CONSTRUCTION UPDATE - SharpSchool

Post on 18-Nov-2021

11 views 1 download

Transcript of CONSTRUCTION UPDATE - SharpSchool

CONSTRUCTION UPDATE

COMMUNITY & RECREATIONAL CENTER

August 2, 2019

West Allis - West Milwaukee

SITE PROGRESS: GOALS NEXT 2 WEEKS:

MILESTONE DATES: CONSTRAINTS:

• None

Building

• Begin constructing masonry elevator shaft

• Start structural precast

• Start underground electrical and plumbing in the addition

Site Work

• Finished footings and frost walls

• Installation of rigid insulation on foundation walls

• Completed backfill around foundations

• Precast Erection – Start 8/5/19

• Structural Steel placement – Start 9/3

Angles for precast installed

Column pads poured and base plates

setInstallation of insulation and backfill

Elevator pit poured

CONSTRUCTION UPDATE

COMMUNITY & RECREATIONAL CENTER

August 9, 2019

West Allis - West Milwaukee

SITE PROGRESS: GOALS NEXT 2 WEEKS:

MILESTONE DATES: CONSTRAINTS:

• None

Building

• Begin constructing masonry elevator shaft

• Start underground electrical and plumbing in the addition

• Field measurements for storefront framing

Site Work

• Started erection of Precast panels

• Completed rigid insulation on foundation walls

• Completed backfill around foundations

• Precast Erection – Finish 8/5/19

• Structural Steel placement – Start 9/3

North face of gym

West face of gym

Northeast corner of gym

CONSTRUCTION UPDATE

COMMUNITY & RECREATIONAL CENTER

August 16, 2019

West Allis - West Milwaukee

SITE PROGRESS: GOALS NEXT 2 WEEKS:

MILESTONE DATES: CONSTRAINTS:

• None

Building

• Complete masonry for stair and elevator shaft

• Complete precast detailing

• Complete underslab plumbing and electrical

Building

• Precast detailing

• Started underslab plumbing and electrical

• Started masonry for stairwell and elevator shaft

• Structural Steel placement – Start 9/3

Elevator and stairwellUnderslab plumbing

Underslab plumbing Precast detailing

CONSTRUCTION UPDATE

COMMUNITY & RECREATIONAL CENTER

August 23, 2019

West Allis - West Milwaukee

SITE PROGRESS: GOALS NEXT 2 WEEKS:

MILESTONE DATES: CONSTRAINTS:

• None

Building

• Complete masonry for stair shaft

• Complete precast detailing

• Complete final grading inside building

Building

• Masonry elevator shaft is complete

• Masonry stair shaft is near completion

• Preparing door and window openings in gym

• Structural Steel placement – Start 9/3

Elevator and stairwell

Door and window openings being prepared

Masonry stair shaft

Underslab plumbing - completed

CONSTRUCTION UPDATE

RECREATION & COMMUNITY SERVICES CENTER

August 30, 2019

West Allis - West Milwaukee

SITE PROGRESS: GOALS NEXT 2 WEEKS:

MILESTONE DATES: CONSTRAINTS:

• None

Building

• Complete final grading inside building

• Start erecting steel between existing building and gym

Building

• Underslab electrical is complete

• Masonry stairwell is complete

• Final grading of building pad is near completion

• Structural Steel placement – Start 9/6

Stairwell 1 – North elevationFinal grading of building pad

Stairwell 1 complete Final grading of building pad