CHAPTER V PERFORMANCE EVALUATION OF CONSTRUCTION...

Post on 27-May-2020

3 views 0 download

Transcript of CHAPTER V PERFORMANCE EVALUATION OF CONSTRUCTION...

132

CHAPTER V

PERFORMANCE EVALUATION OF CONSTRUCTION

INDUSTRIAL UNITS IN KERALA

Controlling the cost and finances of the construction operations and

avoiding financial losses at the job site are of prime importance to the

survival, growth and expansion of a construction organization. Any

discussion on financial management or any other functional area begins

with a reference to the business objectives of the organization. Objectives

are the business plans or goals of the organization. The plans should say

what the business organization is going to do and what are expected to be

the results to benefit the organization itself as a wealth-providing entity,

its shareholders, as individual investors, its employers and the society in

which it operates, now and later. The plans have to match the financial

resources available. It may be noted that while the business objectives of

the organization will guide the management of its financial resources,

only the good financial results of its operations will ensure an efficient

pursuit of the objectives.

The objectives are generally bifurcated into long-term or strategic

objectives and short-term or tactical objectives. The top management

concentrates on the former while departmental managers concentrate on

the latter.

133

The general objectives are outlined below:

1. The organization’s market position in the construction industry

and its order level.

The organization‟s market position is a status to be created by the quality

of performance and professionalism in conduct.

While discussing the orderlevel, the size of operation and the cycle

of operation are the two points to be considered.

For a construction organization the ideal size is the achievement of

annual turnover equal to eight times the shareholder‟s fund.

Operating cycle is the period from the start to the finish of

execution of the whole contract. In heavy industrial construction, it is

2 1/2 years average. Therefore, to be able to achieve a turnover 8 times

the owned funds, 8x2 1/2 =20 times should be the ideal order level. This

level should be maintained on a revolving period. (Joy, 2008)1.

2. Return on Net worth

The organization shall endeavour to earn sufficient after tax return on net

worth.

3. Business growth

The organization‟s policy shall always be to attain a balanced and healthy

growth.

4. Employees’ growth

Generally the employees shall be provided with the compensation for

their efforts. They shall be encouraged and supported for individual

growth and development, be given a co-operative atmosphere of working

and provided with social security benefits.

134

5. Strength to face changes in construction technology

To be able to survive in the competitive industrial field, the organization

should keep abreast of the latest materials, equipments and erection

technology and skill of that time. There should be reasonable measures of

Research and Development, training, information service, collaboration

and /or understanding with leaders in the industry in the more advanced

parts of the world. These measures of innovation should be part of a

going concern‟s preparation to adapt to changes.

6. Strength to face other environmental changes

Environment has several facts. They are: economic, social, ecological

cultural, political, legal, technological and market competition. The

organization has to continuously strengthen itself to face all manner of

changes in all facets.

7. Diversification

Financial resources management will play an important role in the

organization‟s business diversification plans in later years when it would

find that the particular class/ types of jobs undertaken is no longer paying.

8. Social contributions and environmental considerations.

The society in which the organization operates would expect certain

contributions from it. The organization and the community around it are

interwoven and interdependent. It is necessary to emphasize that in all its

plans and polices the organization has to consider social good. It has to

serve the society by doing excellent quality work, earning good profit,

and paying substantial amount of taxes to Government as a major part of

social contribution. There should be concern for the health, hygiene and

welfare of the community around its working. It must cause minimal

damage to the environment.

135

9. Profit

Profit is the prominent objective of a construction organization. This is

because the organization can survive only when it makes sufficient profit

to provide the necessary financial support to the other objectives. Every

decision that it makes should aim at a profit. This objective is classified

into short term as well as a long term because profit is to be earned from

the current operations. Every part of performance should earn the

proportionate profit. No management can ever think of a compromise on

this. The profit earnings have to be reasonable. After providing for

employers‟ long term benefit funds, depreciation on assets, all interest

charges and income tax, the net earning should leave sufficient balance to

pay dividend to shareholders at comparable rate and retain a reasonable

amount to finance the organization‟s growth.

The objectives mentioned above serve as a benchmark to measure

the efficiency, effectiveness or otherwise of the operations undertaken by

construction organizations all over the world. But before attempting to

make such a detailed analysis, certain aspects peculiar to construction

industry are worth noting. The conditions in the construction are entirely

different from other industrial or commercial activities having fixed place

of business, standardized methods, practices, inputs and outputs and

above all fixed overheads. Most construction projects are located in

isolated areas. Only the vital and crucial functions are performed by the

core group of regular employees. A major portion of the supervisory and

administrative personnel and majority of the workers are temporary and

migratory. Further, a number of anticipated modifications and adverse

site conditions require spurts of additional staff and labour resources at

short notice which may be very expensive. Thus, it is not possible to

consider the construction industry as similar to manufacturing or other

service sector.

136

Continuous increases in the prices of construction materials as well

as the cost of labour are posing serious questions on the efficiency of

works contracts. Variations in the costs of these inputs have become

increasingly unpredictable. Contractors are no longer willing to submit

fixed price bids as they are unable to estimate, with reasonable accuracy,

the likely increases in the prices of materials, equipment and labour and

thus provide in their quotations for anticipated cost increases due to these

items.

The frame work to evaluate the working of any system has to

include economic, commercial as well as social and ethical criteria.

It has been empirically proved that sustainable construction

activities will bring about all round economic development. It is also

noted that economic development brings about healthy and ethical

construction practices. Thus the relationship between the two seems to be

symbiotic.

The following questions are to be asked to in order to evaluate the

working of the construction industrial units:-

1. Whether construction business entities find the most productive

investment?

2. Do the units revalue their assets and liabilities in response to the changed

circumstances?

3. Whether the units facilitate the management of risk by making available

the means to insure and diversify risks.

4. Is there any institutional framework that monitor the performance of the

various units, and discipline those not making proper and effective use of

their resources?

5. How effective is the legal, regulatory, supervisory and judicial structures?

6. Whether construction participants (firms) publish consistent and

transparent information?

137

Construction aims at adding value to the quality of life. A new house or a

new residential complex, a new commercial or infrastructural project, all

these can and should enhance the quality of life of the people associated

with it directly or indirectly.

However, one must admit that there is less transparency in the

dealings and there is a uniform reluctance on the part of the construction

participants in sharing the statistical data and their experience. As we find

in many business activities, in construction business too it is customary to

have two sets of accounts, one for the revenue authorities and the other

for one‟s own use.

The atmosphere of corruption and dishonesty that envelops the

administrative apparatus currently found in several countries, is in many

respect, a genuine problem. Paradoxically, it must be seen as a price that

has to be paid to promote economic expansion in the underdeveloped

areas. (Bhagavathi, 1987)2.

In spite of the important position of the residential construction

sector in Kerala, it continues to be a non-formalized one. Even at the

national level, the number of small firms is so large that the construction

is called a non- formal sector of the economy. In construction, there are

no licensing conditions or other regulations as they exist in the

manufacturing sector. As most work is tendered out with advances given

by the owner, the capital required for setting up a firm is small. Thus

entry into the industry is easy and it calls for no special skills.

Although residential construction registered an average annual

increase of 25-30 percent, the sector faces a number of problems.

Tackling the problems effectively calls for a better understanding of its

present structure and working. The industry has its presence all over the

state. An attempt is made in this chapter to study the working of the

industry based on a stratified sample of construction participants that are

138

spread over (three) regions, namely, Northern, Central and Southern of

the state.

Location of building construction industrial units

The important factors which influence the location of the factories

in the organized manufacturing sector are not wholly applicable in the

case of construction firms. In fact, it is the demand for construction

products that will determine the level and volume of construction activity

undertaken in a particular area.

An analysis of the location of the selected units revealed that 70

per cent of the units have an urban or semi-urban location. Since

manufacturing and associated modern services are concentrated in Kochi

and its surrounding region, it is also the centre of the construction

industry in the state. There are certain corridors that reflect high

investment potential locations around Kochi, including Aluva and

Nedumbassery, like Thrippunithara, Thiruvankulam, Chottanikkara,

Aroor, Vypeen, Kadungalloor and North Paravur.

Kochi is where the largest proportion of Kerala‟s upper an middle

class live as indicated by the city‟s average per capita income, the

number of taxpayers resident and the amount of taxes collected from

here. The growing middle-class wants better-quality housing and is

benefitting from ready access to home loans through a more sophisticated

banking sector. One property developer estimates that the private sector is

building upto 20,000 homes a year but this is not enough to meet demand.

Kozhikode and Thiruvananthapuram, the two other big cities of the

state follow Kochi. Besides big cities and suburbs, smaller ones like

Thrissur, Kottayam and Kollam, and Towns like Thiruvalla,

Changanassery, Pala, Chengannore Guruvayoor, Irinjalakuda,

Kodungalloour and Chalakudy are also witnessing tremendous

construction activity.

139

Construction industry is wide spread in its reach. Hence, primary

data is collected from each of the main participants of the industry

namely, the builders, the contractors, the input suppliers and the workers.

Year of establishment

More than 80 percent of the selected units were set up after 1980.

Ownership pattern

There are 33 major builders having their presence all over Kerala.

40 per cent of them have projects (on going or finished) all over the

country. 20 per cent of them have overseas assignments. Of the 33 major

builders, 23 were contacted and details were collected from them. Only

12 firms were ready to share financial data. Of the 23 major builders

contacted, 2 are public companies, 8 are private limited companies, 9 are

partnership firms, 3 are proprietorship concerns and 1 belongs to the other

category. Besides, 40 local builders (area of operation one district) were

contacted ; of these 10 per cent are private limited companies, 75 per cent

are partnerships and 15 per cent are proprietorship concerns.

There are 16 major contracting having their presence all over

Kerala. Of these 11 firms were contacted and data available from 9 of

them. Of the 9 contractors 4 are private limited company 4 partnership

concern and one is a proprietary concern. Besides the major contractors,

there are numerous general and specialty contractor working at the local

level. 40 such contractors were contacted and 33 of them are partnerships

and 7 proprietary concerns.

80 per cent of the 24 input suppliers contacted are partnership concerns

and or the remaining proprietary concerns. All of them are located in

cities or towns.

The construction labour market is a heterogeneous one. From highly

skilled (professional engineers, architects etc) to unskilled workers

constitute it. Most of the administrative and middle level management is

140

performed by employees recruited from Kerala whereas on an average

20-30 percent of the low end or manual work is performed by migrant

labourers.

STUDY METHODOLOGY

The data for this study was collected through questionnaires,

structured face –to- face and telephone interviews. The sample consisted

of 12 major builders and 9 major contractors having presence all over the

state. Besides, 40 local builders and 40 local contractors were contacted.

They belong to the central region of Kerala namely Ernakulam and

Thrissur districts. Of the 24 input suppliers contacted, 9 firms have

outlets in all the three regions.

Table – 5.1

Profile of sample –Annual turnover of firms, Typical value of

projects tendered for and tender success Rate

(Builders and contractors)

Category Frequency ( per cent)

Annual Turnover

Less than Rs. 1 million

Rs. 1 million- Rs. 20 million

Rs. 20 million- Rs. 40 million

Rs. 40 million –Rs. 60 million

Above Rs. 60 million

6.00

40.62

26.26

7.11

20.01

Typical value of projects tendered for

Less than Rs. 5 lakh

Rs. 5 lakh- Rs. 15 lakh

Rs. 15 lakh- Rs. 25 lakh

Rs. 25 lakh- Rs. 35 lakh

Above Rs. 35 lakh

28

38

16

8

10

Tender success Rate

Less than 5 per cent

6-10 per cent

11-20 per cent

21-30 per cent

Above 30 per cent

14

43

14

14

14

Source : Computed from consultations with experts.

141

Workers numbering 200 were contacted of these administrative

staff consisted of 30, Engineers 20, architects 8 and construction

labourers 142. All these are taken form the central region. The residents

numbering 50 contacted are mainly located in Thrissur district especially

Guruvayoor.

Firms’ objectives

Respondents were asked to indicate the relative significance of

economic as well as non-economic objectives on a scale ranging from the

least important to the most important.

Table - 5.2

Ranking of firms’ objectives

(Builders & contractors)

Firm’s objectives Rank

Economic objectives

Profit earnings per share

Return on investments

Turnover

Market share

1

3

6

7

Non- economic objectives

Customer satisfaction

Quality

Performance relative to competitors

Technology leadership

2

4

5

8

Source : Survey.

There is considerable overlapping in the functions undertaken by

builders and contractors. There are generally three categories namely a)

Exclusive builders b) Exclusive contractors, and c) acting as both builders

and contractors. The above two tables are compiled combining the survey

results in respect of both the builders and contractors.

142

Table- 5.3

Composition of fixed capital of the sample units (Builders ) during the

period 1991-00 to 2008-09

(Rs. Crores)

Year Land Buildings Vehicle Total

1999-00 4 6 1 11

2000-01 5 8 1 14

2001-02 6 10 2 18

2002-03 7 11 2 20

2003-04 8.5 13.5 2 24

2004-05 26.0 19.0 3 48

2005-06 51.0 25.0 5 81

2006-07 60.0 33 7 100

2007-08 70 32 9 111

2008-2009 68 49 11 128

Source: Survey.

Table – 5.4

Composition of the fixed capital of the sample units (contractors) during

the period 1991-00 to 2008-09.

(Rs. Crores)

Year Land and

Buildings

Plant and

Machinery

Vehicles Total

1999-00 2.5 39.5 .5 42.5

2000-00 3.0 42.0 .5 45.5

2001-02 4.0 50.25 .75 55.0

2002-03 10.50 58.50 1.50 70.5

2003-04 11.25 70.00 1.75 83.0

2004-05 19.00 80.00 1.50 100.5

2005-06 20.00 117.50 2.50 140.0

2006-07 25.50 151.50 3.00 180.0

2007-08 30.00 161.50 3.50 195.0

2008-09 31.00 165.50 7.50 204.0

Source: Survey

1

2

143

Table-5.5

Composition of physical working capital (PWC) and working capital (WC) of the sample units (Builders )

during 1999-00 to 2008-09

(Rs. Crores)

Year Materials Semi finished

products

Finished

product

Total physical

WC Cash R-P

WC

(5+6+7)

1991-00 4 25 14 43 12.0 5.50 60.5

2000-01 6 27.5 17.5 51 17.5 8.50 77.0

2001-02 8.5 35.0 28.5 72 20.5 9.50 102.0

2002-03 11.5 37.5 31.0 80 24.0 11.50 115.5

2003-04 22.5 38.5 35.0 96 28.5 13.0 137.5

2004-05 49.0 73.0 70.0 192 48.0 20.5 260.5

2005-06 97.5 126.5 100.0 324 64.0 29.0 417.0

2006-07 104.0 146.0 150.0 400 80.0 38.0 518.0

2007-08 105.0 150.0 189.0 444 88.0 40.0 572.0

2008-09 140.0 172.0 200.0 512 91.0 44.0 647.0

Source: Survey.

144

Table – 5.6

Composition of physical workings capital and working capital of the sample units (contractors) during the period

1999-00 to 2008-09

(Rs. Crores)

Year Materials Semi finished

products

Finished

product

Total physical

WC

Cash R-P WC

(5+6+7)

1991-00 30 21.25 55.0 106.25 25.5 10.0 141.75

2000-01 32.5 22.50 60.0 115.00 28.75 12.75 156.50

2001-02 45.0 33.00 87.00 165.00 38.00 17.00 220.00

2002-03 60.0 42.50 110.00 212.50 80.00 34.00 326.50

2003-04 85.0 53.50 141.50 280.00 110.00 60.00 450.00

2004-05 147.5 90.00 212.50 450.00 180.00 95.00 725.00

2005-06 187.5 125.00 317.50 630.00 200.00 105.00 935.00

2006-07 245.00 180.00 475.00 900.00 233.00 120.00 1253.00

2007-08 285.00 195.00 490.00 970.00 235.25 125.00 1330.25

2008-09 270.00 180.00 450.00 900.00 231.50 115.00 1246.50

Source: Survey

145

There is inter firm inconsistency in the financial management

practices reported to by builders and contractors. Viewed from the

technical angle, there is a marked difference in their composition of

fixed capital and working capital. Exclusive builders generally have

less investments in plant and machinery while exclusive contractors

have a very high investment in plant and machinery. There is also

difference in the current ratios with former having an average current

ratio of 5:1.5 while the latter having an average of 1.2:1. The presence

of a very high unsecured loans in their balance sheets points to an

unhealthy practice in raising funds. The capital base is poor even in

the case of large firms while the small firms manage with very small

amount of capital. This raises the question of sustainability of

construction activities undertaken by these firms.

Orgnisation’s market position

Over the years major builders and contractors in the state have

acquired a somewhat unassailable position in the market. Almost 70-

80 per cent of the residential construction work takes place in urban

and semi urban areas. The market here is dominated by large firms. 80

per cent of the work in urban and semi-urban areas is under taken by

large firms. The rural market is characterised by a slow and steady

demand for construction products and the same is met by medium to

small players. With the internal dynamics getting saturated in urban

areas, large players have started ventures in rural areas. Of late, even

big players have started undertaking projects in the outskirts of town

and rural areas.

146

Figure 5.1

Classification of firms undertaking construction activity

in rural areas

Figure 5.2

Classification of firms undertaking construction activity

in urban areas

20%

80%

Large firm

Small firm

10%

90%

Small firm

Large firm

147

Return on Net worth

Investment in construction normally provides a fair return on net

worth. Going by the samples, the urban players could garner a higher

return on net worth than their rural counterparts. The formula for return

on net worth is

= capitaluppaidTotal

incometaxAfter

Table - 5.7

Return on Net worth (Builders)

(Rs. Crores)

Year Total paid up

capital

After tax income per cent

2004-05 12 1.68 14

2005-06 20 4.32 21.6

2006-07 25 5.96 23.84

2007-08 28 8.12 29.0

2008-09 32 7.6 23.75

Source : Survey

Table – 5.8

Return on Net worth (contractors)

(Rs. Crores)

Year Total paid up

capital

After tax

income

per cent

2004-05 20 1.6 8

2005-06 26 3.9 15

2006-07 36 4.5 12.50

2007-08 39 6.98 17.89

2008-09 40 5.60 14.00

Source : Survey

There is considerable difference in the return on net worth enjoyed

with builders having a range of 5-40 per cent while contracting firms

have a range of 8-18 per cent. The average return on net worth enjoyed

148

by the builders for the last five years comes to 22.44 per cent while that

of the contractors it comes to 13.48 per cent. The global economic melt

down has affected the builders and contractors of the state with the

decline in return in the year 2008-09.

Business Growth

Growth presupposes the existence of opportunities on the one hand and

the organisation‟s ability to capitalize on such opportunities. The

construction organizations in urban and semi-urban areas are

experiencing a high rate of growth based on increase in the annual

turnover, acquisition of new fixed assets and rate of profit. The large

players have registered 20-40 per cent average annual growth rate over

the past 5 years. However, in rural areas, business growth has not been

much impressive.

Table – 5.9

Business Growth during 2004-09 (Builders and contractors)

Particulars Frequency (per cent)

Less than 10 per cent 22

10 per cent-20 per cent 38

Above 20 per cent 40

Source : Computed from survey.

Table – 5.10

Average Growth Rates of Builders and contractors in Kerala for the

period 2004 to 2009 in Rural and Urban areas.

Category Frequency (per cent)

Less than 0 R

U

8

3

0-10 per cent R

U

3

10

10 per cent-20 per cent R

U

7

19

Above 20 per cent R

U

10

40

Source : Computed from survey. (R= Rural, U= Urban)

149

Local

Migrant

The failure of certain construction organizations in both rural and

urban areas can be attributed to their own mismanagement rather than

outright competition. It is also to be noted that the growth of business has

not been uniform throughout Kerala. While the central districts showed a

very high growth rate, establishments in northern and southern districts

showed average to high growth rates.

Employee growth

Construction labour force consists of both white and blue collars.

90 per cent of the administrative and 80 per cent of the technical (mainly

engineering) work is undertaken by employees recruited locally. On the

other hand 20-60 per cent of the manual work especially low and jobs are

entrusted to migrant labour force.

Figure 5.3

Estimated share of local and migrant labour force in the

construction activity

The labour management in construction industry is far from

satisfactory. Barring a few employees at the top and middle level, no

other category has any type of job security, let alone other facilities.

Since 85 per cent of the labour are recruited temporarily, the mutual

150

contractual obligations between the firms and the workers come to an

end with the completion of the project on hand. Workers are not given

much training. Here individual growth and development are more a

matter of chance than any deliberate attempt on the part of the

employer. 90 percent of the manual work is characterized by learning

by doing approach. Barring one or two construction organizations, the

construction labour force is treated in the same manner irrespective of

the size of the firm. Human relations are better attended to in rural

projects undertaken by local firms. But they too are disappearing now

–a-days.

Technology upgradation

Technology up gradation focusing on productivity enhancement is

yet another factor determining the performance of construction

industrial units. Here also large firms are better poised to introduce

latest construction technology. But they too are a little bit hesitant in

introducing changes.

Table- 5.11

Adoption of new construction Technology

Category Adopted Ready

to adopt

Not

decided

Not to

adopt

Total

Large builders

and

contractors

6 10 5 - 21

Medium &

small

8 40 18 14 80

Source : Survey

While construction materials are easily accepted, construction technology

continues to be traditional, especially, in rural areas. Technology up

gradation calls for investment in plant and machinery and human

151

resources. Large firms have the resources and they introduce changes.

The local firms continue to follow the traditional methods. There is also

lack of skilled labour force. Construction firms in Kerala are yet to realize

the importance attached to adoption of new construction technology.

There are R&D sections attached to some firms, but most of them are

only ornamental. Some Non-Governmental Organizations (NGOs) have

come up with novel ideas, but the market is yet to respond to these

initiatives positively.

Managing change

Today‟s ever hanging business environment calls for continuous

appraisal of strength and weakness on the part of construction

organizations. These appraisals consist of internal as well as external

appraisals. Generally the methods of internal appraisal usually followed

by world class construction firms include, but not limited to the

following:

1. Employee performance appraisals.

2. Customer surveys; and

3. Skills analysis

Similarly, methods of external appraisals are:

1. Economical

2. Technological

3. Political; and

4. Social

Based on the internal as well as external appraisal results, firms usually re

define their corporate objectives. Then efforts to develop and implement

strategic plans begin. Generally, the planning tools are:

1. Financial projections

2. Formal business plans

152

3. Growth projections

4. Vision statements

5. Market segmentation

6. SWOT analysis; and

7. Core competencies

Going by the sample, majority of the Kerala builders and contractors,

especially the local ones, are not in the habit of conducting regular

internal and external appraisals. Large firms which belong to the

corporate sector are in the habit of designing a strategy for themselves

and they usually make comprehensive plans for the future.

Construction market in Kerala is actually charactersied by what we

call „random walk‟. There is not much homework or project formulation

techniques undertaken before taking a decision to launch a new project.

Selecting the auspicious day and time for the foundation ceremony of a

new project, generally solemnized by a celebrity, „bhoomipooja‟ and

other things associated with it are done with much fanfare. Faith and

rituals play a very important role in construction industry. One cannot

deny the fact that construction has a strong positive linkage with

superstition.

Construction markets move upward and downward which cannot

be justified by rationally formed expectations. The market speculation

multiplies several fold the effect of underlying variability in the value of

materials and labour. Given the turbulent nature of the environment, firms

are usually in a rush to finish the projects on hand. Thus modern methods

of strategic planning have not yet found favour with many construction

organizations in the state.

153

Diversification

Business diversification is supposed to be one of the main

corporate strategies usually adopted by successful construction

organizations the world over. The market for luxury housing has

considerably increased in India especially in mega cities. This applies to

Kerala too. A lot of people desire to live in a posh locality to add their

stature in the society. Urbanization and heavier pockets have made it

possible for the people to quality living.

However, the global economic meltdown has affected the builders

of our state in such a way that some of them have started thinking of

undertaking “ affordable housing projects”. These projects are generally

meant for medium and low income groups. Some prefer flats in the city

and villas in the outskirts of the town. The ability to redesign strategy and

design products that are capable of satisfying the customer expectations

calls for the ability for diversification. What is required is „out of box‟

thinking which should replace the „herd mentality‟ hitherto followed by

many construction firms. Several firms have started undertaking low cost

residential projects in the light of the global economic meltdown. But it

must be admitted that the builders and contractors in the state are yet to

realize the importance of designing multiple investment opportunities.

Social contributions and environmental considerations

The framework to evaluate the working of any system must include

economic, commercial as well as social and ethical criteria. The concept

of corporate social responsibility is gradually gaining ground among the

construction participants of the state. How effectively the organization is

capable of safeguarding the interests of the stakeholders will determine

the degree of importance it attaches to corporate social responsibility.

Quality, productivity and environmental considerations are the

three aspects associated with social responsibility. The two important

154

criteria attached to the above aspects are ISO 9000 and ISO 14000

certification.

Table-5.12

Popularity of ISO 9000 certification among construction firms in

Kerala

Category Obtained

ISO-9000

Certificate

Applied

for

Not

decided

Not

aware

Large firms 17 4 - -

Medium&

small firms

2 - 30 48

Source : Survey

Table 5 -12 shows the popularity of ISO-9000 certification among

the construction firms of Kerala. Accordingly, majority of the large firms

have already obtained ISO 9000 certification. Majority of the local

builders are not aware of such a certification. Some of them are also

reluctant in applying for the same lest it should curtail their freedom.

Table-5.13

Popularity of ISO 14000 certification among construction firms in

Kerala

Category Obtained

ISO-14000

Applied

for

Not

decided

Not

aware

Large firms 2 1 8 10

Medium & small local - - 6 75

Source : Survey

ISO 14000 is much more comprehensive where as ISO 9000 is

market driven. ISO 14000 is driven by the stakeholders, the community

and the regulators. Majority of the large, medium and small firms are

unaware of the system of ISO 14000 certification.

155

Other profitability aspects

As already stated, profit is one of the prominent objectives of any

business organizations. Profit and longevity of individual and institution

are the prime considerations of an entrepreneur. Accordingly every bit of

performance should earn the proportionate profit. There is close linkage

between profitability and productivity on the one hand and waste

management on the other. Productivity measurements are not done

scientifically by majority of the firms. Due to the complex nature of the

industry, there is no clear understanding of the productivity and the

methods of measuring it. Majority of the large builders follow some

methods of measuring productivity. But even among them there is no

agreed or definite format. Local builders and contractors are way behind

their urban corporate counter parts. There is no systematic measurement

of productivity enhancement efforts on the part of management. Closely

associated with productivity enhancement is waste management. In their

eagerness to finish the project on time, very often little attention is given

to waste management. This is the case with majority of the construction

participants irrespective of their size. Waste management is a multi-

disciplinary activity involving engineering principles and management

techniques, to minimize the overall wastages of the system under

consideration.

Operational efficiency

Construction is primarily a contracting business. In recent years,

the construction industry has seen a visible shift from “ owner managed

construction projects” to EPC (Engineering, Procurement and

Construction ) projects with inter-dependent and co-ordinated disciplines

of construction. The different types of contracts are as given below.

Engineering, Procurement and construction (EPC)3

- Complete single point responsibility

156

- Fixed time- fixed price contracts, heavy penalties for non-

performance.

- Escalation possible by mutual consent

- Most popular for power projects

Lump-sum Turnkey (LSTK)

- EPC with no scope for escalation

- Preferred for power and industrial projects

Engineering procurement construction Management

- Responsibility for placement of order for equipment and payment

lies with the promoters

- Fixed time-Fixed Price contracts

- Lower penalties relative to EPC for non- performance

- Preferred for very large projects

Turn key

- Responsibility to implement complete project

- Fixed price as well as cost plus contracts are possible

- Contractor need not have financial capability

- Preferred for medium and small projects.

Engineered package Route

- Promoter breaks up the project into packages

- Turnkey supply of packages

- Promoter is responsible for project co-ordination

Item rate contract

- This is the most prevalent contractual mechanism in which:

- The owner through an appointed consultancy organization does the

engineering.

- Bill of quantities are furnished and the tenderer is required to

quote the price item-wise

- The contractor need not have large financial capacity in this case.

157

- It is practised in subcontract packages.

- Most favoured by Government regulations

- As a consequence of cost and time overruns, possibilities for

disputes are more.

A large project may have a prime contractor who will appoint sub-

contractors for different work packages. A sub- contractor, in turn, may

have his own contractors for various jobs i.e, brick layers, concreters,

painters, tile layers, electricians, carpenters etc. The prime contractor

does the co ordination work. Short –term employment, job tenure lasting

for the project duration only and piece rate system of payment are the

major features of contracting. This system was evolved gradually with the

promoters starting to assume only business risks leaving non-business

risks to other specialists.

Cost components

A typical building construction project has the following cost components

Table 5.14

Cost components

Sl No Account Head Percentage

1 Survey and soil investigation 0.08

2 Tendering and Design 4.67

3 Personnel

Labour 15.0

Staff and officers 2.5

Labour colonies 2.25

Mobilization 3.00 22.75

4 Material 43.00

5 Plant and equipment 7.00

6 Insurance, Bank interest and capital servicing 9.00

7 Project office 0.80

8 Travel 1.30

9 Head office expenses 1.40

10 Miscellaneous (including Agency conclusion) 10.00

100.00

Source: Computed form consultation with experts.

158

The base was created on the basis of discussions with experts in the

field.

The position of the structural aspects of the cost components are as

follows:

Table 5.15

Structural aspects of cost components

Sl.

No

Structural aspects Percentage

1 Design and Technical services 5.00

2 Foundations upto plinth 14.00

3 Columns, Beams, Walling and Roofing 31.00

4 Flooring 4.00

5 Plastering, Painting and Finishing 9.00

6 Water supply and sanitary works 6.00

7 Internal electrification 4.00

8 Doors, windows and Timber items 17.00

9 Miscellaneous 10.00

Total 100.00

Source: Computed from field survey

Materials

Building materials play a crucial role in the construction of housing

stock. They constitute the bulk of the construction cost. Depending upon

the type of a housing project, building materials account for 40 to 60

percent of the total project construction cost (the remaining 33 percent

being the labour cost)

Components of material cost incurred for a representative single

story house has been worked out as follows:

159

Thus, building materials are the major single cost item in the total

construction cost of housing projects.

Table 5.16

Components of material cost

Sl.

No

Item Percentage

1 Cement 17

2 Steel 9

3 Brick / Blocks 13

4 Timber 10

5 Sand 8

6 Aggregates 5

7 Rubbles 5

Total 67

Source: Computed from survey

Apart from the rising costs, non availability and shortages of

materials have created bottlenecks in large construction programmes.

River sand has become a very costly item now a days because of

restrictions imposed by the authorities on river sand mining. One of the

few alternatives before the industry is the manufactured sand or M. sand,

which can replace the river sand.

Environmentalist are of the opinion that there should be enough

precautions to prevent any further pollution from the extensive use of

M. Sand.

A movement for the use of mud in building construction is gaining

ground in Kerala. Building with mud is nothing new. “ Almost 50 percent

160

of the people all over the world live in houses made of mud” says

architect Eugene Pandala. The use of mud implies the applications of

traditional technology which is sure to strengthen the centripetal linkages

of the industry in the state. So far, the role of mud in major construction

projects has not been significant.

Baker, Laurie A. (1993)4 stressed the need for building simple low

cost, eco-friendly houses using even discarded objects used as

construction material. He said that “All building is 10 to 15 per cent

technical know how, and the rest, common sense”.

The use of Ready Mix Concrete (RMC) is slowly gaining ground

in the country. Bangalore is the hub of construction activities using RMC.

There is only 2 percent penetration in Kerala.

It has been observed that the overall potential for cost reduction of

a representative housing unit ranges from 21.5 to 37.5 percent as shown

below.

Table : 5.17

Potential for cost reduction

Sl No. Item Percentage

Range

1 Cement 20-40

2 Steel 30-45

3 Brick / Blocks 30-50

4 Timber 40-50

5 Sand 10-15

6 Aggregates 20-25

7 Rubbles and miscellaneous 15-25

Source: Opinion of construction experts complied by NICMAR (2003)

161

Productivity measures

Construction cost reduction is achieved in several ways. These

include avoiding wastages, adopting appropriate technology, evolving

innovative designs, achieving efficient construction management,

effective programming of works, improving labour skills, on-line

monitoring etc. These techniques are collectively called “ productivity

measures”.

There is no unanimity among the authorities on construction as to

the meaning and definition of productivity in construction. But the

general definition of input-output ratio with a time period with due

consideration for quality is applicable in the case of construction industry

also.

Productivity= )Quality(Inputs

)Quality(Outputs

(Within a time period, quality considered )

The formula indicates that productivity can be improved by i)

increasing outputs with the same inputs, ii) by decreasing inputs but

manufacturing the same output, or iii) by increasing outputs and

decreasing inputs to change the ratio favourably.

Total factor productivity combines various inputs to arrive at a

composite output. Productivity implies effectiveness and efficiency in

individual and organizational performance. Effectiveness is the

achievement of the ends with the least amount of resources.

The highest site productivity is obtained by producing the required

quantity of construction of the specified quality, within the budgeted time

and by the best and the cheapest method.

But this is seldom achieved due to several reasons some of which are

listed below:

a) Changes in the design after the work has started

162

b) Use of unsuitable plant, equipment and tools.

c) Bad sequencing of operations

d) Delay in procurement of materials

e) Too much of material and labour wastage

f) Lack of finance

Material wastage in construction industry

Wastage is the negative variance between the estimated

consumption and actual consumption of inputs for a fixed quantity of

output. Standard wastage is the ± tolerances which are stated in the rule

book issued by the competent authority. It is expressed as follows

W= E1- (1+Tm) x EO

Where,

W = wastage

E1 = Actual consumption of inputs

EO = Estimated consumption derived form final drawings at pre-start

stage

Tm = Factor of tolerance for estimate, allowable wastage

Material wastage Indices (MWI) constitutes the instrument to

monitor consumption of construction materials and labour. Existence of

Building Materials Price Indices (BMPI), Labour Rate Indices (LRI) and

Construction Cost Indices (CCI) is essential to the effective and

meaningful use of MWI. In India, neither of the three BMPI, LRI and

CCI exist (Vaid, 2003)5.

In practice, the extent and quantity of wastages are not exactly

measurable as there is scarcity of records on the one hand and supply of

doctored data making it less authentic on the other. However, a NICMAR

study group headed by Dr. K. N. Vaid has come out with the following

results.

163

Table : 5.18

Composition of cost of wastage

Material Assumed share

in construction

Actual

average

wastage

per cent

Share of

wastage in

construction

Percentage

share

Cement 13.00 9.58 1.24 33.60

Steel 12.00 8.14 0.98 26.56

Sand 6.00 16.28 0.98 26.56

Metal 3.00 6.10 0.18 4.88

Bricks 2.00 12.43 0.25 6.78

Blocks 2.00 2.93 0.06 1.62

Total 36-38 3.69 100.00

Source : Management and Labour in the Indian Construction Industry. K.N Vaid

(2003)

It may be noted from the above table that category „A‟ material

which constituted 36 to 38 percent of total construction cost had a

wastage of 3.69 percent. In other words, the wastage was about 10

percent of the total construction cost. Further column 4 brings out that

cement, steel and sand were the major items whose wastages escalated

the cost of construction significantly (Vaid, 2003)6.

Assuming the average of Rs. 1000 per square foot as the cost of

„B‟ class construction, the wastage was (10 per cent) Rs. 100. For a one

room kitchen unit of 400 sq.ft. area, wastage would be Rs. 40000, and

Rs. 80000 for an 800 sq.ft. housing unit.

Very little efforts are made by the residential construction units in

Kerala in applying scientific methods of Material Requirement Planning

(MRP), working out of Economic order quantity (EOQ), determination of

lot size etc. in any of the projects undertaken by them.

Regarding productivity and quality in construction, organizations

are found to behave almost like bureaucratic organizations that are

164

characterized by underspecification of ends (goals and values) and over

specification of means and by greater emphasis on control and close

supervision rather than autonomy and commitment. In the absence of any

reliable measurements of input- output relationships, the management

process tends to be expressed in terms of input elements only and there

are few measures to achieve the outputs.

Employment of labour in construction

With a very few exceptions, construction labour is supplied by

labour contractors in all housing projects. Where total job is split into

numerous work packages and tendered out to sub-contractors and

specialty contractors, the latter bring labour to execute the contracts. As

such, maintenance of labour records is considered not critical except for

compliance of provisions of various labour laws. These labour records, if

any, are maintained by sub- contractors and specialty contractors who

directly pay labour wages. In practice, the client or builder, though

responsible for the maintenance of labour records, had no such records.

The records are supposedly maintained by contractors who go away on

completion of their respective contracts. As a result, meaningful research

on construction labour is very difficult, if not impossible, as there is little

access to labour data in construction projects; even though its reliability is

often questionable. It needs to be understood that data pertaining to

labour costs and rates would always remain near approximation except in

projects that are executed by big contractors of repute. Another option is

to directly enquire from workers engaged on project work, which is not

possible for completed projects, or go by the prevailing market rates at

the time. One can expect only a limited success in this matter.

Authoritative serial data on the size of construction work force and

its distribution by skill are not available. However, NICMAR studies

bring out the following picture.

165

Table : 5.19

Employment by categories (Projections for 2004-05)

Categories Percentage

Engineers 8.47

Technicians 4.43

Clerical 4.40

Skilled workers 27.62

Unskilled workers 55.08

Total 100

Source: Computed by the NICMAR study group. Taken from

Management and Labour in the Indian Construction Industry –

K.N Vaid (2003)

The distribution of manpower requirements by trades in various

sections was expected to be as under

Table : 5.20

Distribution of manpower requirements by trades in various sectors

( projection for 2004-05)

Trade Percentage

Unskilled workers 54.43

Masons 30.42

Carpenters 7.94

Plumbers 0.32

Electricians 0.47

Others 6.42

100.00

Source: Computed the NICMAR study group, taken from Management

and Labour in the Indian Construction Industry- K.N Vaid

(2003)

166

Generally, in building construction industry, labour is categorized

into skilled, semi-skilled and unskilled.

Figure 5.4

Category of construction labour force on the basis of work and

responsibilities

category Nature of work /trade Responsibility of

reporting to

Skilled Masons, carpenters,

Blacksmiths, stone-cutters,

mechanics, Drivers and clerks

Engineers and senior

level Technical

personnel

Semi- skilled Second class skilled workers

working under first class skilled

workers

First class skilled

workers (Supervisors)

Unskilled

workers

Earth work, stone breaking and

crushing, digging,

transshipment, load carrying and

similar work, include watchmen,

water carriers etc.

The immediate boss

under whom the

person is working

Courtesy : Management and Labour in the Indian Construction Industry-

K.N Vaid (2003)

167

Figure 5.5

The work organization

The line hierarchy of a construction company is as shown below:-

(Courtesy: Management and labour in the Indian construction industry.

K.N. Vaid(2003))

Figure 5.6

The constituents of a work group at the

construction site are as follows:

Come from Report to

Technical pool Engineers

Skilled

Labour pool Semiskilled Gang leader

Unskilled

Clerks

Staff Pool Accounts officer

(Courtesy: Management and labour in the Indian Construction Industry,

K.N Vaid (2003)

Company

Agent/ Director

Sub- contractors Technical personnel, Engineers etc

Staff personnel, accounts, liason etc.

Skilled

workers

Leader of the

unskilled labour force

Clerks

Semi –skilled workers

Unskilled workers

168

Occupation

The majority of the employed construction workers belonged to the

agricultural sector. The construction sector engages 14 types of workers

including brick workers, mason, carpenters, blacksmiths, plumbers and

painters. Out of the 142 samples selected, 40 percent are helpers in the

construction sector followed by masons. Since only workers in the

building construction industry are taken, all the 14 trades cannot be traced

in the sample

Table : 5.21

Classification of construction workers by occupation

Sl No. Type of work No. Percentage

1 Brick worker 10 7.02

2 Mason 25 17.82

3 Carpenter 15 10.54

4 Black smith 7 4.90

5 Plumber 6 4.20

6 Painter 10 7.02

7 Helper 51 35.88

8 Electrician 9 6.31

9 Marble worker 9 6.31

142 100.00

Source: Field survey

Sex Ratio

Majority of the construction workers are males. However, with the

concept of family employment gaining ground, the number of women

workers has started rising in construction sites.

169

Table : 5.22

Classification of construction workers by sex

Sex No Percentage

Male 88 61.97

Female 54 38.03

Total 142 100.00

Source : Field survey

Age composition

Majority of the workers are in the age group of 35-45, followed by

persons belonging to 45-55

Table 5.23

Age composition of construction workers

Age Group No Percentage

18-35 29 20.42

35-45 57 40.14

45-55 48 33.80

>55 8 5.64

Total 142 100.00

Source: Field survey

Experience in construction work by year

Although construction activity forms part of the unorganized

sector, workers usually stick to their work because of the high wage rate

prevalent there. Among the sample workers, 82 percent have experience

of more than 10 years, and 5 percent of more than 40 years in the

construction sector

170

Table : 5.24

Experience in construction work by year groups

Years of

experience

No. of workers

Percentage Male Female Total

0.5 6 2 8 5.65

5-10 12 5 17 11.97

10-20 18 10 28 19.71

20-30 23 19 42 29.57

30-40 25 15 40 28.17

More than 40 4 3 7 4.93

Total 88 54 142 100.00

Source: Field survey.

The number of workers in the 0-5 years category comes only to

5.65 percent. This finding implies that the new generation seldom enters

this field.

Marital status

Among the 142 sample workers, 86 per cent are married 6 per cent

are unmarried, 5 per cent are widowed and 3 per cent are divorced and

separated

Table : 5.25

Marital status of construction workers

Type No Percentage

Married 122 85.91

Unmarried 9 6.33

Widowed 7 4.92

Divorced / separated 4 2.84

Total 142 100.00

Source: Field survey.

171

Community status

Majority of the construction workers belonged to other backward

community, followed by scheduled castes and then forward community.

Scheduled Tribes are absent in the sample selected for study.

Table : 5.26

Classification of construction workers by community

Social group No Percentage

Scheduled caste 36 25.35

Scheduled tribe 0 0

Forward community 28 19.73

Other backward

community

78 54.92

Total 142 100.00

Source: Field survey.

Educational status of construction workers

In the sample studied almost 10 per cent are illiterates. Majority of

the construction workers in the sample have got upper primary education

(28.87 per cent). Graduates numbering 5 and one postgraduate are found

in the study. Those who got professional education were absent in the

sample selected.

172

Table : 5.27

Educational status of construction workers

Educational status No Percentage

Illiterate 14 9.85

Lower primary

education

36 25.35

Upper primary

education

41 28.87

Secondary education 31 21.83

Higher secondary

education

14 9.85

Graduates 5 3.52

Post Graduates 1 0.73

Professional education 0 0

Total 142 100.00

Source Field survey

Participation in political activities and association with trade unions

People in Kerala are, in general, politically active and construction

workers are not an exception. Although construction workers are found

to have membership in one or other trade unions, they are not active as is

seen in other sectors. Perhaps the reason for this is that construction

belongs to the unorganized sector of the economy. Although there is a

positive correlation between active participation in political activities

and active participation in trade union activities, the same is not strong

in the construction sector.

173

Table : 5.28

Politics and trade union activities among construction workers

Nature of association Political parties Trade unions

No Percentage No Percentage

Active membership 38 26.76 18 12.67

Passive membership 68 47.88 112 78.87

No membership 36 25.36 12 8.46

Total 142 100.00 142 100.00

Source: Field survey

Work availability for construction workers

Construction work is essentially temporary, outdoor and piece rate.

Since the tenure of employment is purely temporary, one cannot view his

job beyond the contract period. There occurs constant change in the

workplace, and of the employers for most of the workers. Therefore,

work availability is an important issue among construction workers.

Majority of the workers got an average of 10 to 15 days work per month

(40 per cent) 30 percent of the workers in the sample got 15 to 20 days

work and 22 percent of the workers got 20 to 25 days of work on an

average in a month.

Table : 5.29

Work availability for construction workers

Average number of days per month No Percentage

0 to 10 12 8.45

10 to 15 57 40.14

15 to 20 43 30.28

20 to 25 30 21.13

>25 0 0

Total 142 100.00

Source: Field survey

174

It is to be noted that health factors, household responsibilities and

alternative employment opportunities are sometimes found to be the

reason for short period construction workers.

Daily wage Rates

In Kerala, unlike the other states in the country, construction

workers get high wage rates. It can also be noted that the wage rates

existing in the construction sector are one of the highest in the

unorganized sector.

Table : 5.30

Daily wage Rates of construction workers

Sl.

No.

Construction worker Daily wages (Rs)

Rural Urban

1 Mason first class 325 360

2 Mason second class 300 325

3 Carpenter first class 350 375

4 Carpenter Second class 275 300

5 Brick worker First class 350 370

6 Brick worker second class 280 320

7 Blacksmith 300 320

8 Plumber 225 240

9 Painter 285 310

10 Electrician 200 240

11 Helpers:-

Unskilled Male labour

Unskilled Female labour

250

175

275

200

12 Marble worker 320 350

Source: Field survey

175

The recruitment of construction workers is usually done by labour

recruitment agencies spread all over Kerala. These agencies are

responsible for hiring labour, retaining them during the contract period

and bringing them back when the company has a new contract. In North

India, labour recruitment is done through the institution of Jamadari and

peshgi systems. Jamadar recruits workers by paying them an advance

money called peshgi. A worker pledges his labour in return for peshgi

(Vaid, 2003)7. This practice is not prevalent in Kerala. The Jamadar, in

addition to the income from the employer will also have collections from

the workers. Majority of the migrant labour force from the Northern

parts of India engaged in the building construction sites are recruited in

this manner.

In Kerala also regular deductions from the daily wages paid to the

construction workers are not uncommon. But the plight of the local

workers engaged here is far better than their northern counterparts.

Over the last one and a half decade, Kerala has witnessed an

inward migration of workers from states as far as Bihar, Orissa, West

Bengal and Assam besides from the neighbouring states of Tamil Nadu

and Andhra Pradesh.

Migrant workers are employed in tile and brick manufacturing

units in several parts of Kerala. These workers are brought by labour

contractors. There are large number of migratory workers employed in

the construction sector. Their main concentration is in urban centres and

towns. Most of them are seasonal workers. They generally return home

soon after their work. Very few stay back here. Visiting the sites and

taking their number along with the type of work done by them is the only

option available. The situation in the migrant labour colonies is far from

satisfactory. Lack of basic facilities like drinking water, washing and

toilet facilities make their exclusive settlements away from the

176

mainstream. There are several migrant labour settlements across the

cities and towns of Kerala. There are migrant labour settlements in areas

such as Kallekad, Kalmandapam and Sundharam colonies in Palakkad.

The phenomenon of job migration is bringing with it a host of

problems as well. The authorities take a myopic approach towards

migrant workers and as such the implementation of the Inter-state

Migrant Act, has been tardy (Prabhakaran and Santhosh, 2007)8.

In this chapter, an attempt is made to measure the overall

performance of the construction sector, especially the residential

construction sector in Kerala. The results of the study point to a much

more concerted efforts on the part of all stakeholders for achieving higher

performance levels by the various construction firms. The lack of

uniformity in business practices is the main road- block in drafting a

comprehensive policy. The general approach should be to upgrade the

techniques and reduce wastage in construction. Along with this, socially

responsible real estate practices need to be put in place to achieve

enduring solutions.

LINKAGES IN THE CONSTRUCTION INDUSTRY – A

HYPOTHETICAL EXAMPLE

Construction is a hybrid of both manufacturing and service

activities. Investment in construction naturally leads to additional

investments in both the manufacturing and service sectors.

Let us take a hypothetical example of construction of 1 lakh sq. ft.

buildings with 100 housing units in rural and urban areas of Kerala

separately in order to measure the extent of linkages.

In Kerala, the land values differ in rural and urban areas with the

latter having a value of 4 times the value of the former. Let us assume

that, on an average, the land value in rural area is Rs. 50,000 per cent

where as it is Rs. 2 lakhs in urban areas. For the construction of 1 lakh

177

sq. feet of building, we require 1 acre of land which will cost Rs. 50 lakhs

in rural areas and Rs. 200 lakhs in urban areas.

Let us also assume that the project cost comes to Rs. 12 crores

(excluding land value). There is no marked distinction in the cost of

construction between rural and urban areas. The material carrying cost to

the site is more in rural areas. But this is offset by a higher labour cost in

urban areas.

It is also assumed that 20 to 30 per cent of the material cost and 5

to 10 percent of service costs find outlets in the form of additional

investments in the allied sectors of the state economy.

The period for finishing the project is estimated to be 2 years. A

total of 5 years from the date of inception of the project is taken for

consideration. The first two years demonstrate the impact of backward

linkages and the next three years that of forward linkages. Forward

linkages are predominantly in the form of service sector linkages, the

outcome of which is not exactly measurable. But, in this example, it is

assumed that additional investment in the service sector is to the tune of 5

to 10 per cent of any fresh investment in the construction sector.

In backward linkages, the ratio of additional sectoral investments

between manufacturing and service sector is assumed to be 2:1. In

forward linkages, it is assumed to be 1:2.

The project work begins on 1st January 2001 and the construction

work is finished on 31st December 2002. The maintenance and other

service costs begin from 1st January, 2003. It is assumed that the cost

incurred in the subsequent stages of production is 1 per cent of the total

construction cost in the first year, 3 per cent in the second year and 5 per

cent in the third year.

178

Apart from estimating and analyzing fresh investments and

additional investments separately for rural and urban areas, the example

is based on two different assumptions:-

(1) The material, labour and other inputs are made available from the

state itself; and

(2) The materials (excluding land and sand), labour (excluding 40 per

cent being provided locally), and all other inputs are brought from

outside the state.

The break up cost is estimated as follows:

Table 5.31

The estimated break up cost of the projects

(Rs. In lakhs)

Item First

Year

Second

Year

Third

Year

Fourth

Year

Fifth

Year

R U R U R U R U R U

Land 50 200 - - - - - - - -

Construction

Cost

400 350 800 850 12.5 14.0 37.5 42.5 62.5 70.0

Total 450 550 800 850 12.5 14.0 37.5 42.5 62.5 70.0

(Source : Survey)

R = Rural

U = Urban

3

4

5

6

7

8

179

Table 5.32

Analysis of construction cost in respect of a rural project in the first year of the project and estimation of Additional

Investment in Allied Sectors in the next four years under assumption No. 1. (Rs. In lakhs)

Sl. No. Item Fresh Investment

(2001)

Additional Investments

Percentage Value 2002 2003 2004 2005

1 Land 11.11 50 15.00 4.50 5.85 7.60

2 Survey and Soil investigation,

Tendering, Design and Project

Management Consultants

4.63 20.85 2.08 0.20 0.23 0.25

3 Personnel :

Labour 14.20

Staff and Officers 2.31

Labour Colonies 2.31

Mobilisation 2.78

21.60

97.21

9.72

0.97

1.07

1.17

4 Materials 39.84 179.30 53.79 16.13 20.97 27.26

5 Plant Equipment 6.48 29.20 8.76 2.62 3.41 4.43

6 Insurance and bank interest 7.42 33.34 3.33 0.33 0.37 0.41

7 Miscellaneous

(Project office, Travel, Head office

expenses including agency

commission)

8.92 40.10 4.01 0.40 0.44 0.48

Total 100.00 450.00 96.69 26.20 32.34 41.60

Source : Survey.

180

Table 5.33

Analysis of Construction cost in respect of a rural project in the Second Year and Estimation of additional

investments in the next three years. (Rs. In lakhs)

Sl.

No.

Item Fresh Investment

(2002)

Additional Investments

Percentage Value 2003 2004 2005

1 Land - - - - -

2 Survey and Soil investigation,

Tendering, Design and Project

Management Consultants

- - - - -

3 Personnel :

Labour 16.85

Staff and Officers 2.74

Labour Colonies 2.74

Mobilisation 3.30

25.63

205.04

20.50

2.05

2.25

4 Materials 47.30 378.40 113.52 34.05 44.27

5 Plant Equipment 7.70 61.60 18.48 5.54 7.20

6 Insurance and bank interest 8.80 70.40 7.04 0.70 0.77

7 Miscellaneous

(Project office, Travel, Head office

expenses including agency commission)

10.57 84.56 8.45 0.85 0.93

Total 100.00 800.00 167.99 43.19 55.42

Source : Survey.

181

Table 5.34

Analysis of cost of maintenance and service in respect of a rural

project after construction and estimation of additional investments in

subsequent years of construction.

(Rs. In lakhs)

Fresh

Investments

(Year)

Rs.

(lakhs)

Additional Investment

2004 2005

2003 12.5 1.25 1.37

2004 37.5 - 3.75

2005 62.5 - -

Total 112.5 1.25 5.12

(Source : Survey)

According to the above tables 5.32 and 5.33, the total construction

cost incurred (Rural Project) in the first two years i.e., 2001 and 2002 is

Rs. 1250 lakhs, The total of additional investment estimated for the 4

years i.e. 2002, 2003, 2004 and 2005 comes to Rs. 463.23 lakhs. 2/3 of

this will be 308.82 lakhs takes place in the manufacturing sector and the

balance Rs. 154.41 lakhs takes place in the service sector.

Fresh investment in respect of cost of maintenance and service for

three years (Table 5.34) i.e., 2003, 2004 and 2005 comes to Rs. 112.5

lakhs which will lead to an additional investment of Rs. 6.37 lakhs for

2004 and 2005. It is estimated that of this, 2/3 i.e. Rs. 4.24 lakhs of

additional investment takes place in the service sector and the balance Rs.

2.12 lakhs happens in the manufacturing sector.

182

Table – 5.35

Analysis of construction cost in respect of an urban project in the first year and estimation of additional investments

in the next four years. (Rs. In lakhs)

Sl. No. Item Fresh Investment

(2001)

Additional Investments

Percentage Value 2002 2003 2004 2005

1 Land 36.36 200 60.00 18.00 23.40 30.42

2 Survey and Soil investigation,

Tendering, Design and Project

Management Consultants

3.05 16.76 1.67 0.16 0.18 0.20

3 Personnel :

Labour 12.58

Staff and Officers 1.85

Labour Colonies 1.85

Mobilisation 2.22

18.50

101.74

10.18

01.02

01.12

01.23

4 Materials 28.13 154.70 46.69 14.00 18.20 23.67

5 Plant Equipment 4.44 24.19 7.26 2.17 2.83 3.67

6 Insurance and bank interest 5.17 28.42 2.84 .28 .31 .34

7 Miscellaneous

(Project office, Travel, Head office

expenses including agency

commission)

4.44 24.19 2.42 .24 .26 .29

Total 100.00 550.00 131.06 35.87 46.30 59.82

Source : Survey.

183

Table – 5.36

Analysis of Construction cost of an urban project in the second year and the estimation of additional investment in

the next three years

(Rs. In lakhs)

Sl.

No.

Items Fresh Investment

(2002)

Additional Investments

Percentage Value 2003 2004 2005

1 Land - - - - -

2 Survey and Soil investigation,

Tendering, Design and Project

Management Consultants

- - - - -

3 Personnel :

Labour 20.73

Staff and Officers 3.05

Labour Colonies 3.05

Mobilisation 3.66

30.49

259.17

25.92

2.59

2.85

4 Materials 46.34 393.89 118.17 35.45 46.08

5 Plant Equipment 7.32 62.22 18.66 5.59 7.27

6 Insurance and bank interest 8.53 72.50 7.25 .73 .79

7 Miscellaneous

(Project office, Travel, Head office

expenses including agency commission)

7.32

62.22

6.22

.62

.68

Total 100.00 850.00 176.22 44.98 57.67

(Source : Survey)

184

Table – 5.37

Analysis of cost of maintenance and services in respect of an urban

project after construction and estimation of additional investment in

the subsequent years

Fresh

Investments

(Year)

Rs. In lakhs Additional Investments

2004 2005

2003 14.00 1.4 1.54

2004 42.00 - 4.20

2005 70.00 - -

Total 126.00 1.4 5.74

(Source : Survey)

According to the above Table 5.35 and 5.36 the total construction

cost incurred (Urban Project) in the first two years i.e., 2001 and 2002 is

Rs. 1,400 lakhs. The total of additional investment estimated for the four

years i.e., 2002, 2003, 2004 and 2005 comes to Rs. 551.92 lakhs. Of this

2/3 i.e. Rs. 367.94 is invested in the manufacturing sector and the balance

Rs. 183.97 lakhs in the service sector.

Fresh investment in respect of cost of maintenance and service for

three years i.e., 2003, 2004 and 2005 (Table 5.37) comes to Rs. 126.00

lakhs which will lead to an additional investment of Rs. 7.14 lakhs in the

years 2004 and 2005. Of this, Rs. 4.76 lakhs worth of investments

happen in the service sector and the balance Rs. 2.38 lakhs in the

manufacturing sector.

Alternative Situation under Second Assumption

An alternative situation is worked out under the second

assumption. In this situation, only land, sand and 40 per cent of the

personnel are available from within the state. All other material inputs

185

including plant and equipment services are brought from outside the state.

This will reduce the funds available with the construction participants for

additional investment. In the case of materials (except sand), the

additional investments will be 6 per cent of the fresh investments. In the

case of survey, soil investigation etc. it is only 2 per cent. Additional

investments from local labour would be 10 per cent but it is only 5 per

cent in the case of migrant labour cost. In the case plant and equipment

services, insurance and banking services and miscellaneous expenditure

the additional investment will be restricted to 2 per cent of any fresh

investment in the construction sector.

There may not be any marked variation in the investment

behaviour in respect of service and maintenance activities as a major part

of these activities are provided locally.

186

Table – 5.38

Analysis of construction cost in respect of rural project in the first year and estimation of additional investment in

the next four years

(Rs. In lakhs)

Sl. No. Item Fresh Investment

(2001)

Additional Investments

Percentage Value 2002 2003 2004 2005

1 Land 11.11 50.00 15.00 4.50 5.85 7.60

2 Survey and Soil investigation,

Tendering, Design and Project

Management Consultants

4.63

20.85

.42

.04

.05

.05

3 Personnel

Migrant 12.96 58.22 2.91 .14 .15 .16

Local 8.64 38.88 3.89 .39 .42 .47

4 Materials 37.55 168.79 10.13 3.95 4.22 5.49

5 Plant Equipment 6.42 29.20 0.58 0.06 0.07 0.07

6 Sand 2.39 10.75 3.22 0.96 1.25 1.63

7 Insurance and bank interest 7.40 33.31 0.66 0.07 0.08 0.08

8 Miscellaneous

(Project office, Travel, Head office

expenses including agency

commission)

8.90 40.00 0.80 0.08 0.09 0.09

Total 100.00 450.00 37.61 10.19 11.98 15.64

Source : Survey.

187

Table – 5.39

Analysis of Construction cost in respect of a rural project in the second year and estimation of additional

investments in the next three years.

(Rs. In lakhs)

Sl.

No.

Items Fresh Investment

(2002)

Additional Investments

Percentage Value 2003 2004 2005

1 Land - - - - -

2 Survey and Soil investigation,

Tendering, Design and Project

Management Consultants

- - - - -

3 Personnel :

Migrant 15.38 123.00 6.15 0.31 0.32

Local 10.25 82.00 8.20 0.82 0.90

4 Materials 44.46 356.80 21.40 6.42 8.34

5. Sand 2.84 22.70 6.82 2.04 2.66

6 Plant Equipment 7.70 60.60 1.23 0.12 0.13

7 Insurance and bank interest 8.80 70.40 1.40 0.14 0.15

8 Miscellaneous

(Project office, Travel, Head office

expenses including agency commission)

10.57 84.50 1.69 0.17 0.18

Total 100.00 800.00 47.89 10.02 12.68

Source : Survey.

188

Table – 5.40

Analysis of construction cost in respect of urban project in the first year and estimation of additional investments in

the next four years

(Rs. In lakhs)

Sl. No. Item Fresh Investment

(2001)

Additional Investments

Percentage Value 2002 2003 2004 2005

1 Land 36.36 200.00 60.00 18.00 23.40 30.42

2 Survey and Soil investigation,

Tendering, Design and Project

Management Consultants

3.05 16.76 0.33 0.03 0.03 0.04

3 Personnel

Migrant 11.10 61.05 3.05 0.15 0.16 0.17

Local 7.40 40.69 4.07 0.41 0.44 0.49

4 Materials 26.45 145.46 8.72 2.60 3.40 4.41

5. Sand 1.68 9.23 2.77 0.83 1.08 1.40

5 Plant Equipment 4.44 24.19 0.48 0.05 0.06 0.07

6 Insurance and bank interest 5.17 28.42 0.57 0.06 0.07 0.08

7 Miscellaneous

(Project office, Travel, Head office

expenses including agency

commission)

4.44 24.19 0.48 0.05 0.06 0.07

Total 100.00 550.00 81.81 22.31 28.85 37.31

Source : Survey.

189

Table – 5.41

Analysis of Construction cost in respect of urban project in the second year and estimation of additional investments

in the next three years.

(Rs. In lakhs)

Sl.

No.

Items Fresh Investment

(2002)

Additional Investments

Percentage Value 2003 2004 2005

1 Land - - - - -

2 Survey and Soil investigation,

Tendering, Design and Project

Management Consultants

- - - - -

3 Personnel :

Migrant 18.29 155.46 7.77 0.38 0.40

Local 12.20 103.71 10.37 1.03 1.14

4 Materials 43.56 370.25 22.21 6.66 8.66

5 Sane 2.78 23.64 7.09 2.12 2.76

6 Plant Equipment 7.32 62.22 1.24 0.12 0.13

7 Insurance and bank interest 8.53 72.50 1.45 0.14 0.15

8 Miscellaneous

(Project office, Travel, Head office

expenses including agency commission)

7.32 62.22 1.24 0.12 0.12

Total 100.00 850.00 51.37 10.57 13.36

Source : Survey.

190

According to Tables 5.38 and 5.39, a fresh investment of Rs. 1250

lakhs in construction in respect of rural project in the first two years

would lead to additional investment in allied sectors to the time of Rs.

147.43 lakhs in the next 4 years. These are estimated under the second

assumption. It is only 31.82 percent of the total additional investment

under first assumption.

As per Table 5.40 and 5.41, a fresh investment of Rs. 1400 lakhs in

the construction of an urban project in the first two years would lead to a

total additional investment of Rs. 245.58 lakhs in the next four years.

These are estimated under the second assumption. This is only 44.49

percent of the total additional investment under the first assumption.

Forward Linkages

Based on the above hypothetical example, the following forward

linkages have been traced.

1) Demand for furniture, 2) consumer durable, 3) desk top computers 4)

security, 5) laundry 6) gardening 7) cost of maintenance 8) cost of

decoration of the units 9) insuring the residential units and 10) marketing

the existing units for the purpose of sale.

Closely related to the forward linkages is the consumption linkage

through increased demand for goods and services especially, Fast Moving

Consumer Goods (FMCG). However, it is very difficult to trace each and

every item that becomes part of the forward linkage.

Backward Linkages

Based on the above hypothetical example, the following backward

linkages are traced. They include mainly the inputs, that is, material and

non material. The main items are listed below.

191

1) Land, 2) sand, 3) cement, 4) steel, 5) brick 6) insulation, 7) wood, 8)

tiles 9) paint, 10) sanitary ware 11) electrical lighting and 12) fittings.

Besides the above, a number of professional services are needed

from the outset of a project till its completion. All types of labour namely,

skilled, semi skilled and unskilled are required to undertake the project. It

is estimated that a large number of manufacturing industries are

dependent on the construction industry for their survival, growth and

expansion. The impact of the construction industry on the commodity

market, the labour market and the financial market is phenomenal. While

assessing the linkages of the construction sector, it is found that,

backward linkages are more exactly measurable than forward linkages.

References

1. Op. Cit.

2. Op. Cit.

3. NICMAR Journal of Construction Management April – June 2002,

Vol. XVII, No.II, p.172071-77. The Future of Construction is EPC

Business, p.172071-77.

4. Op. Cit.

5. Op. Cit.

6. Op. Cit.

7. Op. Cit.

8. Op. Cit.