UNIVERSAL M. ENTP.
www.affordablehousing.ug
AFFORDABLE HOUSING & MUCH MORE
JAN 16 – JAN 31
JUPITER APARTMENTS – PHASE 02
NAJJERA
1BED & 2 BED APARTMENTS – TOTAL 40 UNITS
JUPITER APARTMENTS
PHASE 2
FOOTINGS FOR BOTH BUILDINGS COMPLETE
PLINTH BEAM & WALL UPTO PLINTHUNDER PROGRESS
SETTING OUT COMPLETED ON SITE
EXCAVATION FOR PLINTH BEAM
SITE WORK STARTED FOR JUPITER – PHASE 02BACK FILLING OF EARTH
WALL CONSTRUCTED UPTO PLINTH LEVEL
EXCAVATION FOR BOTH BUILDINGS COMPLETE
BACK FILLING IN PROGRESS
BACK FILLING FOR BOTH BUILDINGS IN PROGRESS
BACK FILLING COMPLETE
BRICK WORK ABOVE PLINTH BEING CONSTRUCTED