BOSTON ARTS ACADEMYSCHOOL BUILDING COMMITTEE MEETING
NOVEMBER 9, 2017
2
Introductions
Schedule
Space Summary
Design Update
Project Budget
Vote
AGENDA
3
November 9, 2017 Submit Schematic Design Package to the MSBANovember 15, 2017 Anticipate Introducing Funding Agreement to City Council for ConsiderationDecember 1, 2017 Construction Manager @ Risk InterviewsDecember 13, 2017 MSBA Board Vote & City Council VoteJanuary 2018 Funding Agreement is executed
Design Development BeginsConstruction Manager @ Risk begins work
April 2018 Early Construction Work begins at Cleveland SchoolJuly 2018 BAA begins move out of 174 Ipswich Street
Remaining Construction Work @ Cleveland School BeginsAugust 2018 Construction Complete @ Cleveland School
BAA Moves Into Swing SpaceSeptember 2018 Begin Abatement at 174 Ipswich StreetNovember 2018 Begin Demolition @ 174 Ipswich Street
BAA SCHEDULE UPDATE
4
Core Academic
Special Education
Art & Music
Vocations & Tech.
Health & Phys. Ed.
Media Ctr/Library
Auditorium
Dining & Food Serv.
Medical
Admin & Guidance
Custodial/Maint.
Other
v1499.8K NSF
149.7K GSF
SPACE SUMMARY UPDATE
24915
4680
27545
11055
7700
3755
10595
5475
660
3435
1735
465
PSR Update (v14) Schematic Design (v18)MSBA
79.8K NSF119.7K GSF
V18102.0K NSF
153.5K GSF
-60
+30
-115
+50
-50
+105
+3095
-25
0
+15
-15
+185
5
NEW BUILDINGLEVEL 1
6
HEART OF THE SCHOOL
7
AUDITORIUM LOBBY
8
NEW BUILDINGLEVEL 2
9
VIEW FROM LAST ROW OF ORCHESTRA PRIOR TO BALCONY SHIFT
VIEW FROM LAST ROW OF ORCHESTRA AFTER BALCONY SHIFT
VIEW FROM LAST ROW OF BALCONY PRIOR TO SHIFT
VIEW FROM LAST ROW OF BALCONY AFTER SHIFT
AUDITORIUM SIGHT LINES
10
SIGHTLINE SECTION WITHOUT ORCHESTRA PIT
SIGHTLINE SECTION WITH ORCHESTRA PIT AND BALCONY SHIFT
TOTAL AUDITORIUM AREA SUMMARY
LEVEL/CONFIGURATION SEAT COUNT NSF NSF/SEAT
WITHOUT ORCHESTRA PIT 496 6,418 12.9
WITH ORCHESTRA PIT 496 6,905 13.9
WITH ORCH. PIT & BALCONY SHIFT 502 7,483 14.9
AUDITORIUM SIGHT LINES55’
68’
11
GALLERY & BALCONY LOBBY
12
NEW BUILDINGCATWALK
13
NEW BUILDINGLEVEL 3
14
NEW BUILDINGLEVEL 4
15
NEW BUILDINGLEVEL 5
16
3D VIEWSVAN NESS STREET
17
3D VIEWSIPSWICH STREET
18
3D VIEWSIPSWICH STREET
19
3D VIEWSFENWAY PARK
20
SHADING STUDIESWHOLE BUILDING
NORTHWEST - BASELINE
NORTHWEST - SHADING
• 26% reduction in solar radiation gains with shading
• Saves on cooling load and energy needs
• Reduces glare and visual discomfort in core learning areas
• 41% reduction in solar radiation + glare per classroom
• Daylight Autonomy >75% still achieved
OPTI
MAL
RAN
GE
21
SHADING STUDIESWHOLE BUILDING
SOUTHEAST- BASELINE
SOUTHEAST - SHADING
• 26% reduction in solar radiation gains with shading
• Saves on cooling load and energy needs
• Reduces glare and visual discomfort in core learning areas
• 41% reduction in solar radiation + glare per classroom
• Daylight Autonomy >75% still achieved
OPTI
MAL
RAN
GE
22
SITE PLAN
23
LANDSCAPE
24
LANDSCAPE
25
PROJECT BUDGET UPDATE
Construction Cost: $95,976,807
Project Budget: $124,755,413