CAMINADA HEADLAND BEACH / DUNE RESTORATION Governor’s Advisory Commission on Coastal Protection, Restoration and

Conservation Meeting October 5, 2011

• Project Overview

• Fill Template Options

• Conveyance Corridor Options

• Project Schedule

Outline

PROJECT GOALS

• Address severe erosion of Headland (historical rate average of 45 ft per year)

• Protect and sustain unique coastal habitats, Chenier Ridges, essential for migratory birds

• Reduce wave energy & saltwater intrusion into back barrier environments

• Provide sediment source to sustain barrier breaches east and west of the Headland

PROJECT LOCATION MAP

CAMINADA HEADLAND BBBS RECOMMENDED PLAN

CAMINADA HEADLAND FOOTPRINT OPTIONS 1-3

CAMINADA HEADLAND TYPICAL DESIGN TEMPLATES BEACH ONLY

CAMINADA HEADLAND TYPICAL DESIGN TEMPLATES BEACH AND DUNE

CONCEPTUAL CONVEYANCE CORRIDORS

CONCEPTUAL BELLE PASS PUMP-OUT AREA

CONCEPTUAL PASS FOURCHON PUMP-OUT AREA

CONCEPTUAL OFFSHORE RE-HANDLING / PUMP-OUT AREA

DESIGN SCHEDULE

• Data Collection May 2011 – October 2011• Preliminary Design May 2011 – December

2011• Permitting September 2011 – April 2012• Final Design January 2012– April 2012