Project Summary
Propose the reengineering of the online application that manages CIS alumni
Anticipated completion date 4/15/2009
Divided into five phases with deliverables at the end of each phase
Phases of Project
A.Scope Definition
B.Estimation
C.Project Plan
D.Risk Analysis
E. Project Technical & Cost Proposal
Project Status
Established Yahoo Groups for online collaboration and document management
Analyzed current application
Divided system matrix into major site components then recombined to provide a holistic view of system.
Completed Phase 1 and associated deliverables
Phase A: Scope Definition
Quick Requirements analysis assess necessary functions interfaces strategy for solving
Constraints
Possible/desirable features
System Summary Specification matrix
System Summary
System consists of 3 main pages Alumni Home Page CIS 40th Anniversary view Administrative View
System written in html with backend shell scripts
Forms information seem to be emailed rather than stored in a database
System Constraints
Manual Updates - pages are updated once shell scripts are ran via CLI
Use of email to store data rather than relational database
A number of forms need to be downloaded, printed and then submitted
Desirable Features
Authentication and authorization for admin site. Allow user to login and have various types of access.
Implement control panel so authorized admin can approve or deny content such as “shout outs”.
Implement relational database to store site data and content
System Summary Matrix
Matrix
System Matrix Summary
Matrix Summary
Forms = 6
Reports = 24
Operations = 39
Next Steps
Phase B: Estimation Formulate estimation based on various
methods Due date: 2/23/09
Conclusion
Questions