AQP-WF 1

INTRODUCTION TO RADIUSTitle V

Air Permit Application

New Jersey Department of Environmental Protection

(December 6, 2011)

AQP-WF 2

Air Permit Application

RADIUS software available at: http://www.state.nj.us/dep/aqpp/radius.html Use for non-confidential information

Save RADIUS application on CD and send to DEP

Helplines at: http://www.state.nj.us/dep/aqpp/contact.html

AQP-WF 3

RADIUS Forms

Used for all applications Major and Non-major facilities New and modified sources Use latest version of RADIUS

For Operating Permit Renewals with attachment at: http://www.state.nj.us/dep/aqpp/applying.html

Except Non-Technical Amendments http://www.state.nj.us/dep/aqpp/applying.html

AQP-WF 4

Confidential Information

Need two applications RADIUS to include non-confidential info only Complete Paper Application Consistent with N.J.A.C. 7:27-1

http://www.state.nj.us/dep/aqm/Sub1.pdf

Emission Info may not be confidentialAll info considered confidential until

decision of confidentiality is made

AQP-WF 5

Application InformationN.J.A.C. 7:27-1

See N.J.A.C. 7:27-1 (Definitions)Includes, but not limited to,

Facility Name and location Emission type and rate Frequency and duration of release Maximum production rate Emission estimation methods

AQP-WF 6

Pre-Application Information

Need ID# (or PI#) Use form AIMS-099A

Need PIN code Use form AIMS-099B

Forms available at: http://www.state.nj.us/dep/aqpp/applying.html

AQP-WF 7

Certification

Either electronic or paperElectronic preferred

Need PIN code Use form AIMS-099B

Paper certification at: http://www.state.nj.us/dep/aqpp/applying.html

AQP-WF 8

Application Completeness

Administrative Check Errors Warnings

Instructions To be updated soon http://www.state.nj.us/dep/aqpp/applying.html

AQP-WF 9

Additional Information

Compliance DemonstrationSubmit information electronically

whenever possible Attach files directly to RADIUS forms, or Include separately on the CD

AQP-WF 10

APPLICATION EXAMPLE

INTRODUCTION TO RADIUSTitle V

EXAMPLE OF AN EMISSION UNIT

AQP-WF 11

Example…Adding Equipment

Boiler280 MMBTU/hr heat inputFuel Burned

Natural gas #2 fuel oil (backup)

Hours of Operation: 4000 hrs/yrOne 10,000 Fuel Oil Storage Tank

AQP-WF 12

Select “file” to activate the drop down menu.To create a new application select “New” from the drop down menu.

AQP-WF 13

Adding a new source select“Title V Operating permit” from the drop down menu.

Select permitapplication

AQP-WF 14

Select “OK” to go to main menu

AQP-WF 15

Double click on “Reason for Application”

AQP-WF 16

Enter reasons + any other relevant information.

AQP-WF 17

Double click on “Facility Profile (General)

AQP-WF 18

Select “contact information” from the drop down menu

Select “Owner” from the drop down menu

AQP-WF 19

Select “Responsible Official” - mandatory

AQP-WF 20

Select “Responsible Official” - mandatory

AQP-WF 21

Double click on “Equipment Inventory”

AQP-WF 22

The application adds two pieces of equipment.Enter all required information.

AQP-WF 23

Highlight equip row and select “edit details” to open the equip detail sheet. Enter all details.

AQP-WF 24

Highlight next equip row andHighlight next equip row andselect “edit details” toselect “edit details” toopen the equip detail sheet.open the equip detail sheet.Enter all equip details.Enter all equip details.

AQP-WF 25

Double click on “Control Device Inventory”

AQP-WF 26

Control device is one RTOCanister Regenerative Thermal Oxidizer.

AQP-WF 27

Highlight control device row andselect “edit details” to open the CD detail sheet. Enter all details.

Once the CD details are completeClick “OK”

AQP-WF 28

Double click on “Emission Point Inventory”

AQP-WF 29

Enter emission point details.

AQP-WF 30

Double click “Emission Unit/Batch Process Inventory”

AQP-WF 31

Two Emission Units.

Select “Emission Unit Operating Scenarios” tab.

Select “each raw and enter the respective information”

AQP-WF 32

AQP-WF 33

Select U2 “Edit Detail”

AQP-WF 34

Emission unit 1 (U1) has two operating scenarios.Enter all information.

Double click to open CD and PT fields.

AQP-WF 35

Highlight row OS2, select “edit details” and enter data.

AQP-WF 36

Highlight row U2-OS1, select “edit details” and enter data.

AQP-WF 37

Double click “Potential to Emit”

AQP-WF 38

Select “Emission Unit” from drop down menu.

AQP-WF 39

Select “U1 Boiler” from drop down menu.

AQP-WF 40

Select “U1-OS1 & OS2 Boiler” from drop down menu.And enter the lb/hr emissions

AQP-WF 41

Select “Emission Unit 1- OS1” from drop down menu.And follow the same procedure as with U1 – OS0 before

AQP-WF 42

Select “Emission Unit 2” from drop down menu.And follow the same procedure as with U1 before

AQP-WF 43

Select “Compliance Plan”

AQP-WF 44

Select “Emission Unit” from drop down menu.

AQP-WF 45

Select “OS0” and add tons/year.

AQP-WF 46

Select “OS0” and add emissions tons/year, and rules that apply to all OSs.

AQP-WF 47

Select “OS1” and add emissions Lb/hr, and rules that apply to each OS individually.

AQP-WF 48

Select “Submit” from the drop down menu.

AQP-WF 49

Select “OK”

AQP-WF 50

The system performs an administrative check.If no “errors” are found, select “certify”.If errors are found return to fix them.

AQP-WF 51

Certification may be done electronically or manually. For this case select “Skip Electronic Certification”.

AQP-WF 52

The “Select File” dialogue box appears.

AQP-WF 53

Install CD disc in A-drive.Select “CD Disc” option from drop down menu and select “save”.Beginning “May 1, 2010” The Radius application will be the only form accepted by the Department as official one.

AQP-WF 54

Announcement confirms that the export is successful.Select “OK”. The application is complete!

AQP-WF 55

Tips

In an Emission Unit, an operating scenario can consist of multiple emission points and control devices, but only 1 piece of equipment

Insignificant sources and non-source fugitive sources are only specified for Title V operating permits

In the Emission Unit Operating Scenario screen, double-click the Control Device, Emission Point, and SCC fields to enter data

AQP-WF 56

More Tips

The File\Submit command does not electronically transfer the file to DEP Copy the file to CD-ROM and mail it to DEP Permit modifications must only include the data

that is being added or changed Don’t submit an edited version of the full permit

application Electronic code of Federal regulations -

http://ecfr.gpoaccess.gov/cgi/t/text/text-idx?c=ecfr&tpl=%2Findex.tpl

AQP-WF 57

QUESTIONS…?