CEBC GENERATE CONFERENCE – PLENARY 8
November 28, 2018
Jamie Bassett – Tla-o-qui-aht First Nation
Ben Whyte – Barkley Project Group
@barkleyprojectgroup
Owned & Operated
by
Developed in partnership with
• 4 MW Siemens Generator (Siemens)
• 5 Jet Pelton Turbine (Mavel)
• 42” HDPE 367 m Penstock
• 36” Steel Penstock 218 m
• Net Head 155 m
• Coanda Style Intake
• 16” Tributary Tap HDPE 680 m
• 40 year Electricity Purchase Agreement
with BC Hydro through Standing Offer
Program
• 100% Owned & Operated by Tla-o-qui-aht
First Nation (TFN)
• 3rd Hydropower development by TFN
2010-2016
Feasibility & Design
2016-2018
Project Construction
October 2018
Operational Hydro-Plant
Tofino
Ucluelet
• TFN Land Vision and Tribal Park
• Winchie Creek is 3rd of 7 Run of River Projects
planned for TFN’s Tribal Park, all owned by TFN
• Proceeds from economic development
contribute to Guardianship and Tribal parks
initiatives such as fisheries restoration
• Provision for a salmon spawning side channel to
be rehabilitated at Winchie Creek