PROJECT GOALS
• Address severe erosion of Headland (historical rate average of 45 ft per year)
• Protect and sustain unique coastal habitats, Chenier Ridges, essential for migratory birds
• Reduce wave energy & saltwater intrusion into back barrier environments
• Provide sediment source to sustain barrier breaches east and west of the Headland
PROJECT LOCATION MAP
CAMINADA HEADLAND BBBS RECOMMENDED PLAN
CAMINADA HEADLAND FOOTPRINT OPTIONS 1-3
CAMINADA HEADLAND TYPICAL DESIGN TEMPLATES BEACH ONLY
CAMINADA HEADLAND TYPICAL DESIGN TEMPLATES BEACH AND DUNE
CONCEPTUAL CONVEYANCE CORRIDORS
CONCEPTUAL BELLE PASS PUMP-OUT AREA
CONCEPTUAL PASS FOURCHON PUMP-OUT AREA
CONCEPTUAL OFFSHORE RE-HANDLING / PUMP-OUT AREA
DESIGN SCHEDULE
• Data Collection May 2011 – October 2011• Preliminary Design May 2011 – December
2011• Permitting September 2011 – April 2012• Final Design January 2012– April 2012