Post on 04-Jun-2018
8/13/2019 Cost Adjustment Guidelines
1/25
COST ADJUSTMENT
Page 1 of 25
COST ADJUSTMENT GUIDELINES
CONTENTS
CONTENTS.................................................................................................................................. 1
1 Introduction.............................................................................................................................. 3
1.1 Risks of Rise and Fall in Costs............................................................................................ ............ 3
1.2 Items to which cost adjustment might apply........................................................... ...................... 3
1.3 Purpose of these guidelines .......................................................... ................................................... 3
1.4 NSW Government requirements........................................................... ......................................... 3
1.5 ABS Indexes and proportions for common categories of work .................................................. .. 4
2. Contractual provisions for cost adjustment for labour and material ................................ 4
2.1 Cost Adjustment for Construction Contracts ......................................................... ...................... 4
2.2 Cost Adjustment for Long Term Service Contracts........ ........................................................... .. 4
2.3 Application of cost adjustment to specific subcontracts or work packages, and to multiple
categories of work.................... ............................................................ ................................................... 4
2.4 Dates for Base Index Number and Current Index Number............................................. ............ 5
2.5 Contractors' claims for cost adjustment................. ........................................................... ............ 5
2.6. Administration of cost adjustment claims ..................................................... ............................... 5
2.7. Worked examples of cost adjustment for labour and materials............................................... .. 5
3. Cost adjustment for other than labour and materials ......................................................... 6
3.1 Cost adjustment for fluctuations in currency exchange rates ................................................... .. 6
3.2 Cost adjustment for duties and taxes.................................................... ......................................... 6
3.3 Other cost adjustment ......................................................... ........................................................... .. 6
Appendix A - INDEXES AND PROPORTIONS FOR COMMON CATEGORIES OF
WORK....................................................................................................................................7
Appendix B - COST ADJUSTMENT PROVISIONS...........................................................8
Appendix C - COST ADJUSTMENT TABLE - ARCHITECTURAL (BUILDING) WORKS
................................................................................................................................................9
Appendix D - COST ADJUSTMENT TABLE - CIVIL WORKS ......................................10
Appendix E - COST ADJUSTMENT TABLE - MECHANICAL SERVICES INVOLVING
MAINLY PROPRIETARY OR PREFABRICATED COMPONENTS, SUCH AS
COMMUNICATIONS, PABX AND AIR CONDITIONING ............................................11
Appendix F - COST ADJUSTMENT TABLE - MECHANICAL SERVICES OTHER THAN
THOSE INVOLVING MAINLY PROPRIETARY OR PREFABRICATED COMPONENTS
..............................................................................................................................................12
Appendix G - COST ADJUSTMENT TABLE - ELECTRICAL ENGINEERING WORK13
8/13/2019 Cost Adjustment Guidelines
2/25
COST ADJUSTMENT
Page 2 of 25
Appendix H - COST ADJUSTMENT TABLE - MAINTENANCE INVOLVING
EXTENSIVE MAJOR COMPONENT REPLACEMENT SUCH AS LIFT MAINTENANCE
..............................................................................................................................................14
Appendix I - COST ADJUSTMENT TABLE - MAINTENANCE NOT INVOLVING
EXTENSIVE MAJOR COMPONENT REPLACEMENT .................................................15
Appendix J - COST ADJUSTMENT TABLE - CONSTRUCTION OR PROJECT
MANAGEMENT.................................................................................................................16
Appendix K - EXAMPLE COST ADJUSTMENT TABLE - COMBINATION OF CIVIL
WORKS AND PREFABRICATED ARTICLES ................................................................17
Appendix L - EXAMPLE COST ADJUSTMENT TABLE - TWO CATEGORIES OF
WORK - CIVIL WORKS AND ELECTRICAL ENGINEERING WORKS......................18
Appendix M - LONG TERM SERVICE CONTRACT - ANNUAL COST ADJUSTMENT
TO RATES PRELIMINARIES CLAUSE...........................................................................20
Appendix N - WORKED EXAMPLE OF COST ADJUSTMENT.....................................21
Introduction................................................................................................................................ 21
Tender and Contract Details..................................................................................................... 21
CA Details Derived from Contract Details and Relevant ABS Indexes................................ 21
Claims and Cost Adjustment .................................................................................................... 22
Appendix O - SAMPLE COPIES OF ABS INDEXES .......................................................24
ABS 6345.0 Labour Cost Index Table 11 September Quarter 2004 ..................................... 24
ABS 6345.0 Labour Cost Index Table 11 June Quarter 2005................................................ 24
ABS 6427.0 Producer Price Index Table 17 September Quarter 2005 ................................. 25
8/13/2019 Cost Adjustment Guidelines
3/25
COST ADJUSTMENT
Page 3 of 25
1 Introduction
1.1 Risks of Rise and Fall in Costs
There is a risk that, during the course of a contract, the costs of performing a contract will change fromthose initially estimated. This risk is not directly controllable by either the Principal or the contractor.
Contractors may have difficulty in estimating the long term effects of changes in costs and may:
price tenders conservatively, leading to unnecessarily high contract prices; or
guess or gamble on the effects of changes in costs, leading to tender prices that are either
excessive, or uneconomically low (with consequent risk of financial failure of the contractor).
Cost adjustment provisions in contracts address this risk by providing mechanisms for adjusting
contract payments to reflect changes in costs.
Cost adjustment provisions apply only to long term costs and some specific costs. Contractors retain
the risk of short term fluctuations in costs, and the risk of the calculated cost adjustment not reflecting
actual changes in costs.
1.2 Items to which cost adjustment might apply
Cost adjustment may be applied to the following:
labour and materials costs,
currency exchange rates for goods purchased in foreign currency,
other costs, including
- duties and taxes,
- shipping and transport.In normal contracting strategies, cost adjustment provisions should only be applicable to costs,
typically long term costs, that might cause tenderers to overestimate or uneconomically underestimate
contract prices.
1.3 Purpose of these guidelines
The purpose of these guidelines is to briefly explain cost adjustment, and provide sample Cost
Adjustment provisions for inclusion in contracts where required.
1.4 NSW Government requirements
For consistency, the following should apply to all contracts used by NSW Government agencies:
Cost adjustment for labour and material should normally not apply in construction contracts less
than 52 weeks in duration, and desirably not apply in contracts of less than 75 weeks duration
Cost adjustment may be provided in construction contracts of less than 52 weeks duration in
special circumstances, for example if the contract involves substantial materials or plant
incorporating price sensitive metals or minerals, such as copper.
Cost adjustment provisions for labour and materials should be based on the National Cost
Adjustment Provision Edition 2 (NCAP2).
Australian Bureau of Statistics (ABS) indices should be employed.
8/13/2019 Cost Adjustment Guidelines
4/25
COST ADJUSTMENT
Page 4 of 25
Separate provisions are required for adjustment to take account of changes in foreign exchange
rate, customs duty, dumping duty, sales tax, ocean freight, marine insurance, overseas labour and
materials indices.
The total proportion of the amounts payable under the contract with is subject to cost adjustment
should be limited to 90%, the remaining 10%, representing profit and overheads, being fixed.
1.5 ABS Indexes and proportions for common categories of work
A table showing the appropriate ABS indexes and proportions for labour and materials for selected
common categories of work is atAppendix A. Sample copies of ABS indexes for labour and materials
are shown atAppendix O.
2. Contractual provisions for cost adjustment for labour andmaterial
2.1 Cost Adjustment for Construction ContractsSample contract clauses, based on NCAP2 for each of the categories shown inAppendix A, are
provided in the Appendices. These clauses may be incorporated as Preliminaries, or in the case of
GC21, as Schedule 8 to the General Conditions of Contract.
If cost adjustment is to be used, include the text shown inAppendix B, followed by an appropriate
table selected from or based on those shown inAppendices CtoL
NCAP2 and the attached provisions allow for cost adjustment in respect of each progress payment, or
final payment. Note that this will lead keenly pricing contractors to tender lower prices for work in the
first 52 or 75 weeks of the contract than for a contract without cost adjustment, when the contractor
must take the risk of cost increases.
2.2 Cost Adjustment for Long Term Service Contracts
In long term services contracts, cost adjustment may be applied to rates or prices shown in the contract
on an annual or other periodic basis. For contracts of this nature it may be convenient to avoid cost
adjustment by contracting only for periods up to two years and omitting cost adjustment provisions.
Sample cost adjustment provisions for annual adjustment are shown atAppendix M.
2.3 Application of cost adjustment to specific subcontracts or work packages,and to multiple categories of work
It may be that cost adjustment is appropriate only for some specific subcontracts or work packages, or
that different cost adjustment provisions are applicable to different subcontracts or work packages.This is only appropriate where the subcontracts or work packages are of relatively large scale and long
term.
It may also be appropriate to use different materials indexes where two or more substantial portions of
the work under the contract belong to different categories of work, but it is not convenient to specify
them as separate work packages.
Each of these approaches may be accomplished by adding additional items into the table attached to
the attached cost adjustment clauses as shown in the following examples:
Multiple Materials Indexes without creating different categories of work: Appendix K
Multiple categories of work: Appendix L
8/13/2019 Cost Adjustment Guidelines
5/25
8/13/2019 Cost Adjustment Guidelines
6/25
COST ADJUSTMENT
Page 6 of 25
3. Cost adjustment for other than labour and materials
3.1 Cost adjustment for fluctuations in currency exchange rates
The NSW Government Procurement System for Constructionstandard form contracts provide for cost
adjustment for fluctuations in foreign currency exchange rates in respect of substantial itemspurchased overseas. The provisions may be omitted if desired. There is no reason why the Principal
should be in any better position to control this price risk than the contractor.
3.2 Cost adjustment for duties and taxes
The NSW Government Procurement System for Constructionstandard form contracts provide for cost
adjustment for customs duties or tariffs in respect of substantial items purchased overseas. The
provisions may be omitted if desired. There is no reason why the Principal should be in any better
position to control this price risk than the contractor.
3.3 Other cost adjustment
While it is possible to provide for cost adjustment in respect of other costs such as shipping and
transport, this generally provides no advantage to the Principal because the Principal is in no better
position that the contractor to control these risks. Cost adjustment is only beneficial where it controls
the risk of tender prices being either excessive or uneconomically low as a result of the contractor's
difficulty in estimating the effect of change in some cost component.
8/13/2019 Cost Adjustment Guidelines
7/25
COST ADJUSTMENT Appendix A
Page 7 of 25
Appendix A - INDEXES AND PROPORTIONS FOR COMMONCATEGORIES OF WORKABS Index to be used for Labour:
Labour Price Index(Australian Bureau of Statistics (ABS) Catalogue 6345.0), Table 11, Private
Sector, ConstructionABS Index to be used for Materials:
Producer Price Indexes Australia(ABS Catalogue 6427.0)
Description %
Labour
%
Materials
Materials Index Table Materials
Table
Column
Architectural Works 35 55 Table 17, Materials
Used in House Building
Sydney
Civil Works 40 50 Table 17, Materials
Used in House Building
Sydney
Mechanical Services - involving
mainly proprietary or
prefabricated components, such
as communications, PABX and
air conditioning
35 55 Table 11 Articles
Produced by
Manufacturing
Industries
Electronic
equipment and
other
machinery
Mechanical Services - other 45 45 Table 11 Articles
Produced by
Manufacturing
Industries
Electronic
equipment and
other
machinery
Electrical Engineering Work 45 45 Table 11 Articles
Produced by
Manufacturing
Industries
Electronic
equipment and
other
machinery
Maintenance - involving
extensive major component
replacement such as lift
maintenance
80 10 Table 17, Materials
Used in House Building
Sydney
Maintenance - other 90
Construction Managers 90
8/13/2019 Cost Adjustment Guidelines
8/25
COST ADJUSTMENT Appendix B
Page 8 of 25
Appendix B - COST ADJUSTMENT PROVISIONSDO NOT USE FOR PROJECTS OF LESS THAN 75 WEEKS DURATION
(EXCLUDING OPERATIONAL MAINTENANCE) OR MORE. INCLUDE AFTER THIS
TEXT A COST ADJUSTMENT TABLE SELECTED FROM THE FOLLOWING, OR
SPECIALLY DRAFTED FOLLOWING THE EXAMPLES
1.1 CONTRACT PRICE AND COST ADJUSTMENT
The Contract Price may be increased or decreased for cost adjustment in accordance with these clauses
and the table attached.
1.2 EFFECTIVE VALUE
The Effective Value in respect of each progress payment or final payment is the value of work
included in the progress valuation or the fina1 value less:
- the value of any work included therein valued on the basis of actual cost or current prices;- the value of any increases due to variations;
- the value of any work which the Contract provides is not subject to adjustment for rise and fall incosts;- the value of any work which is subject to adjustment for rise and fall in costs on a different basis
from that provided for by these clauses;
- the Effective Value in respect of previous progress payments;
and disregarding any increase or decrease under these clauses.
1.3 BASE INDEX NUMBER
"Base Index Number" means the index number appropriate to the index referred to in Column 1 of the
table attached, applicable to the date in Column 3.
1.4 CURRENT INDEX NUMBER
Current Index Number" means the index number appropriate to the index referred to in Column 1 of
the table attached, applicable to the earlier of the date in Column 4 or Column 5 but if the date for the
Current Index Number is earlier than the date for the Base Index Number, the date for the Current
Index Number shall be the latter date.
1.5 CLAIMS FOR COST ADJUSTMENT
The Contractor may submit claims for cost adjustment in respect of progress payments progressively,
but must not submit claims for cost adjustment until the Current Index Numbers for the period to
which the valuation of the progress payment that is to be adjusted relates have been published.
At finalisation of the contract, the Contractor must submit a claim for cost adjustment in respect of thevalue of any work executed under the Contract for which cost adjustment has not previously been
claimed in respect of a progress payment. The claim must be submitted in accordance with the
contract requirements for claims at finalisation of the contract.
1.6 DISCONTINUED OR ALTERED INDEXES
If an index is discontinued or the basis on which an index is calculated is altered, there shall be
substituted the nearest index consistent with the intention of these clauses so as to give effect to it.
1.7 ACCESS TO INDEXES
Australian Bureau of Statistics indexes are published on the ABS website at
http://www.abs.gov.au/ausstats
8/13/2019 Cost Adjustment Guidelines
9/25
8/13/2019 Cost Adjustment Guidelines
10/25
COST ADJUSTMENT
Page 10 of 25
Appendix D - COST ADJUSTMENT TABLE - CIVIL WORKSTABLE OF COST ADJUSTMENT DETAILS
CALCULATION
So much of the value of work in each category In Column A as is Included In the Effective Value shall be separately increased or decreased by multiplying it by theindex shown in Column 1 as applicable to the category;
Applicable Proportion in Column 2
NumberIndexBaseNumberIndexBaseNumberIndexCurrent
A B 1 2 3 Category of Work Value (if
applicable)Index or Indexes
ApplicableProportionApplicable
to each Index
Date for BaseIndex Number
The whole of the workunder the contract
NotApplicable
Labour Price Index(AustralianBureau of Statistics (ABS) Catalogue6345.0), Table 11, Private Sector,Construction
.40 14 days beforetenders closedor the date ofthe Contractoroffer.
The whole of the workunder the contract
NotApplicable
The Materials Index -Producer PriceIndexes Australia(ABS Catalogue6427.0), Table 17, Materials Used inHouse Building , Sydney
.50 14 days beforetenders closedor the date ofthe Contractoroffer.
8/13/2019 Cost Adjustment Guidelines
11/25
COST ADJUSTMENT
Page 11 of 25
Appendix E - COST ADJUSTMENT TABLE - MECHANICAL SERVICEPROPRIETARY OR PREFABRICATED COMPONENTS, SUCH AS COMAND AIR CONDITIONING
TABLE OF COST ADJUSTMENT DETAILS
CALCULATION
So much of the value of work in each category In Column A as is Included In the Effective Value shall be separately increased or decreased by multiplying it by theindex shown in Column 1 as applicable to the category;
Applicable Proportion in Column 2
NumberIndexBase
NumberIndexBaseNumberIndexCurrent
A B 1 2 3 Category of Work Value (if
applicable)Index or Indexes
ApplicableProportionApplicable
to each Index
Date for BaseIndex Number
The whole of the workunder the contract
NotApplicable
Labour Price Index(AustralianBureau of Statistics (ABS) Catalogue6345.0), Table 11, Private Sector,
Construction
.35 14 days beforetenders closedor the date of
the Contractoroffer.
The whole of the workunder the contract
NotApplicable
The Materials Index -Producer PriceIndexes Australia(ABS Catalogue6427.0), Table 11, Articles Producedby Manufacturing Industries,Electronic Equipment and other
machinery
.55 14 days beforetenders closedor the date ofthe Contractoroffer.
8/13/2019 Cost Adjustment Guidelines
12/25
COST ADJUSTMENT
Page 12 of 25
Appendix F - COST ADJUSTMENT TABLE - MECHANICAL SERVICESINVOLVING MAINLY PROPRIETARY OR PREFABRICATED COMPONE
TABLE OF COST ADJUSTMENT DETAILS
CALCULATION
So much of the value of work in each category In Column A as is Included In the Effective Value shall be separately increased or decreased by multiplying it by theindex shown in Column 1 as applicable to the category;
Applicable Proportion in Column 2
NumberIndexBase
NumberIndexBaseNumberIndexCurrent
A B 1 2 3 Category of Work Value (if
applicable)Index or Indexes
ApplicableProportionApplicable
to each Index
Date for BaseIndex Number
The whole of the workunder the contract
NotApplicable
Labour Price Index(AustralianBureau of Statistics (ABS) Catalogue6345.0), Table 11, Private Sector,Construction
.45 14 days beforetenders closedor the date ofthe Contractor
offer.
The whole of the workunder the contract
NotApplicable
The Materials Index -Producer PriceIndexes Australia(ABS Catalogue6427.0), Table 11, Articles Producedby Manufacturing Industries,Electronic Equipment and othermachinery
.45 14 days beforetenders closedor the date ofthe Contractoroffer.
8/13/2019 Cost Adjustment Guidelines
13/25
8/13/2019 Cost Adjustment Guidelines
14/25
COST ADJUSTMENT
Page 14 of 25
Appendix H - COST ADJUSTMENT TABLE - MAINTENANCE INMAJOR COMPONENT REPLACEMENT SUCH AS LIFT MAINTENANCE
TABLE OF COST ADJUSTMENT DETAILS
CALCULATION
So much of the value of work in each category In Column A as is Included In the Effective Value shall be separately increased or decreased by multiplying it by theindex shown in Column 1 as applicable to the category;
Applicable Proportion in Column 2
NumberIndexBase
NumberIndexBaseNumberIndexCurrent
A B 1 2 3 Category of Work Value (if
applicable)Index or Indexes
ApplicableProportionApplicable
to each Index
Date for BaseIndex Number
The whole of the workunder the contract
NotApplicable
Labour Price Index(AustralianBureau of Statistics (ABS) Catalogue6345.0), Table 11, Private Sector,Construction
.80 14 days beforetenders closedor the date ofthe Contractor
offer.
The whole of the workunder the contract
NotApplicable
The Materials Index -Producer PriceIndexes Australia(ABS Catalogue6427.0), Table 17, Materials Used inHouse Building , Sydney
.10 14 days beforetenders closedor the date ofthe Contractoroffer.
8/13/2019 Cost Adjustment Guidelines
15/25
COST ADJUSTMENT
Page 15 of 25
Appendix I - COST ADJUSTMENT TABLE - MAINTENANCE NOT INMAJOR COMPONENT REPLACEMENT
TABLE OF COST ADJUSTMENT DETAILS
A B 1 2 3
Category of Work Value (ifapplicable)
Index or IndexesApplicable
ProportionApplicable
to each Index
Date for BaseIndex Number
The whole of the workunder the contract
NotApplicable
Labour Price Index(AustralianBureau of Statistics (ABS) Catalogue6345.0), Table 11, Private Sector,Construction
.90 14 days beforetenders closedor the date ofthe Contractoroffer.
8/13/2019 Cost Adjustment Guidelines
16/25
COST ADJUSTMENT
Page 16 of 25
Appendix J - COST ADJUSTMENT TABLE - CONSTRUCTION OR PROTABLE OF COST ADJUSTMENT DETAILS
CALCULATION
So much of the value of work in each category In Column A as is Included In the Effective Value shall be separately increased or decreased by multiplying it by theindex shown in Column 1 as applicable to the category;
Applicable Proportion in Column 2
NumberIndexBaseNumberIndexBaseNumberIndexCurrent
A B 1 2 3 Category of Work Value (if
applicable)Index or Indexes
ApplicableProportionApplicable
to each Index
Date for BaseIndex Number
The whole of the workunder the contract
NotApplicable
Labour Price Index(AustralianBureau of Statistics (ABS) Catalogue6345.0), Table 11, Private Sector,Construction
.90 14 days beforetenders closedor the date ofthe Contractoroffer.
8/13/2019 Cost Adjustment Guidelines
17/25
8/13/2019 Cost Adjustment Guidelines
18/25
COST ADJUSTMENT
Page 18 of 25
Appendix L - EXAMPLE COST ADJUSTMENT TABLE - TWO CATEGOWORKS AND ELECTRICAL ENGINEERING WORKS
IN THIS EXAMPLE IT IS TAKEN THAT THE TWO CATEGORIES OF WORKS COMPRISE ALL OF THE WORKS UNDBETWEEN THE CATEGORIES OF WORKS WILL BE BASED ON THE VALUE OF WORK COMPLETED.
TABLE OF COST ADJUSTMENT DETAILS
CALCULATION
So much of the value of work in each category In Column A as is Included In the Effective Value shall be separately increased or decreased by multiplying it by theindex shown in Column 1 as applicable to the category;
Applicable Proportion in Column 2
NumberIndexBase
NumberIndexBaseNumberIndexCurrent
A B 1 2 3 Category of Work Value (if
applicable)Index or Indexes
ApplicableProportionApplicable
to each Index
Date for BaseIndex Number
Civil Works Labour Price Index(AustralianBureau of Statistics (ABS) Catalogue
6345.0), Table 11, Private Sector,Construction
.40 14 days beforetenders closed
or the date ofthe Contractoroffer.
Civil Works The Materials Index -Producer PriceIndexes Australia(ABS Catalogue6427.0), Table 17, Materials Used inHouse Building , Sydney
.50 14 days beforetenders closedor the date ofthe Contractoroffer.
Electrical EngineeringWorks
Labour Price Index(AustralianBureau of Statistics (ABS) Catalogue
.35 14 days beforetenders closed
8/13/2019 Cost Adjustment Guidelines
19/25
COST ADJUSTMENT
Page 19 of 25
6345.0), Table 11, Private Sector,Construction
or the date ofthe Contractoroffer.
Electrical EngineeringWorks
The Materials Index -Producer PriceIndexes Australia(ABS Catalogue6427.0), Table 11, Articles Producedby Manufacturing Industries,Electronic Equipment and othermachinery
.55 14 days beforetenders closedor the date ofthe Contractoroffer.
Note If any work is not included in a category of work it shall be included in the most closely related category.
8/13/2019 Cost Adjustment Guidelines
20/25
COST ADJUSTMENT Appendix M
Page 20 of 25
Appendix M - LONG TERM SERVICE CONTRACT - ANNUALCOST ADJUSTMENT TO RATES PRELIMINARIES CLAUSE
COST ADJUSTMENT - LABOUR AND MATERIALS
In determining the rates and lump sums applicable during any financial year each rate and lump sum
accepted by the Principal shall be adjusted in accordance with this clause. With the first paymentclaim made in any financial year the Contractor must submit detailed calculations used to determine
the adjustment factor applicable to the rates and lump sums for that financial year.
'Base Index Number' means the index number applicable to the date 14 days prior to the date on which
tenders closed.
'Current Index Number' means the index number applicable at the Date for Current Index Number.
'Date for Current Index Number' means the 1st May of the financial year before the period in which
the rate or lump sum is applicable.
If an index is discontinued or the basis on which an index is calculated is altered, there shall be
substituted the nearest index consistent with the intention of these clauses so as to give effect to it.
Rates and lump sums shall be adjusted by multiplying the adjustment factor calculated in accordance
with the following formula using the Labour and Materials indexes applicable to each rate or lump
sum as shown in the table
PMBIM
BIMCIMPL
BIL
BILCILFactorAdjustment
+
+=1
Where CIL is the Current Index Number for Labour
BIL is the Base Index Number for Labour
PL is the Proportion Applicable to Labour
CIM is the Current Index Number for Material
BIM is the Base Index Number for Material
PM is the Proportion Applicable to Material
All items in the Schedule of Rates and
Lump Sums where an hourly labour rate
is shown
All other rates and lump sums
Labour Index Labour Price Index (Australian Bureau of Statistics (ABS) Catalogue 6345.0) Table
11, Private Sector, Construction
PL 0.90 0.35
Materials Index Not applicable Producer Price Indexes Australia (ABSCatalogue 6427.0) Table 11 Articles
Produced by Manufacturing Industries,
Electronic equipment and other
machinery
PM Not applicable 0.55
8/13/2019 Cost Adjustment Guidelines
21/25
COST ADJUSTMENT
Page 21 of 25
Appendix N - WORKED EXAMPLE OF COST ADJUSTMENT
Introduction
Shown below is a worked example of cost adjustment (CA) calculations for claims for a hypothetical contract. Copies
at Appendix O.
Tender and Contract Details CA Details Derived from Relevant ABS Indexes
Date Tenders Closed 30 August 2003 Labour Index Labour PrStatistics (Private Se
Contract Price at award of contract $3,080,000 Proportion applicable toLabour Index
0.35
Contractual Completion Date at award of
contract
31 October 2004 Materials Index Producer
CatalogueHouse Bu
Date of month for submission of PaymentClaims
7th Proportion applicable toMaterials Index
0.55
Category of Work for CA purposes (Thetable in the Appendices to these Guidelineswhich was included in the Contract)
Architectural (Building) Work(Appendix C)
Date for Base IndexNumber (14 days beforetenders closed)
16 August
Variations approved September 2004 $200,000, adjusted ContractPrice $3,280,000
Base Index Number forLabour, from the LabourIndex (Sep 2003
Quarter)
98.8
Extension of Time approved September2004
61 days, adjusted ContractualCompletion Date 31 December2004
Base Index Number forMaterials, from theMaterials Index
140.7
Actual Completion Date 30 April 2005
8/13/2019 Cost Adjustment Guidelines
22/25
8/13/2019 Cost Adjustment Guidelines
23/25
8/13/2019 Cost Adjustment Guidelines
24/25
COST ADJUSTMENT Appendix O
Page 24 of 25
Appendix O - SAMPLE COPIES OF ABS INDEXES
ABS 6345.0 Labour Cost Index Table 11 September Quarter 2004
ABS 6345.0 Labour Cost Index Table 11 June Quarter 2005
8/13/2019 Cost Adjustment Guidelines
25/25