of
the Craftsmen on this project.
All other values are automatically calculated as per the
current Construction Industry Registered Employment
(Craftsmen rate automatically set to min. of €17.21)
Delay Event 10
Cost of Materials
Total Cost of Materials
Please enter the required details in relation to plant
required for pallned works. All figures to be entered
exlcuding VAT. Percentage adj. as stated to in Schedule
Part 2D must not be greater than 100%.
Cost of Plant
Total Cost of Plant
Cost of Design Works
Total Recalculated Cost of Section of Works
Total Adjustment to Contract Sum Required
None
Required
1 2nd Year Apprentice
Re-Caluculated Cost of Activity 3rd Year Apprentice
4th Year Apprentice
Adjustment to Contract Sum Required Total Cost of Labour
None RequiredPlease enter the required details in relation to materials
required for pallned works. All figures to be entered
exlcuding VAT. Percentage adj. as stated to in Schedule
Part 2D must not be greater than 100%.
1 1